• Title/Summary/Keyword: Piping support

Search Result 73, Processing Time 0.026 seconds

Thermal Expansion Measurement of Turbine and Main Steam Piping by Using Strain Gages in Power Plants (스트레인게이지를 활용한 발전소 터빈 및 주증기 배관의 열팽창 측정)

  • Na, Sang-Soo;Chung, Jae-Won;Bong, Suk-Kun;Jun, Dong-Ki;Kim, Yun-Suk
    • Proceedings of the KSME Conference
    • /
    • 2000.04b
    • /
    • pp.886-891
    • /
    • 2000
  • One of the domestic co-generation plants have undergone excessive vibration problems of turbine attributed to external force for years. The root cause of turbine vibration may be shan alignment problem which sometimes is changed by thermal expansion and external farce, even if turbine technicians perfectly performed it. To evaluate the alignment condition from plant start-up to full load, a strain measurement of turbine and main steam piping subjected to thermal loading is monitored by using strain gages. The strain gages are bonded on both bearing housing adjusting bolts and pipe stoppers which. installed in the x-direction of left-side main steam piping near the turbine inlet in order to monitor closely the effect of turbine under thermal deformation of turbine casing and main steam piping during plant full load. Also in situ load of constant support hangers in main steam piping system is measured by strain gages and its results are used to rebalance the hanger rod load. Consequently, the experimental stress analysis by using strain gages turns out to be very useful tool to diagnose the trouble and failures of not only to stationary components but to rotating machinery in power plants.

  • PDF

Reduction of Transient Vibration on $H_2$ Piping System for Generator Cooling in a Power Plant (화력발전소 발전기 냉각용 수소배관계 과도진동 개선)

  • Yang Kyeong Hyeon;Kim Sung Hwi;Cho Chul Whan;Bae Chun Hee
    • Proceedings of the Korean Society for Noise and Vibration Engineering Conference
    • /
    • 2002.11a
    • /
    • pp.360.2-360
    • /
    • 2002
  • There was the transient vibration on $H_2$ piping system fer cooling the generator in a power plant. We found it was resulted from resonance between the natural vibration of the piping system and exciting force from the turbine rotor by measurement and simulation test. We verified it would be changed the mode shape of the piping system by several simulation test for the structural modification of the piping system. (omitted)

  • PDF

Technology of Inspection and Real-time Displacement Monitoring on Critical Pipe for Power Plant (발전용 고온 배관의 점검 및 실시간 변위감시 기술)

  • Hyun, Jung-Seob;Heo, Jae-Sil;Cho, Sun-Young;Heo, Jeong-Yeol;Lee, Seong-Kee
    • Transactions of the Korean Society of Mechanical Engineers A
    • /
    • v.33 no.10
    • /
    • pp.1177-1186
    • /
    • 2009
  • High temperature steam pipes of thermal power plant are subject to a severe thermal range and usually operates well into the creep range. Cyclic operation of the plant subjects the piping system to mechanical and thermal fatigue damages. Also, poor or malfunctional supports can impose massive loads or stress onto the piping system. In order to prevent the serious damage and failure of the critical piping system, various inspection methods such as visual inspection, computational analysis and on-line piping displacement monitoring were developed. 3-dimensional piping displacement monitoring system was developed with using the aluminum alloy rod and rotary encoder sensors, this system was installed and operated on the high temperature steam piping of "Y" thermal power plant successfully. It is expected that this study will contribute to the safety of piping system, which could minimize stress and extend the actual life of critical piping.

FUZZY SUPPORT VECTOR REGRESSION MODEL FOR THE CALCULATION OF THE COLLAPSE MOMENT FOR WALL-THINNED PIPES

  • Yang, Heon-Young;Na, Man-Gyun;Kim, Jin-Weon
    • Nuclear Engineering and Technology
    • /
    • v.40 no.7
    • /
    • pp.607-614
    • /
    • 2008
  • Since pipes with wall-thinning defects can collapse at fluid pressure that are lower than expected, the collapse moment of wall-thinned pipes should be determined accurately for the safety of nuclear power plants. Wall-thinning defects, which are mostly found in pipe bends and elbows, are mainly caused by flow-accelerated corrosion. This lowers the failure pressure, load-carrying capacity, deformation ability, and fatigue resistance of pipe bends and elbows. This paper offers a support vector regression (SVR) model further enhanced with a fuzzy algorithm for calculation of the collapse moment and for evaluating the integrity of wall-thinned piping systems. The fuzzy support vector regression (FSVR) model is applied to numerical data obtained from finite element analyses of piping systems with wall-thinning defects. In this paper, three FSVR models are developed, respectively, for three data sets divided into extrados, intrados, and crown defects corresponding to three different defect locations. It is known that FSVR models are sufficiently accurate for an integrity evaluation of piping systems from laser or ultrasonic measurements of wall-thinning defects.

Fracture Resistance Characteristics of SA516-Gr.70 Steel Plate for RCS Piping Elbow and Support Skirt (원자로 냉각재배관 엘보우 및 서포트 스컷트용)

  • Son, Jong-Dong;Lim, Man-Bae
    • Journal of the Korean Society of Safety
    • /
    • v.21 no.4 s.76
    • /
    • pp.49-54
    • /
    • 2006
  • The evaluation of elastic-plastic fracture characteristic was investigated in ferrite steel SA 516- Gr70 used for reactor coolant piping elbow and support skirt of pressure vessels. This paper describes the effect of temperature on J-R curve characteristic of this material. The elastic-plastic fracture mechanics parameter J is obtained with unloading compliance method. The test method were analyzed according to ASTM E 813-89 and E 1152-89. Unloading compliance $J_{IC}$ tests were performed on 1 CT specimens at varied temperatures from $25^{\circ}C$ to about $400^{\circ}C$ using a high temperature extensometer. At all temperature, valid $J_{IC}$ measurements could be made and $J_{IC}$ decreased with increasing temperature. SEM fractography schematically illustrates microvoid initiation, growth and coalescence at the tip of a preexisting crack.

Development for Life Assessment System for Pipes of Thermal Power Plants

  • Hyun, Jung-Seob;Heo, Jae-Sil;Kim, Doo-Young;Park, Min-Gyu
    • KEPCO Journal on Electric Power and Energy
    • /
    • v.2 no.4
    • /
    • pp.583-588
    • /
    • 2016
  • The high-temperature steam pipes of thermal power plants are subjected to severe conditions such as creep and fatigue due to the power plant frequently being started up and shut down. To prevent critical pipes from serious damage and possible failure, inspection methods such as computational analysis and online piping displacement monitoring have been developed. However, these methods are limited in that they cannot determine the life consumption rate of a critical pipe precisely. Therefore, we set out to develop a life assessment system, based on a three-dimensional piping displacement monitoring system, which is capable of evaluating the life consumption rate of a critical pipe. This system was installed at the "M" thermal power plant in Malaysia, and was shown to operate well in practice. The results of this study are expected to contribute to the increase safety of piping systems by minimizing stress and extending the actual life of critical piping.

Thermal stress analysis for high pressure and temperature pipelines in ultra steam turbine (UST) system

  • Choi, Dae-keon
    • Bulletin of the Society of Naval Architects of Korea
    • /
    • v.52 no.2
    • /
    • pp.19-24
    • /
    • 2015
  • A reliable assessment and analysis of the condition of high pressure and temperature steam pipelines requires defining stress state, which will take into consideration not just the impact of internal pressure and temperature but all applied loads. For that, usage of modeling and numerical methods for calculation and analysis of stress state is essential. The main aim of piping stress analysis is to check the design of piping layout, which will allow simple, efficient and economical piping supports and provide flexibility to the piping system for loads and stresses. The piping stress analysis is carried out using CAESER II software. By using this software we can evaluate stresses, stress ratios, flange condition, support loads, element forces and displacements at each node and points. In this paper, only the maximum and minimum displacement results are tabulated, which is also shown in detail by an example of main steam pipelines of UST Main Engine System [1].

Safety Assessment of By-product Gas Piping after Design Change (부생가스 연료배관의 설계변경에 따른 안전성 평가)

  • Yoon, Kee Bong;Nguyen, Van Giang;Nguyen, Tuan Son;Jeong, Seong Yong;Lee, Joo Young;Kim, Ji Yoon
    • Journal of the Korean Institute of Gas
    • /
    • v.17 no.2
    • /
    • pp.50-58
    • /
    • 2013
  • Various process piping usually carries out high flammable and explosible gas under high pressure and high temperature. Due to frequent change of design and structure it becomes more complicated and compactly located. The safety management level is relatively low since it is considered as simply designed component. In this study a safety assessment procedure is proposed for complicated piping system around a mixing drum in which natural gas and by-product gases were mixed. According to ASME code, pipe stress analysis was conducted for determining design margin at some key locations of the piping. These high stress locations can be used as major inspection points for managing the pipe integrity. Sensitivity analysis with outside temperature of the pipe and support constraint condition. Possible effect of hydroen gas to the pipe steel during the previous use of the by-product gas was also discussed.

An Experimental Study on the Improvement of City Gas Buried Double Piping Integrity (도시가스 매설이중배관 건전성 향상에 관한 실험적 연구)

  • Lim, Hyung-Duk
    • Journal of the Korean Society of Industry Convergence
    • /
    • v.23 no.5
    • /
    • pp.757-763
    • /
    • 2020
  • City gas buried pipes are managed by corrosion protection to prevent corrosion. In the case of the press-in section, the double pipe and the main pipe may cause corrosion under the influence of stray current, which can shorten the life of the pipes. In addition, if the insulator is filled in the press-in section, the press-in section itself is a single structure, and can be directly affected by external impact, and when the surrounding ground subsidence occurs, the stress may be concentrated, resulting in serious consequences. In this study, a serration-type shock absorber in the form of a sliding support was proposed as a new buried double piping construction method using EPS. The serration-type shock absorber can contribute to the improvement of the integrity of the buried double piping, as it can utilize the gas piping's own ductility and stress distribution characteristics with proper anti-corrosion management and shock-absorbing material properties by preventing contact inside the buried double pipe. However, for application to ground piping, there remains a task to supplement the vulnerability against fire due to the characteristics of EPS materials.

A REAL-TIME PMIS BASED INDUSTRIAL CONSTRUCTION PROJECT MANAGEMENT SYSTEM

  • Kyusung Lee;Hojeong Song;Jaehyun Choi
    • International conference on construction engineering and project management
    • /
    • 2013.01a
    • /
    • pp.352-358
    • /
    • 2013
  • As amount of information in construction industry is growing, the role of information system in project management is becoming increasingly important. With the emerging IT application to the advancing construction industry, construction project management system with advanced technology has been progressed vigorously to improve construction productivity and management efficiency. Recently, a web-based Project Management Information System (PMIS) is developed to support decision-making process by efficiently managing project related information generated from various discipline. Many firms are in the process of developing the PMIS system or already have been applied the system to various projects. However, PMIS is still in its early stage of development to be applied at industrial plant construction projects that process management is significantly emphasized for the successful execution of the project. With the complexity of the industrial plant projects, the industry practitioners need to be able to visualize the construction schedule information to manage the project efficiently. This study suggests methodologies for improving PMIS specialized for industrial plant piping construction projects to estimate the baseline schedule and performance measurement more accurately by developing a framework for the piping construction projects. By using this developed system, the researchers expect that piping construction projects will be more efficiently managed on a real-time basis through measuring progress of piping at each and every state of progress milestone and provide management with opportunities to forecast the level of efforts required to execute the remaining work scope in a timely manner

  • PDF