Analysis on Emergency Power Supplies in Buildings and a Model for Safe Operation of the Emergency Power System

건축물의 비상전원 적용실태 및 자가발전설비의 안전 운전 모델에 관한 연구

  • Lee, Won-Kang (Department of Fire Safety Engineering, Jeonju University) ;
  • Choi, Chung-Seog (Department of Fire Safety Engineering, Jeonju University)
  • 이원강 (전주대학교 소방안전공학과) ;
  • 최충석 (전주대학교 소방안전공학과)
  • Received : 2012.01.26
  • Accepted : 2012.06.11
  • Published : 2012.06.30

Abstract

The purpose of this paper is to present a model for operating an emergency power system(EPS) that can secure a sufficient power supply used in case of a fire by analyzing the status of power supplies for emergency and firefighting operations. Investigations on the one of the causes of the operational failure of firefighting systems show evidence of EPS. Generally, when power to a building is interrupted, EPS supplies the emergency load(excepted firefighting load) first. When a power outage and a fire occur simultaneously, the EPS must be able to supply both the emergency load and the firefighting load, especially the firefighting load to the end. However, in order to save construction costs, emergency power generators in apartment, commercial, and business buildings can satisfy only one of the required loads. In cases like this, when a power outage and a fire occur simultaneously, there is a danger of firefighting equipment not operating due to insufficient power supply from the emergency generator. Therefore, an EPS must have a reserved firefighting power that can supply both the firefighting and the emergency load. Such EPS, when faced with a danger of an overload, will shut down the supply to all or part of the emergency load, thus securing a continuous power supply to the firefighting equipment. The generator power system with reserved firefighting power (RFP) will also have an indicator to show that the selective control is being used. General power generation systems for emergency load and firefighting load were found to have a demand factor of 50-60% with a lump. However, when installing an EPS, the builders must choose the higher demand factor suggested according to the official approval demand factor of the building.

Keywords

References

  1. 한국전력공사, "한국전력통계(2010) 제80호", pp. 16-17, 2011.
  2. (사)한국소방안전협회, 홈페이지 제공, 국가화재 안전기준, 2012.
  3. 소방방재청, "2008년 국가화재통계", 2008.
  4. LH공사, "전기.정보통신설비설계지침 예비전원 설비 1404", pp. 95-100, 2010.
  5. 법제처, 소방시설 설치 및 안전관리에 관한 법률 제25조(자체점검), 국가법령정보
  6. 소방방재청 공문, "비상발전기 및 부속실 제연설비 운영지침 시달", 방호과-4278, 2010.10.1
  7. 스프링클러설비의 화재안전기준(NFSC-103), 소방방재청고시 제2011-27호 (2011.11.24)
  8. 최홍규, "전력사용시설물 설비 및 설계", pp. 189- 213, 성안당, 2001.
  9. 조성훈, "자가발전설비의 설계 및 시공 핸드북", 도서출판 신기술, pp. 3-6, 63-68, 2003.
  10. 전기설비기술기준, 지식경제부 고시 제2011-1호, 2011.5
  11. NFPA, NFPA 110, "Emergency Power Generation", 2001.
  12. NFPA, NFPA 70, "National Electric Code", 2001.
  13. 건축전기설비설계기준, 국토해양부 공고 제2011-1198호 (2011.12.15)
  14. 日本內燃力發電協會, "自家用發電設備の 出力算定法 (NEGA D 201)", 2007.
  15. 내선규정, 사단법인 대한전기협회, 내선규정 부록 2005.
  16. 김정태, 이욱, "공동주택의 비상발전기 용량산정 방식에 관한 고찰", 조명.전기설비 학회지 제10권 제4호, 1996. 8
  17. 이원강, "국가화재안전기준의 비상전원 개정기준 적용", 소방기술사 전문교육, 과학기술진흥기금 '11년도 기술사 기술향상 교육훈련사업, 기술사 CPD, 한국기술사회 2011. 12. 09
  18. 이원강, "비상전원 기준 충족을 위한 소방전원 보존형 발전기 적용", (사)한국소방안전협회, 소방기술정보 제32권, pp. 12-14, 2010