A Study on Tunnel Excavation by Controlled Blast Vibration at Particular Environment Conditions

발파진동 제어에 의한 특수구간 터널굴착에 관한 연구

  • Published : 2000.06.30

Abstract

It was difficult to apply conventional excavation methods in some sections from Seoul to Pusan high speed rail road construction of 1 lot 2, due to highway concrete road, gas pipe, water pipe and nearby factories with automatic control system machine. To excavate safely and efficiently in these sections new blast patterns were employed within allowable blast vibration level, by test blast and controlled vibration by sequential blast. Behaviors of the rock mass including convergence and displacement around tunnel were measured with construction works and the crack width in concrete wall was also monitored for controlling allowable limits. The results can be summarized as follow : 1. The allowable blast vibration level in structure site is less 1.0cm/sec for highway concrete, 0.5 cm/sec for gas pipe, water pipe and building housing and 0.3 cm/sec for automatic control system machine. 2. The convergence displacement, single rod extensometer and multi rod extensometer around tunnel and cracks in concrete wall were measured, it was confirmed that the measured values were converged within allowable level. 3. The empirical formular of ground vibrations with 90% confidence lines for PD-3 was given as follow. $$V_{90%}=45.549({\frac{D}{\sqrt{W}}})^{-1.353}$$

Keywords