Abstract
Recently, a number of evaluation studies on availability of plant were carried out. This study was conducted to verify of the reliability of a simulation with some variable such as configuration of process, failure probability density function and the number of iteration times for the natural gas liquefaction plant. The error rate of the KICT-RAM solution was evaluated as 0.03~1.79% compared with the result of the MAROS(commercial solution). And the error-rate change was observed in the range of 0.03~1.75 on the condition of the iteration times as 30, 100, 250. As a result the plant availability evaluation approach of KICT-RAM solution was verified as reasonable. However, the careful approach was required to use the solution because the error-rate increased according to iteration times change.