• Title/Summary/Keyword: rock tunnel

Search Result 2,152, Processing Time 0.023 seconds

Optimum Support Pattern Design of the Tae-Gu Subway Tunnel (대구 지하철 터널의 적정지보패턴 선정에 관한 연구)

  • 지왕률;최재진
    • Tunnel and Underground Space
    • /
    • v.4 no.2
    • /
    • pp.119-131
    • /
    • 1994
  • This is a Double-Track Railway tunnel in typical Tae-Gu black and gray shale forming part of the No.1 Line of the Tae-Gu Subway. The main fault zone at tunnel is a moderately to highly weathered and closely jointed zone, 0.5 m wide with associated paralled jointing which is slickensided and fractured. After excavation by blasting, the soft rocks should need to be reinforced with optimal supporting pattern which might be better redesigned through the consideration of the results of in-situ rock measurements at the field. Performances fo the field tests included Point Load Test, Schmidt Hammer Test, and field joint measurement gave the detail data for the optimum support design and safe excavation of the No.1 Line of Tae-Gu Subway at the No.1-7 consturction site adn the safety of this redesigned supports system was analysed by the FDM program FLAC.

  • PDF

Measurement of Joint-Orientation and Monitoring of Displacement in Tunnel using 3D Laser Scanning System (3차원 레이저 스캐닝 시스템을 이용한 불연속면의 방향성 측정과 터널 변위 모니터링)

  • Shon, Ho-Woong;Oh, Seok-Hoon;Kim, Young-Kyung
    • Journal of the Korean Geophysical Society
    • /
    • v.9 no.1
    • /
    • pp.47-62
    • /
    • 2006
  • More than 70% of Korean Peninsula is consisted of mountains, so that lots of roads, rail-roads and tunnel,which play a pivotal role in the industry activity, are existed along the rock-slope and in the rock-mass. Thus,it is urgent that tegration of management system through the optimum survey and design of rock-slope excavation, proper stabilization method and database of rock-slope. However, conventional methods have shortcoming with the economy of survey time and human resources, and the overcome of difficulties of approach to the in-situ rock-slope. To overcome the limitation of conventional method, this paper proposed the development of remote measurement system using Terrestrial Laser Scanning System. The method using Terrestrial 3D Laser Scanning System, which can get 3D spatial information on the rock-slope and2)Dept. Geosystem Engineering, Kangwon National University, Korea tunnel, has an advantage of reduction of measurement time and the overcome of difficulties of approach to the in-situ rock-slope/dam/tunnel. In the case of rock-slope, through the analysis of 3D modeling of point-cloud by Terrestrial Laser Scanning System, orientation of discontinuity, roughness of joint surface, failure shape and volume were successively achieved. in the case of tunnel face, through reverse-engineering, monitoring of displacement was possible.

  • PDF

A Study of Rockbursts Within a Deep Mountain TBM Tunnel (산악 TBM 터널에서 발생한 암반파열 현상에 대한 연구)

  • Lee, Seong-Min;Park, Boo-Seong
    • Journal of the Korean Geotechnical Society
    • /
    • v.19 no.6
    • /
    • pp.39-47
    • /
    • 2003
  • Rockbursts are mainly caused by a sudden release or the stored strain energy in the rock mass. They have been the major hazard in deep hard rock mines but rarely occur in tunnels. Due to the short history and limited information on rockbursts, the topic has rarely been studied in Korea. Some cases of rockbursts, however, have been reported during construction of a mountain tunnel for waterway. This study focuses on analyzing data on rockbursts obtained from a TBM (Tunnel Boring Machine) tunnel and suggests methods for a comprehensive understanding on rockbursts. From the analysis of the field data of rockbursts, it was found that most rockbursts mainly occurred at the section between the tunnel face and the TBM operating room, and the rock bursting phenomena lasted up to 20 days after excavation in certain areas. The data also show that the bursting spots are located all around the tunnel surface including the face, the wall, and the roof, The maximum size of bursting spots is usually less than 100cm. This study also suggests new scale systems of brittleness and uniaxial compressive strength to evaluate the possible tendency for a rockburst. These systems are scaled based on the scale system of strain energy density. In addition, with these scale systems, this research shows that there are potentially higher tendencies for rockbursts in this specific tunnel. Moreover this research suggests that properties of rock and rock mass, RMR (Rock Mass Rating) value, tunneling method, excavating speed, and depth of tunnel have a strong correlation with rockbursts.

Soft Sedimentary Rock Slopes Design of Diversion Tunnel

  • Jee, Warren Wangryul
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 2007.10a
    • /
    • pp.63-79
    • /
    • 2007
  • Several remedial works were attempted to stabilize the collapsed area of the inlet slopes of diversion tunnel, but prevention of any further movement was being only carried out at beginning stage by filling the area with aggregates and rock debris, after several cracks had been initiated and developed around the area. The extra specialty developed folding zone is consisted with highly weathered Greywacke and Black shale. The suggested solution is to improve the properties of the rock mass of failed area by choosing the optimum level of reinforcement through the increment of slope rock support design so as to control the movement of slopes during the re-excavation. The Bakun hydroelectric project includes the construction of a hydroelectric power plant with an installed capacity of 2,520MW and a power transmission system connecting to the existing transmission networks in Sarawak and Western Malaysia. The power station will consist of a 210m height Concrete Faced Rockfill Dam. During the construction of the dam and the power facilities the Balui River has to be diverted of the tunnels is 12m and the tunnel width is 16m at the portal area. This paper describes the stability analysis and design methods for the open cut rock slopes in the inlet area of the diversion tunnels. The geotechnical parameters employed in stability calculations were given as a function of four defined Rock Mass Type (RMT) which were based on RMR system from Bieniawski. The stability calculations procedure of the rock slopes are divided into two stages. In the first stage, it is calculated for the stability of each "global" slope without any rock support and shotcrete system. In the second stage, it is calculated for each "local" slope stability with berms and supported with rock bolts and shotcrete. The monitoring instrumentation was performed continuously and some of the design modification was carried out in order to increase the safety of failed area based on the unforeseen geological risks during the open cut excavation.

  • PDF

Control of Blast Vibration, Air Blast, and Fly Rock in Rock Excavation (암반굴착에 의한 발파진동, 소음 및 비석의 조절)

  • Ryu, Chang-Ha
    • Tunnel and Underground Space
    • /
    • v.2 no.1
    • /
    • pp.102-115
    • /
    • 1992
  • Blasting operations associated with rock excavation work may have an environmental impact in nearby structures or human beings. With the increase of construction work in urban areas, vibration problems and complaints have also increased. In order to determine the optimum design parameters for safe blast, it is essential to understand blast mechanism, design variables involved in blast-induced damage, and their effects on the blasting results. This paper deals with the characteristics of ground vibrations, air blast and fly rock caused by blast, including the general method of establishing the vibration predictors, and damage criteria suggested by various investigators. The results of field measurements from open pit mine and tunnel construction work are discussed. Basic concepts of how to design blast parameters to control the generation of ground vibrations, air blast and fly rock are presented.

  • PDF

전면접착형 록볼트의 지보거동: 이론적 수식화와 경계요소해석에 대한 적용

  • 김호영;이희근
    • Tunnel and Underground Space
    • /
    • v.1 no.2
    • /
    • pp.168-180
    • /
    • 1991
  • Through field measurements, it was shown that the shear stresses along a fully grouted rock blot were proportional to the differences between the displacement of a bolt rod and that of surrounding rock. Accordingly the theoretical equation for the displacement along a rock bolt, R(x), can be proposed as differential form; $ \frac{d^2R(x)}{dx^2}-aR(x)=-a^2U(x)$ where U(x) is the displacement of surrounding rock and α is a constant. In this study above equation was applied to the boundary element analysis which can simulate the supporting behavior of each rock bolt around a tunnel and the results of the implementation of boundary element technique were shown.

  • PDF

Tunnel Safety Diagnosis in Near-excavation by In-depth Inspection of Tunnel (기존터널 안전진단 결과를 통한 근접시공 시 터널 안정성 평가)

  • Kim, Seok-Jae;Kim, Min-Seok;Kim, Jun-Chul;Yoo, Young-Il;Oh, Joung-Bae;Oh, Sae-Joon
    • Tunnel and Underground Space
    • /
    • v.16 no.4 s.63
    • /
    • pp.347-356
    • /
    • 2006
  • We analyzed case studies doing in-depth inspection of tunnel to maintain safety of existing tunnel in constructing new tunnel near to a existing tunnel with single track. Futhermore, We accomplished in-depth inspection of existing tunnel and numerical analysis. We suggested remedies to security safety of existing tunnel. We applied line drilling and pre-large hole boring method not to have an effect on existing tunnel and convinced the safety of existing tunnel from blast-vibration and blast-noise of numerical analysis. We planed to install basset system to measure displacement of existing tunnel according to excavating new tunnel.

Tunnel Pressure acting on Shallow Tunnel in Unconsolidated Ground (미고결 저토피 터널에 작용하는 토압에 관한 연구)

  • Lee, Jae-Ho;Akutagawa, Shinish;Kim, Young-Su;Moon, Hong-Duk
    • Tunnel and Underground Space
    • /
    • v.17 no.6
    • /
    • pp.453-463
    • /
    • 2007
  • Terzaghi's tunnel pressure theory is generally used to estimate primary design pressures on tunnel support for shield and urban NATM tunnels until now. A trial is made in this paper to investigate the interaction between the ground deformation behavior and Terzaghi's tunnel pressure, which assumes pound's limit (or critical) state, by considering results of 'Terzaghi's tunnel pressure theory. two-dimensional reduced-scale model tunnel tests and nonlinear numerical analysis based on strain softening modeling. A full understanding between tunnel pressure and ground deformation behavior under the tunnel excavation and an effective utilization of this interaction lead to an economical tunnel support design and a safe construction of tunnel.

Measurement of Tunnel Arch Settlements Ahead of and Behind the Tunnel Face Using a Horizontal Inclinometer and Settlement Pins (수평경사계와 천단침하계에 의한 터널막장 전후방의 천단침하 계측)

  • Kim, Cheehwan
    • Tunnel and Underground Space
    • /
    • v.23 no.2
    • /
    • pp.120-129
    • /
    • 2013
  • It is important to measure the displacement behind and ahead of a tunnel face during construction for evaluating mechanical stability by comparing it to a displacement criteria set by tunnel designers. The 30 m long horizontal inclinometer was installed frontward from the tunnel face and the displacement occurred ahead of a tunnel face during excavation was measured by using it. Tunnel arch settlements behind tunnel face were surveyed using a settlement pins on the arch. So total settlement and longitudinal displacement curve were obtained combining settlement measured by both the horizontal inclinometer ahead of tunnel face and the settlement pins behind the tunnel face.

The First Case Study of TBM Pre-Excavation Type 2-Arch Tunnel in Korea (국내 최초 TBM선굴진 2-Arch터널 설계사례 연구)

  • Hyung-Ryul Kim;Sang-Jun Jung;Jun-Ho Kang
    • Tunnel and Underground Space
    • /
    • v.33 no.4
    • /
    • pp.255-264
    • /
    • 2023
  • As the demand for urban underground space increases recently, urban tunnel planning is actively progressing. In the urban area, a underground station is planned in consideration of the living environment of residents, and 2-arch tunnel is applied for the stability of existing structures and reduction of environmental damage. However, since the depth of weak rock mass is deeply distributed in the urban area due to severe weathering, careful planning is required to secure tunnel stability. In addition, if TBM mechanical excavation is applied as the main tunnel excavation method considering the composite ground in urban area, the construction connectivity with the 2-arch tunnel of the NATM concept may be deteriorated. In this study, the design case of applying TBM pre-excavation type 2-arch tunnel for the first time in Korea was mainly described. The main considerations for the segment design of TBM pre-excavation type 2-arch tunnel were explained for side tunnels. Also, a stability analysis was conducted to verify the effectiveness and adequacy of the TBM pre-excavation type 2-arch tunnel.