Study on Development of Steam Curing Method for In-situ production of Precast Concrete members

프리캐스트 콘크리트 부재의 현장생산용 증기 양생 방법 개발 연구

  • Published : 2014.11.14

Abstract

Green Frame is a building frame system to construct a column-beam structure using composite precast concrete members. To reduce the cost of producing precast concrete, in-situ production of members is required. However, when the structural members are produced on site, it needs a large space for production. So, "Just-In-Time" production method should be adopted. For Just-In-Time to be realized, the early strength of members should be ensured for them to be transported. Thus, steam curing to secure the early strength is applied in Green Frame. Yet, a large-scale steam curing system is not possible for in-situ production of precast concrete. A smaller steam curing system is needed. In this regard, the study is aimed to develop a new steam curing method applicable to the in-situ production of precast concrete.

Keywords