A Study on the Method of Preliminary Works Management for a Schedule Performance Management

공정이행관리를 위한 선행작업관리 시안

  • 박홍태 (공주대학교 공과대학 건설환경공학부) ;
  • 송용선 (공주대학교 공과대학 건설환경공학부)
  • Published : 2008.06.30

Abstract

It is important to know the activities itself exactly and to control the activities correctly so as to assure timely progress and the quality of any project. In order to progress smoothly in accordance with construction schedule, it is important to systematize the preliminary arrangements necessary for each process and then manage them. In this study, in order to progress smoothly the qualify and schedule management of the construction, We can make systematically preliminary works in accordance with construction schedule by the architecture construction items of the apartment house construction. We suggested important preliminary control item by the workers through experiential method of construction engineers in accordance with network schedule. should not use "we" in technical sentence.

효율적인 공정이행관리를 통해서 건설공사 일정의 불필요한 공기지연을 사전에 예방하고, 나아가 품질확보를 위하여 각 공정의 내용을 정확하게 숙지하고 관리하는 일이 중요하다. 더욱 중요한 것은 공사계획에 따른 공정이 원활하게 진행될 수 있도록 각각의 공정에 필요한 선행작업들을 체계화하여 관리하는 것이다. 이를 위하여 본 연구에서는 아파트공사를 대상으로 이정표 중심, 작업공종 중심, 활동 중심, 작업 담당자 중심으로 구분하여 선행작업관리 시안을 제시하였다.

Keywords

References

  1. 강인석, 건설공정관리학. 보문당, 2007
  2. 강인석, 이우식, 곽종민, 토목분야 공사분할체계의 정 보분류기준 모형화 연구, 대한토목학회 논문집, 2004, 6
  3. 김동성, 사전작업관리에 의한 공정관리의 효율화 방안, 주택도시연구원2000)
  4. 대한주택공사, 공사감독 실무요령. 1995
  5. 대한주택공사, 공법별 노무량 조사분석. 1994
  6. 박동원, 공정관리 과학화 연구. 대한주택공사, 1993
  7. 박홍태․이철규, 종합공정관리 전산시스템 구축시안. 대한주택공사, 1997
  8. 박찬용, 이교선, 건설정보분류 표준화 연구, 한국건설기술연구원, 1994. 12
  9. 이태식, 박종현, 토목공사의 분할체계를 통한 공사관리 합리화 방안, 한국건설기술연구원. 1991. 12