개략견적 기법 개발을 위한 신한옥 특성 분석

Characteristics of Modernized Hanok for development Estimate system.

  • 발행 : 2013.05.09

초록

The purpose of this research is to propose an approximate estimation system for Modernized Hanok. Mock-up (Jisinjae) site data has been collected and analysed to characterize the modernized Hanok and to examine the range of cost fluctuation rate with each work items. As a result, number of floor, area (㎥), shape, methods and materials were considered as key factors for price change on the total construction cost. Furthermore, wood structure (34%) and roof (17%) account for major cost percentage. The cost fluctuation rate of two factors were -3.3%~+5.6% (wood structure) and -4.1%~+4.2% (roof). For further research, existing method will be analysed in order to developing the Hanok estimation system. And the cost fluctuation rate of every work items will be continually evaluated.