Proceedings of the Korean Institute of Building Construction Conference (한국건축시공학회:학술대회논문집)
- 2003.05a
- /
- Pages.157-160
- /
- 2003
Analysis of Progress Schedule and Delay Element of Frame Works in Apartments
아파트 구체공사의 공정관리 및 공기지연요소 분석에 관한 연구
Abstract
In order to reduce the construction cost and period without degrading the quality, construction companies are making a lot of efforts to prefabricate and mechanize the construction process, and introducing and utilizing various techniques of construction time management in the process of construction. However, due to the various factors (such as weather conditions, labor factors, supply of equipment and materials, safety accident, etc) in the process of construction, construction projects are not frequently completed within the scheduled Period. This research is to examine the current status of construction time management and factors causing delay in construction with regard to the concrete work (such as form work, steel reinforcement, and concrete work) in building apartments.
Keywords