A Model for Assessing Maximum Overtime Rate in Labor Subcontracting Practices

  • Nassar, Khaled (The American University in Cairo, Department of Construction and Architectural Engineering) ;
  • Hosny, Ossama (The American University in Cairo, Department of Construction and Architectural Engineering)
  • Received : 2011.07.22
  • Accepted : 2012.01.31
  • Published : 2012.06.01

Abstract

Despite the rapid development in the construction industry due to the changing new technologies, many projects still fail to meet target deadlines. Shortage in manpower and skilled laborers is one of the main reasons for such delays. Markets with high economic growth and economic expansion (such as Gulf Countries in the Middle East) may have pronounced labor the shortages. Labor subcontracting practices are used sometimes to increase production rates and meet project deadlines. This paper explains and analyses labor subcontracting practices currently being used in many places around the world (and especially in the Gulf Countries) and in particular defines a maximum overtime rate for laborers in the laborer-subcontracting method ensuring that the contractor gains both the time saved during overtime and also reduces the cost per unit produced. The mathematical model used formalizes a closed-form equation for overtime pay in similar situations and as such can be applicable worldwide. Data was collected from representative projects that employed such practices from various trades. Validation of the model and formula has been tested successfully by analyzing historic data. The results prove that contractors often do not reach the optimum use of their practices resulting in a higher cost per unit. The presented model and the analysis should be of interest to many contractors currently involved in the practice or considering its use and to those who wish to find new methods that would help in eliminating as much wastes as possible by allocating their resources in the most efficient way.

Keywords

References

  1. AMANA, Project Costing Manual, AMANA construction company, Dubai, UAE, 2008.
  2. M.R. Anderberg, "Cluster Analysis for Applications", Academic Press, NY, New York, 1973.
  3. Business Round Table, Report (BRT) C-2, "Scheduled Overtime Effect on Construction Projects", Business Round Table, New York, N.Y, 1990.
  4. Construction Industry Institute (CII), "Effects of Scheduled Overtime on Labor Productivity: A Quantitative Analysis", 2nd ed., Electrical Construction, 1994.
  5. Gulf News, "Amnesty has achieved its Goals, says Official", Gulf news Online: Immigration & Visas, http://archive.gulfnews.com/indepth/amnesty/mainstorey/10166474.html, 2007.
  6. A.S. Hanna, C.S. Taylor, K.T. Sullivan, "Impact of extended overtime on construction labor productivity", Journal of Construction Engineering and Management, ASCE, vol. 131, no. 6, pp. 734-739, 2005. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(734)
  7. Mechanical Contractors Association of America, "Change Orders, Overtime, Productivity", Rockville, MD, 1994.
  8. National Electrical Contractors Association (NECA), "Overtime and productivity in electrical construction," 2nd ed., National Electrical Contractors Association (NECA), Bethesda, Md, 1989.
  9. A.K. Jayawardane, F.C. Harris, "Construction Productivity Management", Harlow, Longman, London, 1998.
  10. R. Mayo, K. Knutson, G. Barras, F. Pineda, "Improving Construction Productivity with Scheduled Overtime", Royal Institution of Chartered Surveyors Conference, vol. 53-II, pp. 897-900, RICS Foundation, London, 2001.
  11. R. Ditcham, "UAE Tops Region in terms of Construction Value", Gulf News October 26, 2006, http://archive.gulfnews.com/articles/06/10/26/10077598.html, 2006.
  12. H. Park, S.R. Thomas, R.L. Tucker, "Benchmarking of construction productivity" Journal of Construction Engineering and Management, vol. 131, no.7, pp. 772-778, 2005. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:7(772)
  13. H.R. Thomas, K.A. Raynar, "Scheduled overtime and labor productivity: quantitative analysis", Journal of Construction Engineering and Management, ASCE, vol. 123, no. 2, pp. 181-188, 1997. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:2(181)
  14. A. Yun, "Regulating multi-layer subcontracting to improve labour protection", http://www.ilo.org/legacy/english/protection/travail/pdf/rdwpaper17b.pdf, Last Access, January 2012.

Cited by

  1. The Productivity Improvement for Steel Framing Work Efficiency by Work Sampling and 5-minute Rating Technique vol.5, pp.1, 2015, https://doi.org/10.6106/JCEPM.2015.5.1.040