A Study on Buckling Analysis of Portable Prestressing Device for Pretensioning PSC girders

프리텐션 방식의 PSC 거더 이동식 제작장치의 좌굴해석 연구

  • Received : 2011.11.25
  • Accepted : 2012.01.05
  • Published : 2012.01.31

Abstract

This study is a research on the buckling analysis of a portable prestressing device using finite element analysis program, ABAQUS. In order to produce 50m-span PSC girders using pretensioning method, a portable prestressing device has to endure a large jacking force about 10MN. Therefore it shall be safe and stable about the jacking force. In this study, the buckling analysis technique is developed and the buckling analysis of a portable prestressing device is performed using previous studies about the analytical model that the validity of the analytical model was demonstrated by comparing analytical results with experimental results. The stability of the device to produce 10m span PSC girders is investigated.

본 연구는 유한요소해석프로그램(ABAQUS)을 사용하여 이동식 긴장대의 좌굴해석 기법을 연구한 것이다. 50m에 달하는 프리텐션 방식의 PSC 부재를 제작하기 위해서는 약 10MN에 이르는 매우 큰 긴장력이 가해져 이동식 긴장대가 PSC 부재의 양생 전까지 이 긴장력을 저항하여야 한다. 따라서 이동식 긴장대는 하중에 대한 안전성과 좌굴에 대한 안정성을 확보하여야 한다. 이에 본 논문에서는 앞서 개발한 이동식 긴장대의 해석모델을 이용하여 좌굴해석 기법에 대해 연구하여 이동식 긴장대가 좌굴에 대한 안정성 확보 여부를 파악하고자 하였다.

Keywords

References

  1. KRTA(2005) Bridge Design Specifications, Korea Road & Transportation Association.
  2. MLTM(2008) Statistical Yearbook of Land, Transport and Maritime - Bridges and Tunnels, Ministry of Land, Transport and Maritime Affairs.
  3. MLTM(2010) Anweisung of Ministry of Land, Transport and Maritime Affairs - Roading Restrictions of vehicles, Ministry of Land, Transport and Maritime Affairs.
  4. Kim, Jang Ho, Moon, Do Young, Zi, Goang Seup, Kim, Gyuseon(2008) Dynamic Behavior of Pretensioned Concrete Member during Detensioning, KSCE(Korean Society of Civil Engineers) Journal, Vol.28, No.5A, pp.747-756.
  5. Nam, Yoo Seok, Cho, Chang Geun, Park, Moon Ho(2006) Time-Dependent Behavior Analysis of Pre-Tensioned Members Using High-Performance Concrete (HPC), KCI(Korea Concrete Institute) Journal, Vol.18, No.4, pp.479-487. https://doi.org/10.4334/JKCI.2006.18.4.479
  6. Moon, Do Young, Kim, Jang Ho, Kim, Gyu Seon, Yun, Man Geun, Zi, Goang Seup(2009) Investigation of Stress Changes in Concrete and Strands according to Cutting Order of the Strands in Pre-tensioned Concrete Slab, KCI(Korea Concrete Institute) Journal, Vol.21, No.4, pp.419-429. https://doi.org/10.4334/JKCI.2009.21.4.419
  7. Oh, Byung Hwan, Kim, Eui Sung(2000) Influencing Factors and Evaluation of Transfer Lengths in Pretensioned Prestressed Concrete Members, KSCE(Korean Society of Civil Engineers) Journal, Vol.20, No.6-A, pp.945-956.
  8. Oh, Byung Hwan, Lim, Si Nae, Choi, Young Cheol(2004) Finite Element Analysis of Transfer Length in Pretensioned Prestressed Concrete Members, KCI(Korea Concrete Institute) Journal, Vol.16, No.3, pp.293-302. https://doi.org/10.4334/JKCI.2004.16.3.293
  9. Yi, Gyu Sei, Yoon, Ki Yong, Kim, Jong Suk, Kim, Yong Huck(2011) An Experimental Fundamental Study on Development of Portable Prestressing Device for Pretensioning PSC girder, Journal of Korean Society of Hazard Mitigation, Vol.11, No. 6. pp.61-66. https://doi.org/10.9798/KOSHAM.2011.11.6.061
  10. Byeon,, Ji-Seok, Yoon, Ki Yong, Kim, Jong Suk, Kim, Yong Huck(2011) A Basic Study on the Analysis Model of Portable Prestressing Device for Pretensioning PSC girders, Journal of Korean Society of Hazard Mitigation, Vol.11, No. 6. pp.77-82.
  11. Sin, Hyun Mook(2003) Prestressed Concrete, Dongmyungsa.
  12. Jang, Sung Pil(2008) Steel Structures, Youngji Publishers.
  13. ABAQUS, Manual & Reference Manual Ver. 6.5-1, 2007.