Problems Related to Construction and Building Materials in Libya

  • Salah, Abuzaid (CCIR: Centre for Construction Innovation Research, School of Science and Engineering (SSE), Teesside University) ;
  • Bloomer, Steve (CCIR: Centre for Construction Innovation Research, School of Science and Engineering (SSE), Teesside University)
  • Published : 2014.12.01

Abstract

The broad aim of this paper is to provide a detailed understanding of the post-war problems associated with materials for reconstruction in Libya, and to identify key problems and obstructions. Theoretical and empirical studies are being conducted in Libya. The theoretical study focuses on materials for construction and the key issues such as sources, transport and storage of materials, as well as their impact on the national economy, the nation's socio-economic development and the environment. This empirical study employed questionnaires, observations and a series of interviews with researchers, academics, suppliers and manufacturers, supported by the researcher's three decades of experience of working in the construction industry and its associated processes and operations. The empirical study illustrated that materials for post-disaster reconstruction in Libya suffer from external problems related to policies and decision-making in terms of availability of materials, fluctuation of prices of materials, specifications, building codes, legislation and regulations, and internal problems related to the construction and building material's key players: construction companies, consultancy firms, manufacturers and suppliers.

Keywords

References

  1. ACC, The company's production. Internal ACC report. Unpublished, 2004.
  2. Aibinu, A. and Jagboro, G., "The effects of construction delays on project delivery in Nigerian construction industry", International Journal of Project Management, 20(8), pp. 593-599, 2002. https://doi.org/10.1016/S0263-7863(02)00028-5
  3. Al-Aghbari, W., Abdul Kadir, M., Salim, A. and Ernawati, "The significant factors causing delay of building construction projects in Malaysia", Engineering, Construction and Architectural Management, 14(2), pp. 192-206, 2007. https://doi.org/10.1108/09699980710731308
  4. Al-Tabtabai and Hashem M., "Causes for delays in construction projects in Kuwait", Engineering Journal of Qatar University, Vol. 15, pp.19-37, 2002.
  5. Asnaashari, E., Knight, A., Hurst, A. and Farahani, S.S., "Causes of construction delays in Iran: project management, logistics, technology and environment". Procs 25th Annual ARCOM Conference, Association of Researchers in Construction Management, 897-906, 2009. Nottingham, 7-9 September 2009 [on line]. Available at: https://www.google.co.uk/?gws_rd=cr&ei=Z_BLUuiWJvHu0gWumoCQDA#q=causes+of+construction+ delays+in+iran+project+management+logistics+technology+and+environment. (Accessed: 24 September 2013).
  6. Doxiadis, A. (1964) Housing in Libya: problems, policies, programmes. Volume two. Athens: Doxiadis Associates.
  7. Elmahmudi, A. (1996) The Islamic Cities in Libya: planning and architecture. Berlin: Peter Lang.
  8. Frimpong, Y., Oluwoye, J. and Crawford, L. (2003) "Causes of delay and cost overruns in construction of groundwater projects in a developing countries: Ghana as a case study", International journal of project management, 21 (5), pp. 321-326. https://doi.org/10.1016/S0263-7863(02)00055-8
  9. GAEP (2010) Estimating of maintenance works of sewage treatment plants. Internal GAEP report. Unpublished.
  10. GCP (2000) The general framework of the social and economic development plan (2001-2005). Internal GCP report. Unpublished.
  11. GCP (2003) The follow-up report on the implementation of the development budget for the financial year 2002: an assessment of the general economic sectors. Internal GCP report. Unpublished.
  12. GPCPBC (1998) An evaluation of the cement industry in Libya. Tripoli: Libyan government printers.
  13. Grifa, M. (2008) Construction industry in Libya: PhD thesis. Newcastle University.
  14. Gruneberg, S. and lve, G. (2000) The economics of the modern construction firm. London: Palgrave Macmillan.
  15. Harrison, S. and Sinha, B. (1995) "A study of alternative building materials technologies for housing in Bangalore, India", Construction and Building Materials, 9(4), pp. 211-217. https://doi.org/10.1016/0950-0618(95)00012-5
  16. Hellman, J. and Gadde, L. (1996) "Information technology and the efficiency of materials supply: the implementation of EDI in the Swedish construction industry", European Journal of Purchasing & Supply Management, 2(4), pp. 221-228. https://doi.org/10.1016/S0969-7012(96)00018-4
  17. Joffe, E. and McLachlan, K. (1982) Social & economic development of Libya. Cambridgeshire: Middle East and North African Studies Press.
  18. Kaming, P., Olomolaiye, P., Holt, G. and Harris, F. (1998) "What motivates construction craftsmen in developing countries? A case study of Indonesia", Building and Environment, 33(2-3), pp.131-141. https://doi.org/10.1016/S0360-1323(97)00041-3
  19. Iarossi, G. (2006) The power of survey design: a user's guide for managing surveys. Interpreting results and influencing respondents. Washington D C: The World Bank.
  20. Libyan Cabinet (2009) The follow-up report on under-construction projects. Internal Libyan Cabinet report. Unpublished.
  21. Libyan Cabinet (2011) Estimating of reconstruction works. Internal Libyan Cabinet report. Unpublished.
  22. Libyan Government (1969) Libya's constitution: articles 6, 7, 8 and 9. Tripoli: Libyan government printers.
  23. Libyan Government (1977) Law no. 343 of the year 1977, regarding the limitation of construction contracts with public construction companies. Tripoli: Libyan government printers.
  24. Libyan Government (1984) Law gave tenants the rights and support to become owners of the houses that they rented. Tripoli: Libyan government printers.
  25. Ministry of Housing (1982) Decision and regulations to prevent private construction companies from carrying out their activities. Tripoli: Libyan government printers.
  26. Ministry of Housing (1985) Libyan citizen has the right to build and own only one house. Tripoli: Libyan government printers.
  27. Ministry of Housing (2010) Shortage of housing units. Internal Ministry of Housing report. Unpublished.
  28. Ministry of Planning (2006) Construction sector's contribution to the Libya GDP. Internal Ministry of Housing report. Unpublished.
  29. Neuman, W.L. (2009) Social research methods: qualitative and quantitative approaches. 7th edn. Boston: Pearson.
  30. Ngab, A. (2007) "Libya, the construction industry- an overview" International Workshop - Cements based Materials and Civil Infrastructure, Need University of engineering and technology, Karachi, 10 December 2007. [Online]. Available at: http://enpub.fulton.asu.edu/cement/CBM_CI/TOPICS.HTM. (Accessed: 21 October 2012).
  31. NOUP (2006) The gap in the housing sector. Tripoli: Macmillan.
  32. Ogunlana, S. and Promkuntong, K. (1996) "Construction delays in a fast-growing economy: Comparing Thailand with other economies", International Journal of Project Management, 14(1), pp. 37- 45. https://doi.org/10.1016/0263-7863(95)00052-6
  33. Plummer, K. (2004) "On the diversity of life documents", in Seale, C. Social research methods: a reader. London: Routledge. pp. 282-290.
  34. Rasheed, K. (2004) "Water needs and population growth in the Sahl Al-Jafara" Proceedings of the first National conference on population and development in Libya. Tripoli, 12-22 November. Unpublished.
  35. RCBMC (2000) Annual report of the prices of construction materials in the Libyan market. Tripoli: Libyan government printers.
  36. Robertson, D. and McLaughlin P. (1996) Looking into Housing: A Practical Guide to Housing Research. Coventry.
  37. Coventry: Chartered Institute of Housing Policy and Practice.
  38. Sharp, J. A., Peters, J. and Howard, K. (2002) The management of a student research project. Hants: Gower Ltd.
  39. Shebob A. (2012) Development of a methodology for analysing and quantifying delay factors affecting construction projects in Libya. PhD thesis. Teesside University.
  40. Tumi, S., Omran, A. and Pakir, A. (2009) "Causes of delay on construction industry in Libya" The international conference on economies and administration, University of Bucharest, Bucharest, Romania, 14 to 15 November 2009.
  41. UNCCD (2001) Global alarm: dust and sandstorms from the world's dry lands. Beijing: United Nations.
  42. Waniss, O. and Erling, K. (2007) The Libyan economy: economic diversification and international repositioning. Heidelberg: Springer.