Study on Improvement of Cost Calculation Method in Construction less than One Day Workload

1일 작업량 미만 공사의 공사비 산정 방식의 개선방안에 관한 연구

  • Shin, Dae-Woong (Department of Architectural Engineering, Kyonggi University) ;
  • Lee, Young-Do (Department of Architectural Engineering, Kyungdong University) ;
  • Shin, Yoonseok (Department of Plant.Architectural Engineering, Kyonggi University) ;
  • Kim, Gwang-Hee (Department of Plant.Architectural Engineering, Kyonggi University) ;
  • Yoo, Sangrok (Kyonggi-Do Branch, Korean Specialty Contractors Association) ;
  • Park, Wonjun (Kyonggi-Do Branch, Korean Specialty Contractors Association)
  • Received : 2014.08.04
  • Accepted : 2014.08.29
  • Published : 2014.10.20

Abstract

Standard production unit system and historical cost data are the most typical data base for calculating budget price in construction. However, these construction cost estimation methods are difficult to calculate proper construction cost because definition, additional allowance or modification criteria is not clear in construction within one day. Therefore, this study identifies problems for standard production unit system and historical cost data and suggests the improvements for them. For the objectives, this study analyzes frequency after implementing survey for 44 specialty contractors in placing at kyeonggi-province. As the results of the study, labor costs in standard production unit system and equipment costs in historical cost data and in construction of pavement and maintenance by project type was exceeded at most high rate against construction cost estimation methods. Based on this result, standard production unit system and historical cost data need to be modified by three improvements such as classification by project scale. These will be baseline data for improvement of construction cost estimation methods for less than one day workload.

표준품셈과 실적공사비 적산방식은 건설공사의 예정가격을 산정하는 가장 대표적인 기준자료이다. 하지만 이러한 공사비 산정방식은 1일 작업량 미만의 작업에서 정의, 할증 또는 보정기준 등이 명확하지 않아 적정 공사비의 산정이 어려운 실정이다. 따라서 본 연구는 1일 작업량 미만의 작업에서 표준품셈과 실적공사비의 문제점을 파악하고 이에 대한 개선방안을 제시하고자 한다. 이를 위해 본 연구에서는 경기도내 44개의 전문건설업체에 대하여 설문조사를 실시하여 빈도분석을 하였다. 본 연구를 통하여 표준품셈에서는 인건비, 실적공사비에서는 장비비, 공종별로는 도로포장 및 유지공사의 장비비가 각각 가장 높은 비율로 초과되었다는 결과를 도출하였다. 결과를 바탕으로 표준품셈과 실적공사비는 공사의 규모에 따른 구분 등 각각 3가지의 개선이 필요하다. 본 연구의 결과는 1일 작업량 미만의 작업에서 공사비 산정 제도의 개선을 위한 기초자료로 활용될 수 있을 것이다.

Keywords

References

  1. Hyun CT, Ji SM, Park SH. A comparison of construction cost data based on daily production rates. Proceedings of Spring Annual Conference of the Architectural Institute of Korea; 2011 Apr 29-30; Seongnam, Korea. Seoul (Korea): Architectural Institute of Korea; 2011. p. 205-6.
  2. Kim YW, Shin WS, Son CB. An analysis on the influence factors relative to reliability of standard production unit system. Proceedings of Spring Annual Conference of the Korea Institute of Building Construction; 2011 May 20; Busan, Korea. Seoul (Korea): The Korea Institute of Building Construction; 2011. p. 187-9.
  3. Son CB, Hong SH, Kim HJ. Strategies for improving a measurement system of standard unit productivity data on construction projects. Journal of the Architectural Institute of Korea. 2010 Jun;26(6):157-66.
  4. Ha GJ, Choi MK, Yi DR, Ha MS. Improving method of historical cost data through developed countries case study. Proceedings of Annual Conference of the Architectural Institute of Korea - Region Association; 2008 Dec 3; Yangsan, Korea. Daegu (Korea): Architectural Institute of Korea - Region Association; 2008. p. 541-4.
  5. Ha GJ, Choi MK, Yi DR, Lee YS, Kang TK, Ha MS. A study on the application methods of historical data cost method by historical data analysis in construction cost. Proceedings of Annual Conference of the Architectural Institute of Korea - Region Association; 2008 Dec 3; Yangsan, Korea. Daegu (Korea): Architectural Institute of Korea - Region Association; 2008. p. 531-4.
  6. Kim OG. A study on the work crew based estimation for the application of rational construction cost [mater's thesis]. [Gyeongsan (Korea)]: Gyeongill University; 2010. 52 p.
  7. Kim DW. A study on cost data prototype based production crew through productivity analysis of form work [mater's thesis]. [Seoul (Korea)]: University of Seoul; 2010. 103 p.
  8. Cho HJ. A study on productivity analysis and comparison of breakdown cost method and work crew method focused GNR method [mater's thesis]. [Jeju (Korea)]: Jeju National University; 2011. 51 p.
  9. Ahn JS, Lee JH, Kim YS, Tae YH, Lim HS. A study on the improvement of revision process and depreciation method of the construction standard estimating system. Journal of the Architectural Institute of Korea. 2009 Aug;25(8):195-204.
  10. Lee KH, Yun JC. Characteristics of periodical changes on standard of estimated unit manpower and material of landscape architectural construction korea. Journal of the Korean Institute of Landscape Architecture. 2009 Apr;37(1):131-8.
  11. Son CB, Shin WS, Lee DE. Development of work manual for efficient enactment and/or revision of construction standard production unit system. Journal of the Architectural Institute of Korea. 2012 Dec;28(12):95-102.
  12. Jung HW. Improvement method of cost estimating based on actual unit price for small size construction project [mater's thesis]. [Jinju (Korea)]: Gyeongsang National University; 2006. 79 p.
  13. Hong SH, Shin JY, Kim CH, Lee DW. Comparative analysis on unit price based on historical cost data estimating for large and small-scale civil engineering works. Journal of the Korean Society of Civil Engineers. 2013 Jul;33(4):1707-18. https://doi.org/10.12652/Ksce.2013.33.4.1707
  14. Cho JH, Chun JY. The proper construction cost estimating method based on the actual cost data. Proceedings of Annual Conference of the Architectural Institute of Korea; 2001 Apr 28; Ansan, Korea. Seoul (Korea): Architectural Institute of Korea; 2001. p. 425-8.
  15. Kim KS, Hyun CT, Hong TH, Jo SM, Mun HS. Development of an unit cost modification model for proper actual cost data in small building construction projects. Journal of the Korea Institute of Building Construction. 2010 Feb;10(1):81-9. https://doi.org/10.5345/JKIC.2010.10.1.081
  16. Jeong KC. Problems and improvement schemes to historical cost fluctuation ratio calculation according to the escalation [mater's thesis]. [Seoul (Korea)]: Chung-Ang University; 2008. 100 p.
  17. Yang JW. A study on the evaluation model for R&D personnel managements [mater's thesis]. [Ansan (Korea)]: Hanyang University; 2013. 57 p.

Cited by

  1. Comparison between Labor Inputs by Quantity per Unit Method and by Actual Data Method in the Apartment Housing Construction Work - Focusing on Masonry Plaster Waterproofing Tile Labors - vol.16, pp.1, 2015, https://doi.org/10.6106/KJCEM.2015.16.1.110
  2. Improvements of the Bidding Process through Order Case Analysis of Specialty Construction vol.15, pp.5, 2015, https://doi.org/10.5345/JKIBC.2015.15.5.507
  3. Digital Pen System for Inputting the Actual Amount of Labor Input at Construction Site vol.16, pp.2, 2016, https://doi.org/10.5345/JKIBC.2016.16.2.133