Abstract
Since the blast vibration induced by explosives of the powder possibly provide damage of the nearby structures adjacent to the tunnel, the stability of the nearby structures should be estimated. In this study, the stability of the tunnel based on the allowable peak particle velocity of the structures as well as allowable stress of the structures presented in the concrete structural design standard was estimated with respect to the stress of the concrete lining and axial force of the rockbolt during the blasting operation at the ground surface of the pre-existing tunnel. The analyses were carried out by using $FLAC^{2D}$ which is one of the programs developed based on the finite difference method. The bending compressive stress and shear stress of the concrete lining and axial force of the rockbolt were rapidly increased when the blasting operation was conducted near the tunnel.
발파 시 폭약의 폭발로 발생되는 발파진동은 발파지역 인근의 기존 구조물에 피해를 유발시킬 수도 있으며, 이러한 경우 구조물의 안정성 검토를 필요로 한다. 본 연구에서는 기설 터널의 상부 지층 발파 시 터널의 안정성을 구조물의 허용진동속도가 아닌 콘크리트 구조설계기준에 제시된 구조물의 허용응력을 기준으로 수치해석 프로그램인 $FLAC^{2D}$를 이용하여 구조물의 발파 진동이 터널 지보재인 콘크리트 라이닝의 응력 및 록볼트의 축력에 미치는 영향을 검토하였다. 터널에 근접하여 발파가 이루어지는 경우에는 발파진동속도와 콘크리트 라이닝의 휨 압축응력과 전단응력, 록볼트의 축력은 급격히 증가하는 것으로 나타났다.