Process Optimization Method Based on Emergency Construction Work Scenario

돌관공사 시나리오 기반 공정관리 최적화 방안

  • 이시현 (홍익대학교 건축공학과) ;
  • 이승학 (홍익대학교 건축공학과) ;
  • 우미선 (홍익대학교 건축공학과) ;
  • 손재호 (홍익대학교 건축공학과)
  • Published : 2015.05.28

Abstract

These days buildings have more possibilities to occur construction delay as many variables and risks are inherent in them due to the enlargement and complexity. When a project is delayed, it generates extra working expenses and this causes a dispute between the employer and the constructor. Most construction sites conduct emergency construction work to recover the delay of the project duration. When an emergency construction is carried out in the actual construction site, it's necessary to utilize and distribute the proper working groups based on the procedure of successor and predecessor. Many constructions, however, have been going only with more number of work forces and working time. This study suggests a process management optimization plan with an application of emergency construction scenario by using linear programing.

Keywords