Analysis of Crew Productivity and Influence Factor for Reinforce Concrete Work in the Nuclear Power Plant

원자력발전소 철근콘크리트 공종의 작업조 생산성 및 영향요인 분석

  • 허영기 (부산대학교 건축공학과) ;
  • 손창백 (세명대학교 건축공학과) ;
  • 임진호 (부산대학교 건축공학과 대학원) ;
  • 안영철 (부산대학교 건축공학과) ;
  • 오재훈 (부산대학교 건축공학과 대학원)
  • Received : 2014.09.04
  • Accepted : 2014.12.02
  • Published : 2014.12.30

Abstract

Few studies on crew productivity has been conducted, although the data is significant for time and cost estimation. Crew productivity data was collected for over 9 months from a nuclear power plant and analysed in order to identify factors driving the productivity. It was revealed that the crew productivity of form work and rebar work was 45.64($m^2/crew{\cdot}day$), 2.93($t/crew{\cdot}day$) on average respectively. The study also found that 'nightwork' and 'total work amount completed' were identified as drivers for the both works. Moreover, 'complexity of daywork' can lead to crew productivity deduction of about 77% for form-work and 81% for rebar-work. The productivity data collected and factors affecting the productivity will help managers to plan and control their similar works. This study will also be beneficial for those performing related studies.

Keywords

Acknowledgement

Supported by : 한국연구재단

References

  1. 허영기, 김창완, 송종철 (2004), Data Collection Methodology of Activity Production Rates For Contract Time Determination, 한국건설관리학회, 5권, 1호, p.p. 107-113
  2. 조영석 (2002), 원자력발전소의 효율적인 시공관리를 통한 생산성 향상, 한국건설관리학회, 3권, 2호(통권10호), p.p. 9-13.
  3. Allmon, E., Haas, C. T., and Borcherding, J. D. (2000), U.S. Construction Labor Productivity Trends, 1970-1998, Journal of Construction Engineering and Management, Volume 126, Issue 2, p.p. 97-104. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:2(97)
  4. J. T. O'Connor, Y. K. Huh (2005), Crew Production Rates for Contract Time Estimation: Bent Footing, Column, and Cap of Highway Bridges, Journal of Construction Engineering and Management, Journal of Construction Engineering and Management, Volume.131, Issue.9, p.p.1013-1020. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:9(1013)
  5. 이우방, 문병석 (2000), 원전 건설 생산성 향상을 위한 정보 시스템 구축, 원자력산업 20권 12호(통권214호), p.p. 32-38.
  6. 김우주(2001), 지식 기반 플랜트건설 공정계획 시스템의 개발, 한국지능정보시스템학회논문지, p.p. 81-95.
  7. 문성우, 박상천, 권기남 (2009), 초기 사업단계에서 표준공정모델을 이용한 가스 플랜트 공사의 개략적 공사기간 산정, 한국건설관리학회, 10권, 2호, p.p. 26-33.
  8. 장명훈, 이재용, 이광호, 이현수 (1999), "鐵骨工事日程및 費用管理시스템의 開發", 대한건축학회 논문집, 제15권 제7호
  9. 박영석 (2002), "住商複合建物의 鐵骨設置工程計劃 및 施工生産性分析", 대한건축학회 학술발표논문집, 제22권 제2호
  10. 이은석 외 1인 (2003), "鐵骨工事現場의 勞務實態에 관한 硏究", 대한건축학회 학술발표논문집, 제23권 제1호
  11. 손정욱, 윤준선, 백준홍 (2003), "건설공사 생산성 측정방법에 관한 연구", 대한건축학회 논문집 제19권 제10호
  12. 손창백, 이덕찬(2006), 공동주택 건축공사의 생산성 향상용인 선정 및 적용성 분석, 대한건축학회, 21권, 4호(통권 198호), p.p. 133-140.
  13. 김경훈, 김경환, 이윤선, 김재준(2007), 철골골조공사의 실시간 진도관리 시스템 구축에 관한 연구, 한국건설관리학회, 정기학술발표대회 논문집, p.p. 886-891
  14. 문우경, 한성훈, 김예상, 김영석, 김상범 (2006), "건설 생산성 정보 관리를 위한 생산성 영향요인 분석", 한국건설관리학회 학술발표대회 논문집
  15. 손창백, 이덕찬 (2005), "공동주택 건축공사의 생산성 향상요인 선정 및 적용성 분석", 대한건축학회 논문집 제21권 제4 호