A Study on the Analysis of Delay Claim Risk in Apartment Housing Projects
공동주택공사에서의 공기지연 리스크분석에 관한 연구
- Published : 2003.11.01
Abstract
This study proposes a new classification system and analysis methodology for time delay risk of apartment projects. And this study proposes the classification of major trades and risk level and risk index by performing expert-oriented interview and survey report on a national scale. The purpose of this study is to present basic data for time delay risk management system through the analysis of risk level, risk index and rank of major 5 trades(earth work, structure work, masonry work, window and door/glass work, and interior finish work) in apartment projects.