Investigating Main Causes for Schedule Delay in Construction Projects in Bangladesh

  • Rahman, MD. Mizanur (Interdisciplinary Program of Construction Engineering and Management, Pukyong National University) ;
  • Lee, Young Dai (Department of Civil Engineering, Pukyong National University) ;
  • Ha, Duy Khanh (Interdisciplinary Program of Construction Engineering and Management, Pukyong National University)
  • Published : 2014.09.01

Abstract

Delay is the most common problem in the construction industry. It has many negative effects on project's success in terms of time, cost, quality, and safety. From the literature review, a total of thirty-five factors of delay were selected. These factors were divided into seven groups related to materials, manpower, owner, consultant, contractor, construction, and external problems. This study was carried out to identify the main causes of delay for a construction project through their importance level. The importance level was determined based on the frequency of occurrence and severity of impact. The structured questionnaire has distributed to the respondents who have much experience in construction management in Bangladesh. The results of analysis indicated that top five factors of construction delay according to their level of importance are: (1) price of construction materials increased very rapidly, (2) political situation (revolution/ public strikes), (3) shortages of skilled workers, (4) poor site management and supervision by contractor, (5) incompetent/ immature subcontractors. These findings of this study are expected to be significant contributions to Bangladesh construction industry in controlling current performance of project on time overrun.

Keywords

References

  1. H. A. Rahman, M. A. Berawi, A.R. Berawi, O. Mohamed, M. Othman, I.A. Yahya, "Delay mitigation in the Malaysian construction industry." Journal of Construction Engineering Management, vol. 132, no. 2, pp.125-133, 2006. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:2(125)
  2. N.K. Acharya, Y.D. Lee, H.M. Im, "Investigating Delay Factors in Construction Industry: A Korean perspective." Korean Journal of Construction Engineering and Management, vol. 10, no. 6, pp. 177-190, 2006.
  3. A.A. Aibinu, A. Odeyinka, "Construction Delays and their Causative Factors in Nigeria." Journal of Construction Engineering Management, ASCE, vol. 132, no. 7, pp. 667-677, 2006. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667)
  4. R.T.M. Akogbe, X. Feng, J. Zhou, "Importance and Ranking Evaluation of Delay Factors for Development Construction Projects in Benin." KSCE Journal of Civil Engineering, vol. 17, no. 6, pp. 1213-1222, 2013. https://doi.org/10.1007/s12205-013-0446-2
  5. MD. A. Hasan, "Evaluation of Building Construction Management in Sylhet City, Bangladesh" KICEM Journal of Construction Engineering and Project Management, vol. 2, no.2, pp. 40-47, 2012. https://doi.org/10.6106/JCEPM.2012.2.3.040
  6. A.H. Al-Momani, "Construction Delay: A Quantitative Analysis." International Journal of Project Management, vol. 18, no. 1, pp. 51-59, 2000. https://doi.org/10.1016/S0263-7863(98)00060-X
  7. S.A. Asaaf, M. Al-Khalil, "Causes of Delay in Large Building Construction Projects." International Journal of Project Management, vol. 11, no. 2, pp. 45-50, 1995.
  8. S.A. Asaaf, S. Al Hejji, "Causes of Delay in Large Construction Projects." International Journal of Project Management, vol. 24, pp. 349-357, 2006. https://doi.org/10.1016/j.ijproman.2005.11.010
  9. J.R. Baldwin, J.M. Manthei, "Causes of Delay in the Construction Industry." Journal of Construction Division, ASCE, vol. 97, no. 2, pp. 177-187, 1971.
  10. D.W. Chan, M.M. Kumaraswamy, "A Comparative Study of Causes of Time Overruns in Hong Kong Construction Projects". International Journal of Project Management, vol. 15, no. 1, pp. 55-63, 1997. https://doi.org/10.1016/S0263-7863(96)00039-7
  11. H. Doloi, A. Sawhney, K.C. Iyer, S. Rentala, "Analyzing Factors Affecting Delays in Indian Construction Projects." International Journal of Project Management, Vol. 30, 479-489, 2012. https://doi.org/10.1016/j.ijproman.2011.10.004
  12. M.E. El-Razek, H.A. Bassioni, A.M. Mobarak, "Causes of Delay in Building Construction Projects in Egypt." Journal of Construction Engineering and Management, ASCE, vol. 134, no. 11, pp. 831-841, 2008. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831)
  13. A.S. Ezeldin, M. Abdel-Ghany, "Causes of Construction Delays for Engineering Projects in the Middle-East: An Egyptian Perspective." AEI, ASCE, pp. 53-62, 2013.
  14. A.S. Faridi, S.M. Sayegh, "Significant Factors Causing Delay in the UAE Construction Industry." Construction Management and Economics, vol. 24, no. 11, pp. 1167-1176, 2006. https://doi.org/10.1080/01446190600827033
  15. Y. Frimpong, J. Oluwoye, L. Crawford, "Causes of Delay and Cost Overruns in Construction of Groundwater Projects in a Developing Countries; Ghana as a Case Study." International Journal Project Management, vol. 21, pp. 321-326, 2003. https://doi.org/10.1016/S0263-7863(02)00055-8
  16. M. Ibrahim, A. Bruland, N. Dmaidi, "Causes of Delay in Road Construction Projects." Journal of Management in Engineering, ASCE, vol. 28, no. 3, pp. 300-310, 2012. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000096
  17. P. Kaming, P. Olomolaiye, G. Holt, F. Harris, "Factors Influencing Construction Time and Cost Overruns on High-Rise Projects in Indonesia." Construct Management and Economics, vol. 15, pp. 83-94, 1997. https://doi.org/10.1080/014461997373132
  18. P.A. Koushki, K. Al-Rashid, N. Kartam, "Delays and Cost Increases in the Construction of Private Residential Projects in Kuwait." Construction Management and Economics, Vol. 23, no. 3, pp. 285-294, 2005. https://doi.org/10.1080/0144619042000326710
  19. L. Le-Hoai, Y.D. Lee, J.Y. Lee, "Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with other Selected Countries." KSCE Journal of Civil Engineering, Vol. 12, no. 6, pp. 367-377, 2008 https://doi.org/10.1007/s12205-008-0367-7
  20. T.Y. Lo, I.W.H. Fung, K.C.F. Tung, "Construction Delays in Hong Kong Civil Engineering Projects." Journal of Construction Engineering Management, ASCE, vol. 132, no. 6, pp. 636-649, 2006. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:6(636)
  21. M.M. Marzouk, T.I. El-Rasas, "Analyzing Delay Causes in Egyptian Construction Projects." Journal of Advanced Research, 2013.
  22. M. Sambasivan, Y.W. Soon, "Causes and Effects of Delays in Malaysian Construction Industry." International Journal of Project Management, vol. 25, pp. 517-526, 2007. https://doi.org/10.1016/j.ijproman.2006.11.007
  23. MD.R.R. Shaon, "Investigation of Construction Delay of Real Estate Companies in Dhaka City", Bachelor of Science thesis, Bangladesh University of Engineering and Technology, Dhaka, Bangladesh, 2012.

Cited by

  1. The top 10 universal delay factors in construction projects vol.11, pp.3, 2018, https://doi.org/10.1108/IJMPB-05-2017-0052