• Title/Summary/Keyword: TBM tunnel

Search Result 287, Processing Time 0.026 seconds

A Study on ground behavior of shield TBM lunching area during xcavation (Shield TBM 발진부 굴착에 따른 지반거동에 관한 연구)

  • O, Tae-Sang;Kim, Bae-Sik;Sin, Han-Cheol;Kim, Sang-Hwan
    • Proceedings of the KSR Conference
    • /
    • 2011.10a
    • /
    • pp.353-364
    • /
    • 2011
  • This paper presents the ground behaviour of shield TBM lunching area during excavation. In order to perform this study, a scaled model test was carried out in the 1/45 scale for a field tunnel in practice where the tunnel had about 7.8 m diameter at Seoul Metro Line 9 construction site. The test to simulate earth pressure balance (EPB) shield TBM tunnelling at the lunching area was conducted with the developed small scaled shield TBM machine. Measurements were performed during simulation of excavation for total jacking thrust force, ground displacements and pressures. Based on the analysis of simulation results, the stability of ground was verified and evaluated. In particular, the suitable reinforcement range and methods are also suggested. In addition, these results are useful for engineers and technicians to select suitable and serviceable machine operation parameters and reduce environmental influence at all stages of tunnel construction.

  • PDF

Analysis of aerodynamic characteristics for the selection of cross-section to the TBM railway tunnels (TBM 철도터널 단면선정을 위한 공기역학적 특성 분석)

  • Lee, Ho-Keun;Kang, Hyun-Wook;Kim, Hyun-Soo;Kim, Hong-Moon
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.15 no.6
    • /
    • pp.625-635
    • /
    • 2013
  • Although the TBM method is mainly adopted in overseas market including the Europe, etc, the method scarcely adopted in domestic market. For highly enhancing applications of the TBM method for railway, It is needed to select the optimal cross-section considering design elements of civil engineering and aerodynamic effects. Also, it is needed to establish plan of proper section as well as reviewing aerodynamic effects and consideration about civil engineering elements such as length of tunnel, speed of railway, height of whole lines and size of utility tunnel, etc. Even though it should be recently considered high-speed railway tunnels and required to be standard establishments in aerodynamic reviews, it is being applied to be criteria of inconsistent pneumatic analysis owing to be not related with domestic standards. In this study, therefore, we are willing to establishment of domestic and foreign aerodynamic standards and investigate correlation between optimal cross-section and aerodynamic effects of TBM railway tunnels.

Effect of utilizing pressurized ring beam system in modern rock TBM: I. Numerical study (현대식 Rock TBM에서 가압형 링빔의 효과 연구: I. 수치해석적 연구)

  • Kwak, Yun-Suk;Kang, Gi-Don;Kim, Do-Hoon;Lee, In-Mo
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.14 no.1
    • /
    • pp.55-77
    • /
    • 2012
  • A Modern Rock TBM is a tunnel excavation method combining the conventional tunnelling method with the mechanized tunnelling method. It is a hybrid system that excavates a tunnel with TBM and supports the ground by ring beam, wire mesh, rock bolt, shotcrete, i.e., conventional tunnelling method. In the Modern Rock TBM, a ring beam is similar to a steel rib in NATM in the way that uses H-beam. But using a ring beam is more effective than a steel rib because it is installed in a closed-circle. Therefore, improving the performance of the ring beam is a key factor for achieving tunnel stability. In this respect, this study introduces a pressurized ring beam that might be functioning more effectively by confining convergence during tunnel excavation. In order to verify the effect of the pressurized ring beam, a three-dimensional numerical analysis was conducted. The numerical analysis confirms an increase in the minimum principal stress and reduction in the plastic strain that triggers excessive displacement. The analysis result also indicates a decrease in the relative displacement occurring after installing the ring beam, and expansion in spacing between the ring beams.

Estimation of the excavation damage zone in TBM tunnel using large deformation FE analysis

  • Kim, Dohyun;Jeong, Sangseom
    • Geomechanics and Engineering
    • /
    • v.24 no.4
    • /
    • pp.323-335
    • /
    • 2021
  • This paper aims to estimate the range of the excavation damaged zone (EDZ) formation caused by the tunnel boring machine (TBM) advancement through dynamic three-dimensional large deformation finite element analysis. Large deformation analysis based on Coupled Eulerian-Lagrangian (CEL) analysis is used to accurately simulate the behavior during TBM excavation. The analysis model is verified based on numerous test results reported in the literature. The range of the formed EDZ will be suggested as a boundary under various conditions - different tunnel diameter, tunnel depth, and rock type. Moreover, evaluation of the integrity of the tunnel structure during excavation has been carried out. Based on the numerical results, the apparent boundary of the EDZ is shown to within the range of 0.7D (D: tunnel diameter) around the excavation surface. Through series of numerical computation, it is clear that for the rock of with higher rock mass rating (RMR) grade (close to 1st grade), the EDZ around the tunnel tends to increase. The size of the EDZ is found to be direct proportional to the tunnel diameter, whereas the depth of the tunnel is inversely proportional to the magnitude of the EDZ. However, the relationship between the formation of the EDZ and the stability of the tunnel was not found to be consistent. In case where the TBM excavation is carried out in hard rock or rock under high confinement (excavation under greater depth), large range of the EDZ may be formed, but less strain occurs along the excavation surface during excavation and is found to be more stable.

A probabilistic assessment of ground condition prediction ahead of TBM tunnels combining each geophysical prediction method (TBM 현장에서 막장전방 예측기법 결과의 확률론적 분석을 통한 지반상태 평가)

  • Lee, Kang-Hyun;Seo, Hyung-Joon;Park, Jeongjun;Park, Jinho;Lee, In-Mo
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.18 no.3
    • /
    • pp.257-272
    • /
    • 2016
  • It is usually not an easy task to counter-measure on time and appropriately when confronting with troubles in mechanized tunnelling job-sites because of the limitation of available spaces to perform those actions with the existence of disk cutter, cutter head, chamber and other various apparatus in Tunnel Boring Machine (TBM). So, it is important to predict the ground condition ahead of a tunnel face during tunnel excavation. Efforts have been made to utilize geophysical methods such as elastic wave survey, electromagnetic wave survey, electrical resistivity survey, etc for predicting the ground condition ahead of the TBM tunnel face. Each prediction method among these geophysical methods has its own advantage and disadvantage. Therefore, it might be needed to apply several geophysical methods rather than just one to predict the ground condition ahead of the tunnel face in the complex and/or mixed grounds since those methods will compensate among others. The problem is that each prediction method will give us different answer on the predicted ground condition; how to combine different solutions into a most reasonable and representative predicted value might be important. Therefore, in this study, we proposed a methodology how to systematically combine each prediction method utilizing probabilistic analysis as well as analytic hierarchy process. The proposed methods is applied to a virtual job site to confirm the applicability of the model to predict the ground condition ahead of the tunnel face in the mechanized tunnelling.

A Intercomparison on the estimating shield TBM tunnel face pressure through analytical and numerical analysis (이론해와 수치해석적 검토를 통한 쉴드TBM 막장압 산정 결과 상호비교)

  • Jun, Gy-Chan;Kim, Dong-Hyun
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.18 no.3
    • /
    • pp.273-282
    • /
    • 2016
  • This study estimates tunnel face pressure through existing 8 analytical equations and 3D numerical analysis, and compares and examines it. In general, the estimating tunnel face pressure of domestic shield TBM has been examined by a method according to analytical equation and empirical method, but numerical analysis is combined in a section passing complicated stratigraphic condition and special soil condition. Therefore, the researcher is to find a reliable method to examine of tunnel face pressure by confirming a correlation between tunnel face pressure estimated by equation and tunnel face pressure estimated by numerical analysis program. When tunnel face pressure is estimated, both analytical equation and numerical analysis were identically examined in soil conditions such as sandy soil and cohesive soil. In addition, existing analytical equation is used as equation, and 3D analysis copying construction process and shield tunnel as numerical analysis.

Waterproofing performance evaluation according to each waterproofing material due to segment construction error (세그먼트 시공오차에 따른 이음부 지수재별 방수성능 평가)

  • Heo, Seung-Mu;Jung, Hoon;Lee, Seok-Won
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.20 no.6
    • /
    • pp.1023-1037
    • /
    • 2018
  • The interest in the use of shield TBM (Tunnel Boring Machine) on the tunnel excavation has been increased rapidly in Korea. The shield TBM tunnel is generally designed as non-drainage tunnel. Consequently, if water leakage through the segment joints happens, big problems on the usage and stability of tunnel can be occurred. In this study, the variation of waterproof capacity of hydrophilic rubber waterstop and gasket, respectively by the construction error and excessive displacement of segment was studied. The test results show that hydrophilic rubber waterstop has favorable on the offset, however unfavorable on the gap. On the other hand, gasket has unfavorable on the offset, however favorable on the gap.

Development of performance assessment criterion for structures of shield TBM tunnel (쉴드 TBM 터널의 구조물 성능 평가 기준 개발)

  • Seong, Joo-Hyun;Lee, Yu-Seok;Hong, Eun-Soo;Byun, Yo-Seph
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.5
    • /
    • pp.553-561
    • /
    • 2015
  • In this study, the performance assessment criterion for reasonable maintenance of shield TBM tunnel was presented. The performance assessment items such as crack, leakage, breakage, spalling, exfoliation/detachment, efflorescence, quality condition, exposure of steel, carbonation, faulting step, bolts condition, drainage condition, ground condition, contact section condition and conduit condition were selected by analyzing domestic and foreign performance assessment criterions and investigating segment lining deterioration cases through the site investigation and in-depth inspection analysis result on the shield TBM tunnel. In addition, the reasonable weight using AHP (Analytic Hierarchy Process) were estimated.

Review of Technical Issues for Shield TBM Tunneling in Difficult Grounds (특수지반에서 쉴드TBM의 시공을 위한 기술적 고찰)

  • Jeong, Hoyoung;Zhang, Nan;Jeon, Seokwon
    • Tunnel and Underground Space
    • /
    • v.28 no.1
    • /
    • pp.1-24
    • /
    • 2018
  • The use of TBM (tunnel boring machine) gradually increases in worldwide tunneling projects. TBM machine are often applied to more difficult and complex geological conditions in urban area, and many problems and difficulties have been reported due to these geological conditions. However, in Korea, there is a lack of research on difficult grounds so far. This paper discussed general aspects of investigation method, and problems of TBM tunneling in difficult grounds. Construction cases that passed through the difficult grounds in worldwide were analyzed and the typical difficult grounds were classified into 11 cases. For each case, the definition and general problems were summarized. Particularly, for mixed ground and boulder ground, and fault zone, which are frequent geological conditions in urban area with shallow depth, classification system, investigation methods and major considerations were discussed, and proposed the direction of future research. This paper is a basic study for the development of TBM construction technology in difficult ground, and it is expected that it will be useful for related research and construction of TBM in difficult ground in the future.

The $Mer{\aa}ker$ TBM Project in Norway (노르웨이 메로케르 수력발전소의 TBM 굴착)

  • Park Yeonjun;Park Chulwhan
    • Tunnel and Underground Space
    • /
    • v.15 no.1 s.54
    • /
    • pp.22-27
    • /
    • 2005
  • This paper presents an article explaining a TBM project overall in Norway. The paper which published in Norwegian TBM Tunnelling by Norwegian Soil and Rock Eng. Assoc. in 1998, contains most of the items considered in TBM tunnelling. New powerplants, tunnels and dams have been built at Meraker in Central Norway. A total of 44 km of tunnels with cross sections varying from $7\;m^2\;to\;32\;m^2$ have been excavated in hard rock formation. Tunnel of 10 km with the 3.5 m diameter was excavated by a HP TBM in a year. his project gives the special attention to the TBM drive and equipment selection, including planning, site organization and performance.