A study on application method of "Result unit cost" to Nuclear Power Plant (NPP) construction cost estimating
원전 건설공사 실적공사비 단가 제도 도입을 위한 연구
- Published : 2014.05.29
Abstract
Recently, BAI(Board of Audit and Inspection of Korea) has recommended that "Result unit cost" of Korean government apply to national power plant construction project when plant owner corporations estimate budget price for tender. but nuclear industry have difficulties with this suggestion. the purpose of this study is to review the "Result unit cost" and problem with application of NPP construction cost estimating. And proposed the direction of application of "Result unit cost" to NPP construction cost estimating.