Causes of Delay in Khuzestan Steel Company Construction Projects

  • Saeb, Sajjad (Department of Civil Engineering, Ahvaz Branch, Islamic Azad University) ;
  • Khayat, Navid (Department of Civil Engineering, Ahvaz Branch, Islamic Azad University) ;
  • Telvari, Abdulrasoul (Department of Civil Engineering, Ahvaz Branch, Islamic Azad University)
  • Received : 2016.09.10
  • Accepted : 2016.11.25
  • Published : 2016.12.30

Abstract

Construction project is a competitive business with high risk especially in developing countries like Iran which faces with many problems such as delay and time and costs increases. Thus, the first priority here is to determine the causes of prolongation of construction projects and to evaluate their importance. Khuzestan Steel Company (KSC) has made important contribution to the projects in Iran and in turn is required to finish them on time. In this study, an attempt was made to investigate the causes of delay in implementation of construction projects held by this company. Data was collected through questionnaire distributed among the sample including 10 owners, 10 consultants and 15 con-tractors. Accordingly, participants rated the causes in the questionnaire so the most important priorities of each area were specified using TOPSIS method. The results showed that according to the employers, consultants and contractors' viewpoints, the most important reason for delays in construction projects of KSC is related to the financial matters. Hence, according to the results obtained, causes for delays in the company's projects are largely related to the drilling permits and long administrative cycle to renew them. Besides, continuous production of steel in this company is another reason to delays of construction projects.

Keywords

References

  1. Aibinu, A. and Odeyinka, H. (2006), Construction delays and their causative factors in Nigeria, J. Constr. Eng. Manage, 132(7), 667-677. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667)
  2. Al-Kharashi, A. and Skitmore, M. (2009), Causes of delays in Saudi Arabian public sector construction projects, Construction Management and Economics, 27(1), 3-23. https://doi.org/10.1080/01446190802541457
  3. Assaf, S. A. and Al-Hejji, S. (2006), Causes of delay in large construction projects, International Journal of Project Management, 24, 349-357. https://doi.org/10.1016/j.ijproman.2005.11.010
  4. Aziz, R. (2013), Ranking of delay factors in construction projects after Egyptian revolution, Alexandria Eng. J., 52(3), 387-406. https://doi.org/10.1016/j.aej.2013.03.002
  5. Aziz, R. F. and Abedel-Hakam, A. A. (2016), Exploring delay causes of road construction projects in Egypt, Alexandria Engineering Journal, In Press.
  6. Chan, D. W. M. and Kumaraswamy, M. M. (2002), Compressing construction duration: lessons learned from Hong Kong building projects, International Journal of Project Management, 20(8), 23-35. https://doi.org/10.1016/S0263-7863(00)00032-6
  7. Ezeldin, A. and Abdel-Ghany, M. (2013), Causes of construction delays for engineering projects: an Egyptian perspective, AEI, 54-63.
  8. Frimpong, Y., Oluwoye, J., and Crawford, L. (2003), Causes of delay and cost overruns in construction of groundwater projects in a developing countries: Ghana as a case study, International Journal of Project Management, 21, 321-326. https://doi.org/10.1016/S0263-7863(02)00055-8
  9. Golenko-Ginzburg, D., Gonik, A., and Laslo, Z. (2003), Resource constrained scheduling simulation model for alternative stochastic network Projects, Mathematics and Computers in Simulation, 63(2), 105-117. https://doi.org/10.1016/S0378-4754(03)00050-8
  10. Habibi, A., Izadyar, S., and Sarafrazi, A. (2014), Fuzzy Multi-Criteria Decision Making, Published by the inscription Gill. (In Persian).
  11. Hamzah, N., Khoiry, M. A., Arshad, I., Badaruzzaman, W. H. W., and Tawil, N. M. (2012), Identification of the causes of construction delay in Malaysia, World Acad. Sci., Eng. Technol., WASET. Int. Journal of Civ.Sci. Eng., 6(12), 578-583.
  12. Hasseb, M., Xinhai-Lu, A., Bibi, M., and Dyian, W. R. (2011), Problems of projects and effects of delays in the construction industry of Pakistan, Austr. Journal of Bus. Manage. Res., 1(5), 41-50.
  13. James, G. and Zack, J. R. (2004), Schedule analysis is there agreement?, Presentation, 5-6.
  14. Kaliba, C., Muya, M., and Mumba, K. (2009), Cost escalation and schedule delays in road construction projects in Zambia, International Journal of Project Management, 27(3), 522-531. https://doi.org/10.1016/j.ijproman.2008.07.003
  15. Kamikg, P. F., Olomolaiye, P. O., Gray, D., Holt, F., and Harris, C. (1997), Factors influencing construction time and cost overruns on high-rise projects in Indonesia, Construction management and economics, 83-94.
  16. Khanzadi, M., Afandizadeh Zargari, S. H., and Abrishamchi, I. (2011), Estimated delay in the construction of road construction projects due to weather conditions using analyzing fuzzy-probability, Transportation Journal, 8(3), 211-224.
  17. Mansfield, N., Ugwu, O., and Doran, T. (1994), Causes of delay and cost overruns in Nigerian construction projects, International Journal of Project Management, 12(1), 254-260. https://doi.org/10.1016/0263-7863(94)90050-7
  18. Marzouk, M., El-Dokhmasey, A., and El-Said, M. (2008), Assessing construction engineering-related delays: Egyptian perspective, Journal of Professional Issues in Engineering Education and Practice, 134(2), 315-326. https://doi.org/10.1061/(ASCE)1052-3928(2008)134:3(315)
  19. Menesi, W. (2007), Construction delay analysis under multiple baseline updates, A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied Science in Civil Engineering.
  20. Mola'ie, F. and Ghazanfari Nia, J. (2009), Investigating of delay causes in construction projects, Management publication. 6th ed., 314(7).
  21. Ndekugri, I., Braimah, N., and Gameson, R. (2008), Delay analysis within construction contracting organizations, The Journal of Construction Engineering and Management, ASCE, 134(9), 692-700. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(692)
  22. Odeh, A. and Battaineh, H. (2002), Causes of construction delay: traditional Contracts, International Project Management, 20(1), 67-73. https://doi.org/10.1016/S0263-7863(00)00037-5
  23. Ogunlana, S. O., Promkuntong, K., and Jearkjirm, V. (1996), Construction delays in a fast-growing economy: comparing Thailand with other economies. Int. J. Project Manage, 14(1), 37-45. https://doi.org/10.1016/0263-7863(95)00052-6
  24. Ruqaishi, M. and Bashir, H. (2015), Causes of delay in construction projects in the oil and gas industry in the Gulf Cooperation Council countries: a case study, Journal of Manage. Eng., 31(3).
  25. Sambasivan, M. and Soon, Y. (2007), Causes and effects of delays in Malaysian construction industry, International Project Management, 25(2), 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007
  26. Schumacher, L. (1995), Quantifying and apportioning delay on construction projects, J. Cost Eng, 37, 11-13.
  27. Thomas Ng, S. and Tang, Z. (2010), Labour-intensive construction sub-contractors: Their critical success factors, International Journal of Project Management, 28, 732-740. https://doi.org/10.1016/j.ijproman.2009.11.005
  28. Trohid, S. A. (2004), Setting methodology to determine the activities portion in creating projects delay for separate administrators, Master dissertation, Industry Engineering course, Amir-Kabir Industrial Uniersity, 160.
  29. Williams, T. (2003), Assessing extension of time delays on major projects, International Project Management, 21(1), 19-26. https://doi.org/10.1016/S0263-7863(01)00060-6
  30. Yang, J. B. and Wei, P. R. (2010), Causes of delay in the planning and design phases for construction projects, Journal of Architectural Engineering, 16(3), 80-83. https://doi.org/10.1061/(ASCE)1076-0431(2010)16:2(80)

Cited by

  1. The top 10 universal delay factors in construction projects vol.11, pp.3, 2018, https://doi.org/10.1108/IJMPB-05-2017-0052
  2. Major Factors Causing Delay in the Delivery of Manufacturing and Building Projects in Saudi Arabia vol.9, pp.4, 2019, https://doi.org/10.3390/buildings9040093
  3. A systemic inquiry into the delay factors in South African electrical distribution projects vol.12, pp.3, 2016, https://doi.org/10.1108/ijmpb-07-2018-0122
  4. Delay Causes and Emerging Digital Tools: A Novel Model of Delay Analysis, Including Integrated Project Delivery and PMBOK vol.9, pp.9, 2016, https://doi.org/10.3390/buildings9090191
  5. Study on the factors of delay in construction works vol.21, pp.3, 2016, https://doi.org/10.1590/s1678-86212021000300536
  6. Causes of Problems in Post-Disaster Emergency Re-Construction Projects-Iraq as a Case Study vol.27, pp.1, 2016, https://doi.org/10.1177/1087724x21990034