Selection of Single Point Vulnerability through the Failure Mode Effect Analysis of Equipment in Newly built Nuclear Power Plant

신규원전의 기기별 고장분석을 통한 발전정지유발기기 선정

  • Received : 2011.10.21
  • Accepted : 2012.03.23
  • Published : 2012.04.01

Abstract

For decreasing an unexpected shutdown of Nuclear Power Plants, Korea Hydro & Nuclear Power co.(KHNP) has developed Single Point Vulnerability(SPV) of NPPs since 2008. SPV is the equipment that cause reactor shutdown & turbine trip or more than 50% power rundown due to its malfunction. Newly built Nuclear Power Plants need to develop the SPV list, so performed the job which analyse equipment failure effect for SPV selection for 1 year. To develop this, Failure Mode Effect Analysis(FMEA) and Fault Tree Analysis(FTA) methods are used. As results of this analysis, about 900 equipment are selected as SPV. Thereafter those are going to be applied to Nuclear Power Plants to enhance equipment reliability.

Keywords

References

  1. Eun Chan Lee, "A Single Point Vulnerability Outline," KHNP., pp. 2, 2010.
  2. Jang Whan Na, Jin Gyu Han etc., "Development of Single Point Vulnerability (SPV) Management Scheme for OPR1000" KHNP., pp. 6-11, 2008.
  3. Jin Woo Hyun, Jin Gyu Han etc., "Final report of Single Point Vulnerability Selection for Shinkori unit 1&2" KHNP., pp. 1-9, 2011.
  4. Eun Chan Lee, Jin Gyu Han etc., "FMEA Report of Korean Nuclear Standard Plant" KHNP., pp. 1-9, 2009.
  5. Jin Gyu Han., "Presentation for Development of Maintenance Management Base Using System Function Analyses., KEPCO E&C.,pp. 20-22, 2010.

Cited by

  1. A systematic framework to investigate the coverage of abnormal operating procedures in nuclear power plants vol.138, 2015, https://doi.org/10.1016/j.ress.2015.01.013