Characteristics of Modernized Hanok for development Estimate system.
개략견적 기법 개발을 위한 신한옥 특성 분석
Abstract
The purpose of this research is to propose an approximate estimation system for Modernized Hanok. Mock-up (Jisinjae) site data has been collected and analysed to characterize the modernized Hanok and to examine the range of cost fluctuation rate with each work items. As a result, number of floor, area (㎥), shape, methods and materials were considered as key factors for price change on the total construction cost. Furthermore, wood structure (34%) and roof (17%) account for major cost percentage. The cost fluctuation rate of two factors were -3.3%~+5.6% (wood structure) and -4.1%~+4.2% (roof). For further research, existing method will be analysed in order to developing the Hanok estimation system. And the cost fluctuation rate of every work items will be continually evaluated.