Abstract
This paper reveals both the operational situation and the cause of the error occurred in wind turbine generator system of Hangwon wind farm in Jeju island. The four wind turbines were selected for this work, and the monitored period was for six months. Wind resource in the wind farm was analyzed, and the estimated energy production was compared with the actual energy production. As a result, with a decrease of system error, the estimated energy production was in good agreement with the actual energy production. The errors occurring in components such as gearbox and hydraulic motor affected the Availability of the wind turbine. Also, poor external conditions such as a strong wind, lightning and gust caused a standstill of wind turbines.