P.R.D. 공법을 활용한 가물막이 설계

The design of coffer dam utilized P.R.D. method

  • 박철숙 (한국수자원공사 수자원 연구원) ;
  • 이규탁 (한국수자원공사 댐유역 관리처) ;
  • 염경택 (한국수자원공사 댐유역 관리처) ;
  • 김윤구 (한국수자원공사 울산권 관리단) ;
  • 강봉권 (한국수자원공사 울산권 관리단) ;
  • 이재원 ((주)태조 엔지니어링) ;
  • 임석산 (삼성물산(주) EA팀) ;
  • 정지열 (삼성물산(주))
  • 발행 : 2008.10.10

초록

Coffer dam for tunnel type spillway in inflow section of Dae-am dam was originally planned as 2 lines sheet piles with Water Zet method. But, the result of pilot test was caused of some problems that vibration during installation of pile could pollute water and water leakage could the lower part. So, sheet piles was not satisfactory for faculty of coffer dam. Structural instability of sheet pile system need to reinforcement. Characteristic of Dae-am dam was small reservoir capacity but wide drainage area, of which it was judgment that security of leakage and stability was difficult during excavation of inlet part. So, we consider that water curtain method utilized with in site pouring concrete pile method was designed at weir part of spillway. We were known about basement rock that geological boring was carried out in weir part. After taking a deep consideration, PRD method was accepted as a new method. Concrete pile by PRD was installed to below country rock. CJM method was carried out with PRD. After making concrete wall using Top-down method, earth anchors were installed for supporting it. According to the result of numerical analysis, as water level rises, wall is stable.

키워드