UHF 부분방전 진단법에 의한 가스절연 개폐장치의 성능검증 (Performance Verification of the Gas Insulated Switchgear using UHF Partial Discharge Diagnosis Method)

  • 김정배;정재룡;김민수;송원표;김맹현;고희석;최인혁
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 2004년도 춘계학술대회 논문집 전기설비전문위원
    • /
    • pp.132-135
    • /
    • 2004
  • In generally, compared with VHF band, electromagnetic waves of UHF band have a low influence for external noise. We can detect the real abnormality with several pC in GIS using UHF method. Recently, it has applied to use the external UHF sensor attached on spacer to GIS of existing substation. In this paper, we firstly described the technique of the partial discharge measurement using frequency analysis and phase analysis in UHF band. Secondly, we presented the results of sensitivity, the relationship of dBm-pC and diagnosis of the reason of PD source by phase analysis. And then, we report the diagnosis result of partial discharge on 800kV GIS in domestic substation. rge diagnosis of GIS.

  • PDF

765kV 변전소 감시제어용 시범시스템 (Design of a Prototype Fibre Optic Based Monitoring and Control System for Future KEPCO's 765kV Substation)

  • 장문명;정상진;최종협;박종명
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1996년도 하계학술대회 논문집 B
    • /
    • pp.883-886
    • /
    • 1996
  • Instead of point-to-point hard wiring between substation yard equipments and SCADA RTU(Remote Terminal Unit), fibre optic cable will be used in the portion between Local Units and Central Unit in the future KEPCO 765kV substation. The connections between substation yard equipments and nearby Local Unit remain the same hard wiring. The new fibre optic system will provide security especially during ground faults and is immune to electrical noise. A prototype system will be manufactured and installed in the existing 154kV Yeosan Substation by the end of July this year and operated for one year. By incorporating the operation experiences acquired in the system, an improved system will be commercially applied to 765kV Shin-An-Seong Substation where 345kV GIS will be installed initially and act as the switching station in the year 1998. The system is composed of one Central Unit and several Local Units. The Central Unit is composed of two workstation level computers, one is in operation and the other backup, and a Communication Control Unit. The Local Unit uses the existing SCADA RTU technology and takes the form of a distributed one. Between the Communication Control Unit and Local Units, the fibre optic system with star-coupler is used.

  • PDF

GIS에서 UHF 부분방전 검출법의 교정방안 연구 (The Study of The Calibration Method for The UHF PD Detection in GIS)

  • 이우영;정진교;최영길
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1999년도 하계학술대회 논문집 E
    • /
    • pp.2290-2292
    • /
    • 1999
  • The Ultra-High Frequency(UHF) method for detecting a partial discharge in Gas-Insulated Substation(GIS) has some advantages compared to a conventional method(IEC 270) but there is a shortage in view of a quantitative analysis. Therefore, this paper describes the implementation of a calibrator and the calibration process based on it. And its characteristics are confirmed through the experiment using the 362kV GIS chamber.

  • PDF

Measurement of Transient Electric Field Emission from a 245 kV Gas Insulated Substation Model during Switching

  • Rao, M. Mohana;Thomas, M. Joy;Singh, B.P.
    • Journal of Electrical Engineering and Technology
    • /
    • 제2권3호
    • /
    • pp.306-311
    • /
    • 2007
  • The transient fields generated during switching operations in a Gas Insulated Substation (GIS) are associated with high frequency components in the order of few tens of MHz. These transient fields leak into the external environment of the gas-insulated equipment and can interfere with the nearby electronics. Measurements of the transient fields are thus required to characterise the interference caused by switching phenomena in such substations. In view of the above, E-field emission measurement during a switching operation has been carried out for a 245 kV GIS model, using a resonant dipole antenna and D-dot sensor. The characteristics of the E-fields i.e., frequency spectra and their levels have been analysed and are reported in the paper. Suitability of the measurements has been confirmed by comparing frequency spectra of the measured and computed transient fields.

345 kV급 GIS 차단기의 고유과도회복전압 특성 검토 (TRV Characteristics of 345 kV GIS Circuit Breaker)

  • 우정욱;심응보;강지원;강연욱
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1998년도 추계학술대회 논문집 학회본부 C
    • /
    • pp.962-965
    • /
    • 1998
  • The circuit breakers had been withdrawn from 345 kV SIC substation. because these were made following the old IEC requirement(IEC 56; TRV rating) and insufficient current rating(2,000 A) for the system requirement(4,000 A). And, they are going to be reused at 345 kV UR substation and SJS switching section. This paper deals with the TRV(temporary recovery voltage) analysis results in order to reuse them. The analysis results are satisfied with the IEC requirements of RRRV(Rate of Rise of Recovery Voltage) and peak voltage($U_c$) from 2000 to 2010.

  • PDF

154 kV GIS의 PT 철공진 소손사례와 원인규명 (A analysis result on the PT ferroresonance at 154 kV GIS substation)

  • 우정욱;심응보;김승규
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1999년도 하계학술대회 논문집 E
    • /
    • pp.2076-2079
    • /
    • 1999
  • This paper describes the analysis results on the PT ferroresonance at 154 kV GIS (gas Insulated substation by EMTP (Electro-magnetic Transient Program). We had simulated the PT ferroresonance between a potential transformer(PT) and an open circuit breaker's grading capacitance. The ferroresonance leads to very large power frequency overvoltages on PT bus and subsequent insulation failure. The large power can be supplied to the PT by the high voltage on the opened circuit due to the grading capacitance and equivalent capacitance of the buses during the ferroresonance. The damping circuit connected on the secondary winding were considered in the model. The actual countermeasure include a saturable inductor and a resistor series-mounted, but the 2 ohms of damping resistance was used in the computational model.

  • PDF

변전기기 예방진단 시스템의 적용 - 765kV 변전소 예방진단 시스템 (The Application of Preventative and Diagnostic System for 765kV Substation)

  • 권동진;최인혁;유연표;정시환;최영준;최대희;김경근
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 2000년도 하계학술대회 논문집 C
    • /
    • pp.1885-1887
    • /
    • 2000
  • In this paper we introduce preventative and diagnostic systems developed to prevent substations from accidental fault of electric power transmitting apparatus. We propose monitoring and diagnostic system for ultra high voltage GIS and main transformer of 765kV substations as an example of preventative and diagnostic techniques being applied in Korea. We also present a guideline to construct and manage an expert system for this purpose. Finally, an engineering solution as a substation management support system is proposed.

  • PDF

800kV GIS 개발을 위한 기본연구 (The Basic Study on 800kV GIS Development)

  • 김정배;양대일;송원표;이철현;노철웅
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1995년도 하계학술대회 논문집 C
    • /
    • pp.1341-1343
    • /
    • 1995
  • The maximum transmission voltage in our country is going to change 345kV into 765kV owing to the increase of Electrical Power Demand and power System Stability. Our company is developing 800kV GIS and 765kV Transformer which are main equipments in 765kV substation. This paper describs the specification on 800kV GIS which we prepared for 800kV 8,000A 50kA GIS development. This specification is supported by Public Standards and Data. And, we are designing the 800kV GIS on this specification and drawing up the 800kV GIS layout for type test.

  • PDF

열전달 계수의 변화를 고려한 초고압 GIS 모선의 온도 상승 예측 (Temperature Rise Prediction of Busbar of EHV GIS Considering Variation of Heat-Transfer Coefficient)

  • 김현훈;한성진;주수원;정진교;이병윤;박경엽
    • 대한전기학회논문지:전기기기및에너지변환시스템부문B
    • /
    • 제49권5호
    • /
    • pp.313-319
    • /
    • 2000
  • In order to design the current carrying conductor for GIS, it is important to predict temperature-rise when rated current flows in the bus bar. However, it is not easy to apply the correct heat transfer coefficient on the boundary between different material for the thermal analysis. In this paper, the heat transfer coefficient which depends on parameters such like material constant, model geometry as well as ambient temperature, was calculated by analytic method. The calculated coefficient is used for the temperature rise prediction by F.E.M. The results show good agreement with experimental data.

  • PDF

154kV급 인텔리전트 변전소 구축 (Construction of Intelligent Substation for 154kV Class)

  • 정영환;양대일;김정배;송원표;최인혁;김정호;이동일
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 2005년도 제36회 하계학술대회 논문집 A
    • /
    • pp.33-35
    • /
    • 2005
  • We perform intelligent substation construction of 154kV class with KEPRI. The intelligent substation is build in Gochang 765kV testing facility and consists of electronic instruments, digital control panel, remote monitoring and diagnosis system and digital relay system. Rogowski coil type CT(RCT) and capacitive voltage divider(CVD) are applicable for instrument transformer of conventional type. Digital control panel(DCP) replaces local panel which is drived by mechanical operation. For monitoring condition of GIS and TR, various sensors are used. In this paper, we report the synopsis and the progress state of project.

  • PDF