A Case Study on Tensile Behavior Characteristics of Long-length Rockbolt for Anchoring Systems (장대록볼트 정착방식에 따른 인발거동특성 사례연구)

  • Han, Sang-Hyun;Yea, Geu-Guwen
    • The Journal of Engineering Geology
    • /
    • v.17 no.1 s.50
    • /
    • pp.65-73
    • /
    • 2007
  • Recently, large-scale underground cavern such as underground hydraulic-power plant tend to be constructed very largely, so long-length rock bolt are generally used to support the huge plastic zone. However, problems fur bend-ing shape of the long-length steel bar and the bonding effects of anchoring systems are caused during the construction of the long-length rock bolt. In this study, field pull-out test for long-length rock bolt are carried out to estimate the most efficient anchoring system among the saw-toothed shape, grooved shape and smoothed shape with each 6 shells for 5.0m, 7.5m, 10.0m, 15.0m length. The axial load and axial displacement are measured with each load stage and than test results are analyzed to evaluate the behavior characteristics for each anchoring systems of long-length rock bolt. Also, the improvements of anchoring systems are proposed and discussed in this paper.

Stress distribution in a passive fully grouted rock bolts

  • Karanam U. M. Rao;Dasyapu S. K.
    • 한국지구물리탐사학회:학술대회논문집
    • /
    • 2003.11a
    • /
    • pp.122-128
    • /
    • 2003
  • Rock bolts are widely used as a supplementary roof support system in hard-rock mining since a long time. Since the performance of fully grouted passive bolts depends on bond strength, in the present investigation extensive laboratory pull-out as well as push-out tests were conducted varying the bolt diameter, length and cement-water mixing ratios of grout. The load-displacement curves were developed and were verified with the numerical results obtained from finite element analysis using ALGOR software. Numerical models were validated for push-out tests and a detailed analysis was carried out to know the displacement, stress, strain distribution along the bolt.

  • PDF

A Study on Efficient Design Technique of RPUM Steel Pipes (RPUM 강관의 효율적인 설계기법에 관한 연구)

  • Kim, Jung-Su;Park, Tae-Soon
    • Proceedings of the KSR Conference
    • /
    • 2006.11b
    • /
    • pp.1354-1363
    • /
    • 2006
  • Until now, NATM(New Austrian Tunneling Method) has been increasingly developed based on concept of making use of ground as support. Also, NATM in its essence is a method of risk based on monitoring behaviour of tunnel. This Monitoring is irreplaceable for the quality construction of tunnel, and safety of tunnel itself. Pre-reinforcement ahead of a tunnel face using long steel pipes in NATM, known as the RPUM(Reinforced Protective Umbrella Method), is the auxiliary method to sustain the stability of a tunnel face and reduce the ground settlements. Since design of RPUM has been dependent on the empirical design, it is necessary to develop the improved design methods. In this study, to understand behaviour of steel pipes, it is monitored displacement of tunnel crown, axial force of rock bolt, displacement and axial stress of steel pipes. Also, in order to clarify the mechanical behaviour and RPUM effects, 3-Dimensional numerical analysis is performed that various cases of different parameter combinations including original length and repeated length of steel pipes, installation width and angle, repeated length of steel. In the results of comparison monitoring with analysis, it is suggested more economical and efficient design technique than empirical design methods.

  • PDF

Evalution for Mechanical Property and Durability of Miner's Shotcrete (광산용 숏크리트의 역학적 특성 및 내구성 평가)

  • Nam-Gung, Kyeong;Ma, Sang-Joon;Lee, Kyeo-Re;Yun, Kyong-Ku
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.16 no.2
    • /
    • pp.1461-1468
    • /
    • 2015
  • Mostly mine support(Rock bolt and Support) which is currently general for reinforcements of a large scale tunnel is applied, Some executing a reinforcement to Poor ground by cast-in-place shotcrete. However On domestic mine conditions that couldn't having every time after mine tunnel excavation, it couldn't ensure the field batch plant which is a fixed in an issue of economies and site security, constructing it by supply gets from shotcrete materials combined in neighborhood ready mixed concrete manufacturing plants. carried shotcrete in ready mixed concrete manufacturing plants as migration length and time are falling off in quality. But, it is difficult for construction quality control By quality control arbitrariness absence at on-scene. In the present study, carry out Laboratory Test by kinds and percentages of accelerating agent for evalution of Mechanical Property and Durability of Shotcrete.