Network Compression by Saying Idle Time of Resources and Spaces for Repetitive Activities

작업공간과 자원의 여유시간 최소화를 통한 반복작업 공정계획기법

  • Published : 2000.09.01

Abstract

In scheduling multi-unit projects, several alternatives can exist in network construction due to repetitiveness of their activities. Project duration is affected not only by the duration of each activity but also by the arrangement of repeating activities in such projects. This paper provides a network compression method that assigns predecessors to each activity to minimize its float time. Different to the previous efforts that utilized line of balance as the base scheduling-model, this research adopts precedence diagram arranged in two coordinates, the space axis and the resource one. This method seeks the most appropriate predecessors for each activity in each direction of the two coordinates for the purpose of minimizing the idle resource and space. This activity arrangement method was applied to a multi-unit apartment-construction project, to prove its capability of network compression. The result shows that the method successfully sought room for saving construction duration by changing the activity arrangement. The network compression method presented in this research can be utilized in multi-unit construction projects such as apartment complex projects.

공간의 분할이 많은 건축공사에서는 반복적 특성으로 인해 공정계획상에 다수의 대안이 존재한다. 공사기간은 각 액티비티의 기간뿐 아니라 반복되는 액티비티의 배열방법에 의해서도 많은 영향을 받는다. 본 연구는 각 액티비티에 적정한 선행 액티비티를 할당함으로써 여유시간을 최소화하는 공정계획기법을 제시하는 것을 목적으로 진행되었다. Line of Balance 기법을 기본으로 하는 기존연구와는 달리 본 연구에서는 AON방식의 네트워크 기법을 기본으로 하여 공간과 자원의 두 축 사이에 액티비티를 배열하였다. 각 액티비티별로 자원과 공간의 양방향으로 가장 적절한 선행 액티비티를 검색하여 여유시간을 최소화한다. 본 연구에서 제시한 액티비티 배열방법을 공동주택공사 건설공사를 대상으로 적용한 결과, 액티비티 배열을 달리함에 따라서 다수의 대안이 존재함을 확인할 수 있었으며 그중 적정대안을 찾아낼 수 있었다. 본 기법은 공동주택공사와 같은 다수의 유사공간으로 구성된 건설공사의 공정 계획에 도움을 줄 수 있을 것으로 판단된다.

Keywords