Methods of Establishing the Optimal Performance Measurement Baseline and Evaluating the Progress for Implementing EVMS

EVMS 적용을 위한 최적 성과측정기준선 설정 및 진도율 산정 방법

  • Published : 2001.11.01

Abstract

In construction projects, it is very important to evaluate the performance of works in comparison with the cost and schedule plans. So, on the first of July, 2000, the Ministry of Construction and Transportation announced the EVMS will be applied in public sector soon. However there are still many arguments about how to establish the Performance Measurement Baseline(PMB) and how to evaluate the progress with accuracy. And many people confuse the meaning of EVMS with that of cost and schedule management. So, the purpose of this research is to propose the new useful methods to set up the PMB and to assess the exact progress in consideration of cost, schedule, and float time for successful implementation of EVMS.

건설공사의 성공적인 수행을 위해서는 프로젝트의 성과에 대한 주기적이고 반복적인 측정 및 그에 대한 조치가 필요하다. 이에 비용, 일정, 품질은 프로젝트 성과 측정의 주요 대상이 되며, 비용 및 일정의 경우 정량화할 수 있고, 상호연관성이 높기 때문에 통합관리의 필요성이 매우 높다. 이러한 비용일정 통합관리를 통한 성과측정 방법이 바로 EVMS이며, 이러한 새로운 관리방식의 성공적인 국내적용을 위해선 그 관리 방법의 절차 및 의미가 명확히 인식되어야 한다. 이에 본 연구는 비용, 일정, 여유시간을 종합적으로 고려한 새로운 최적의 성과측정기준선(Performance Measurement Baseline)설정 및 진도율 산정 방법을 제시하고자 한다. 제시된 방법을 통해 비용 및 일정정보가 통합된 성과측정기준선이 마련되었으며, 진도율 산정에 있어서도 작업간 영향요소 및 공기지연가능성을 고려한 종합적인 작업별 가중치가 산정되었다.

Keywords