On the influence survey to building by the cable Tunnel blasting works. (통신구 터널발파작업으로 인한 진동.소음이 지상주택에 미치는 영향 평가)

  • Huh Ginn;Cheon Sang Back
    • Explosives and Blasting
    • /
    • v.11 no.1
    • /
    • pp.5-33
    • /
    • 1993
  • On the cable Tunnel works. Cautious blasting works were so effective and carried out. The vibration record were under 0.4cm / sec and blasting noise are under 75dB Which it was measured at the ground of Tailor House. As a result cautious blasting works under above allowable value, are not Influenced the structure of house and living. On the architechtural survey, there were some hair crack on the wall but this was not crack from recently blasting work.

  • PDF

On The influence study to building by seoul sub-way construction 7-20 site Tunnel works. (서울지하철 7-20공구 터널 굴착으로 인한 지상 주택 구조물에 미치는 진동 소음 영향 조사연구)

  • Huh, Ginn
    • Explosives and Blasting
    • /
    • v.13 no.3
    • /
    • pp.7-18
    • /
    • 1995
  • On the Seoul sub-way tunnel works 7-20 site, Cautious blasting works were so effectivelly carried out. The vibration record were under 0.3cm/sec and blasting noise was under 80dB. Which was measured at the ground of house. At a result cautious blasting works under above allowable value was not influenced the structure of house and living conditions. On the architectural survey, They were some hair crack on the wall and floors but this was not a crack from blasting works.

  • PDF

On the Cautious blasting pattern of Weak zone of NAMSAN NO. twin Tunneling (남산1호터널 쌍굴 굴진공사 정밀발파 작업에 대한 안전도검토)

  • Huh, Ginn
    • Explosives and Blasting
    • /
    • v.8 no.4
    • /
    • pp.3-22
    • /
    • 1990
  • The $\varphi{4.5}$ meters pilot tunneling work is almost done to the $\varphi{11.3}$ meters twin tunnel of NAM SAN No1. The south side pit of 400 meters is weak zone of Rock status, so client request us to allow the cautious blasting pattern for drilling on the condition of 0.2 kine vibration allowance limited for the safety of side running tunnel. The pattern of cautious blasting carried out by 6 time divided fiving on the round drilling depth of 1.20 meters(1.10) and also applied control blasting method with line drilling due to the reduction of vibration.

  • PDF

On the Influence Study to Building by Seoul Sub-way(8-6 site) Tunnel works (서울지하철공사 8-6공구터널 발파작업으로 인한 진동, 소음이 지상주택가 구조물에 미치는 연구조사)

  • Huh Ginn;Cheon Sang Back
    • Explosives and Blasting
    • /
    • v.12 no.1
    • /
    • pp.5-31
    • /
    • 1994
  • On the Seoul Sub-way Tunnel works (8-6 site ). Cautious blasting works were so effectivelly tarried out the vibration record were under 0.3cm /sec and blasting noise was under 75dB which was measured at the ground of house. As a result cautious blasting works under above allowable value was not influenced the structure of house and living. On the architectural survey, There were some hair crack on the wall and floors but this was not a crack from balsting work.

  • PDF

Standardization of Cautious blasting (정밀발파의 표준화)

  • Huh Ginn
    • Explosives and Blasting
    • /
    • v.8 no.3
    • /
    • pp.3-13
    • /
    • 1990
  • First ot of all, under given condition such as bit gage of 36mm Drill bit with right class of jack-leg-experimental test carried out from two face of Bench, firing of each hole brought 90 degree Angle face and them measured length of Burden and charged ammount of powder as following. $ca=\frac{A}{SW}$ A=Activated Area A=nd i=m S=Peripheral length of charged, room Ca=Rock Coeffiecency d: di=Hole diameter When constructed subway of Seoul in 1980 the blasting works increased complaint of ground vibration, in order to prevent the damage to structures. Some empirical equations were made as follows on condition with Jackleg Drill (Bit Gage 36mm) and within 30 meter distance between blasting site and structures. $V=K(D/W)^{-n}$ N=1.60 - 1.78 K= 48 - 138 Project is one of contineous works to above a determination of empirical equation on the cautious blasting vibration with Crawler Drill (70-75mm) in long distance. $V=41(D/\sqrt[3]{W})^{-1.41}$ $30m\le{D}\le{100m}$ $V=124(D/\sqrt[3]{W})^{-1.66}$ $100m\le{D}\le{285m}$.

  • PDF

Cautious Blasting Works on the Po-Ryong Power Plant #3 #4 Foundation (#3 #4호기 보령화력발전소 기초공사 정밀발파공법)

  • Huh, Ginn
    • Journal of the Korean Professional Engineers Association
    • /
    • v.21 no.4
    • /
    • pp.12-18
    • /
    • 1988
  • On the foundation work of Po-Ryong power plant #3 & #4. It was 30meters away from the running states of #1 & #2 plant site. In order to protect the #1 & #2 power plant facilities & factory structure. Allowable vibration was required below 0.07 gal. Therefore, it had to set up the anti-vibration trench to reduce the vibration reference and secondary. I applied the low gravity and low velocity explosives with M/S delay caps by cautious blasting pattern.

  • PDF

On the vibration influence to the running power plant facilities when the foundation excavated of the cautious blasting works. (S화력발전소 3, 4호기 증설에 따르는 정밀발파작업으로 인한 인접가동발전기및 구조물에 미치는 파동영향조사)

  • Huh Ginn
    • Explosives and Blasting
    • /
    • v.8 no.1
    • /
    • pp.3-16
    • /
    • 1990
  • The cautious blasting works had been used with emulsion explosion electric M/S delay caps. Drill depth was from 3m to 6m with Crawler Drill $\varphi{70mm}$ on the calcalious sand stone(sort-moderate-semi hard Rock). The total numbers of feet blast were 88. Scale distance were induces 15.52-60.32. It was applied to propagation Law in blasting vibration as follows. Propagtion Law in Blasting Vibration $V=K(\frac{D}{W^b})^n$ where V : Peak partical velocity(cm/sec) D : Distance between explosion and recording sites (m) W : Maximum Charge per delay-period of eighit milliseconds or more(Kg) K : Ground transmission constant, empirically determind on th Rocks, Explosive and drilling pattern ets. b : Charge exponents n : Reduced exponents Where the quantity $D/W^b$ is known as the Scale distance. Above equation is worked by the U.S Bureau of Mines to determine peak particle velocity. The propagation Law can be catagrorized in three graups. Cabic root Scaling charge per delay Square root Scaling of charge per delay Site-specific Scaling of charge per delay Charge and reduction exponents carried out by multiple regressional analysis. It's divided into under loom and over loom distance because the frequency is verified by the distance from blast site. Empirical equation of cautious blasting vibration is as follows. Over 30m----under l00m----- $V=41(D/3\sqrt{W})^{-1.41}$ -----A Over l00m-----$V= 121(D/3\sqrt{W})^{-1.66}$-----B K value on the above equation has to be more specified for furthur understang about the effect of explosives, Rock strength. And Drilling pattern on the vibration levels, it is necessary to carry out more tests.

  • PDF

On the vibration influence to the running power plant facilities when the foundation excavated of the cautious blasting works. (S 화력발전소 3, 4호기 증설에 따르는 정밀발파작업으로 인한 인접가동발전기 및 구조물에 미치는 진동영향조사)

  • Huh Ginn
    • Explosives and Blasting
    • /
    • v.9 no.4
    • /
    • pp.3-12
    • /
    • 1991
  • The cautious blasting works had been used with emulsion explosion electric M /S delay caps. Drill depth was from 3m to 6m with Crawler Drill 70mm on the calcalious sand stone (soft-moderate-semi hard Rock) . The total numbers of feet blast were 88. Scale distance were induces 15.52-60.32. It was applied to Propagation Law in blasting vibration as follows .Propagtion Law in Blasting Vibration V=k(D/W/sup b/)/sup n/ where V : Peak partical velocity(cm/sec) D : Distance between explosion and recording sites(m) W ; Maximum Charge per delay -period of eight milliseconds or more(Kg) K : Ground transmission constant, empirically determind on the Rocks, Explosive and drilling pattern ets. b : Charge exponents n : Reduced exponents Where the quantity D/W/sup b/ is known as the Scale distance. Above equation is worked by the U.S Bureau of Mines to determine peak particle velocity. The propagation Law can be catagrorized in three groups. Cabic root Scaling charge per delay Square root Scaling of charge per delay Site-specific Scaling of charge delay Charge and reduction exponents carried out by multiple regressional analysis. It's divided into under loom and over loom distance because the frequency is varified by the distance from blast site. Empirical equation of cautious blasting vibration is as follows. Over 30m--under 100m----V=41(D/ W)/sup -1.41/-----A Over l00m---------V=121(D/ W)/sup -1.56/-----B K value on the above equation has to be more specified for furthur understand about the effect of explosives. Rock strength, And Drilling pattern on the vibration levels, it is necessary to carry out more tests.

  • PDF

Standardization of Cautious blasting (정밀발파의 표준화(下))

  • Huh, Ginn
    • Journal of the Korean Professional Engineers Association
    • /
    • v.23 no.6
    • /
    • pp.41-46
    • /
    • 1990
  • First of all, Under given condition such as bit gage of 36mm Drill bit with right class of jack-logs experimental test carried out from two face of Bench, firing of each hole brought 90 degree Angle face and them measured length of Burden and charged ammount of powder as following. (equation omitted) A=Activated Area A=ndi=m S=Peripheral length of Charged. room Ca=Rock Coeffiecency d : di=Hole diameter When constructed subway of Seoul in 1980 the blasting works increased complaint of ground vibration. in order to prevent the damage to structures. Some empirical equations were made as follows on condition with Jackleg Drill (Bit Gage ø 36mm) and within 30 meter distance between blasting site and structures. V=K(D / W)$\^$-n/ N=1.60-1.78 K=48-138 Project one of contineous works to above a determination of empirical equation on the cautious blasting vibration with Crawler Drill(ø 70-75mm) in long distance. V=41(equation omitted) V=124(equation omitted).

  • PDF

On the vibration influence to the running power plant facilities when the foundation excavated of the cautious blasting works (삼천포화력발전소 3, 4호기 증설에 따르는 정밀발파작업으로 인한 인접가동발전기 및 구조물에 미치는 진동영향조사)

  • Huh, Ginn
    • Journal of the Korean Professional Engineers Association
    • /
    • v.24 no.6
    • /
    • pp.97-105
    • /
    • 1991
  • The cautious blasting works had been used with emulsion explosion electric M/S delay caps. Drill depth was from 3m to 6m with Crawler Drill ø70mm on the calcalious sand stone (soft-moderate-semi hard Rock). The total numbers of fire blast were 88 round. Scale distance were induces 15.52-60.32. It was applied to propagation Law in blasting vibration as follows. Propagation Law in Blasting Vibration (Equation omitted) where V : Peak partical velocity(cm/sec) D : Distance between explosion and recording sites(m) W : Maximum Charge per delay-period of eighit milliseconds o. more(kg) K : Ground transmission constant, empirically determind on the Rocks, Explosive and drilling pattern ets. b : Charge exponents n : Reduced exponents Where the quantity D / W$^n$ is known as the Scale distance. Above equation is worked by the U.S Bureau of Mines to determine peak particle velocity. The propagation Law can be catagrorized in three graups. Cubic root Scaling charge per delay Square root Scaling of charge per delay Site-specific Scaling of charge per delay Charge and reduction exponents carried out by multiple regressional analysis. It's divided into under loom and over 100m distance because the frequency is verified by the distance from blast site. Empirical equation of cautious blasting vibration is as follows. Over 30 ‥‥‥under 100m ‥‥‥V=41(D/$^3$√W)$\^$-1.41/ ‥‥‥A Over 100 ‥‥‥‥under 100m ‥‥‥V=121(D/$^3$√W)$\^$-1.56/ ‥‥‥B K value on the above equation has to be more specified for furthur understang about the effect of explosives, Rock strength. And Drilling pattern on the vibration levels, it is necessary to carry out more tests.

  • PDF