제약만족기법 기반의 최대부하감소를 통한 탑재 네크워크의 부하평준화 (Load Leveling of Block Erection Network Using Diminution of Maximum Load Based on Constraint Satisfaction Technique)

  • 류지성;김홍태;박진형;이병로;신종계
    • 대한조선학회논문집
    • /
    • 제41권5호
    • /
    • pp.55-62
    • /
    • 2004
  • The logistics of entire shipbuilding process are integrated during the block erection process and the schedules for the erection process are made prior to. the schedules of any other processes. Therefore, efficient scheduling of the block erection process are one of most important issues in shipbuilding. There are only a few studies published regarding block erection scheduling methods because of its complexity and variability. This paper proposes an algorithm for diminution of maximum load based on constraint satisfaction technique. it is developed primarily for the efficiency in load leveling and applicability to the actual block erection process. The proposed algorithm is applied to actual block erection process and the results shows improvements in load leveling. It can also be used for the scheduling of fabrication, sub-assembly, and assembly to improve load leveling.

A CSP-based Load Leveling Algorithm for Ship Block Erection Network

  • Ryu, Ji-Sung;Park, Jin-Hyoung;Kim, Hong-Tae;Lee, Byung-No;Shin, Jong-Gye
    • Journal of Ship and Ocean Technology
    • /
    • 제10권2호
    • /
    • pp.37-44
    • /
    • 2006
  • The erection in shipbuilding is the process to assemble all the blocks one by one in certain order and requires more leveled and efficient schedule than other processes do. However, erection schedule includes too many constraints to be systemized with simple programs and constraints are changed frequently. These difficulties make it rare to find automatic erection schedule generation system with load leveling ability. In this paper, a CSP (Constraint Satisfaction Problem)-based load leveling algorithm using a maximum load diminution technique is proposed and applied to the block erection scheduling of a dock in a shipyard. The result shows that it performs better than currently used scheduling method based on empirical logics. The maximum load of welding length and crane usage are reduced by 31.63% and 30.00% respectively. The deviation of resource usage amount also decreases by 8.93% and 7.51%.