• Title/Summary/Keyword: Excavation Works

Search Result 128, Processing Time 0.022 seconds

A Study on the shrine plan composition from the Ungjindan excavation works (웅진단 발굴에 따른 사당의 평면구성에 관한 연구)

  • Kim, Sang-Tae
    • Korean Institute of Interior Design Journal
    • /
    • v.21 no.6
    • /
    • pp.186-193
    • /
    • 2012
  • This study is to reveal the periodical form of the 4 staged building sites with the size and the site composition of the master plan and floor plan of the Ungjindan (altar) from the Ungjindan excavation works in 2011. In order to project the research results aiming to the purpose of the study, the basic study was done with collecting data about shrine architecture for its architectural characteristics and case studies with ancestral facilities such as the Ak hae dok (national-level ancestral ritual to the big mountain, ocean and river) to understand the exact form of the site plan and architectural composition elements through the general information and excavation status. In addition, with the current situation and information from the excavation works the planned measurement scale will be calculated in inference for the size of the construction by stages and speculate the floor plan composition of the shrine architecture.

  • PDF

Deformation Behaviors of Temporary Tieback Wall during Excavation Works (현장계측과 수치해석을 이용한 가설 흙막이 구조물의 변형특성 연구)

  • 김종우
    • Tunnel and Underground Space
    • /
    • v.5 no.3
    • /
    • pp.223-229
    • /
    • 1995
  • During excavation works for underground facilities, temporary tieback wall with earth anchor system was investigated for safety's sake. An excavation 9.7 meter deep was monitored by slope inclinometer in twelve measuring points. Instrumented lateral displacements of the wall during 177 days are represented. Especially, lateral displacements of the two positions under completely different condition are compared to investigate the effect of backfilling between soldier pile and the soil behind wall. The deformation behaviors of the wall according to both depth and elasped time are discussed. Finally, a numerical analysis by the program FLAC was performed, and calculated displacements are compared to measured ones.

  • PDF

Optimum Construction Duration for Road Tunnel Excavation Works (도로터널 굴착공사의 적정공기 판단기준)

  • Kim, Ha-Na;Kim, Dae Young;Kim, Dae-Young;Jeong, Seong-Chun;Huh, Young-Ki
    • Journal of the Architectural Institute of Korea Structure & Construction
    • /
    • v.34 no.4
    • /
    • pp.59-64
    • /
    • 2018
  • Construction schedule acceleration due to unreasonable construction planning frequently leads to construction accidents. In order to avoid such inevitable acceleration and to ensure safety in construction sites, there is a need for objective standards to determine appropriate construction duration for each construction process earlier in the process. In order to achieve the goal, intensive experts interviews were firstly conducted to identify candidate drivers affecting construction schedule of road tunnel excavation works. Then, a total of 34 field data was collected from on-going sites to analyze. It was found that actual excavation length per one day on site is varied mostly by Rock Mass Rating(RMR) types from various statistical analyses. Therefore an one-way table of excavation length per a day by RMR types were presented in a form of percentile. The results will help industry experts determine the most appropriate construction schedule for the works, which eventually lead to a zero accident site in many ways.

Estimation of Suspended Solids Concentration Caused by Stream Bed Excavation Works through the Application of the Fickian Diffusion Model (Fick 확산 모형을 이용한 하상 굴착 공사로부터의 부유물질 농도 산정)

  • An, Myeong-Gil
    • Journal of Korea Water Resources Association
    • /
    • v.30 no.6
    • /
    • pp.621-628
    • /
    • 1997
  • Excavation works on stream beds have been done for various reasons including aggregate collection, sediment dredging, bridge constructions, or laying pipes under the ground. These activities may cause significant loadings of SS (suspended solids) resulting in water pollution and other detrimental effects to the surrounding environment. This research investigates application potential of a fickian diffustion model, derived from two dimensional advection-diffusion equation through some simplifying assumptions, as a planning tool for the estimation of SS loadings from excavation works and evaluation fo pollution prevention measures in case that sophisticated numerical simulation models are not applicable due to various practical reasons. Through a case study of the Juncheon stream in the Donghae City on the Kangwondo Province, this study demonstrates applicability of the fickian diffustion model as a practical method for the preliminary estimation of Ss loadings from excavation works and evaluation of performance of fabrics made of synthetic fiber for the reduction of downstream SS concentration with deficient field data.

  • PDF

An Experimental Study on the Reinforcement Effect of Installed composite stiffener on Earth Retaining Walls using Stabilizing Piles (억지말뚝 흙막이공법에 설치된 복합버팀의 보강효과에 관한 실험적 연구)

  • Kim, Tae-Hyo;Im, Jong-Chul;Park, Lee-Keun;Kwon, Joung-Keun
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2008.03a
    • /
    • pp.1224-1239
    • /
    • 2008
  • The earth retaining walls using stabilizing piles can be applied to shallow excavation works without any stiffener. But, It demends a variety of installed composite stiffener on the earth retaining walls when it is installed as deep excavation works. Because, it causes an excessive displacement of walls. This research tried to overcome the problems created by the above issues and intended to apply the composite stiffener. The model test, focused on the effect of installed composite stiffener, measured the bending stress with stabilizing piles and walls, the settlement of earth surface, the displacement of walls for a step excavation and an increase in strip load. With the test results and soil deformation analysis, the reinforcement effect(relating to control displacement and earth presure) was analyzed in a qualitative and quantitative manner. It is expected to overcome a deep excavation works.

  • PDF

Influence Analysis of Deep Excavation on the Nearby Undercrossing Road by Centrifuge Model Test

  • Huang, Hongwei;Xie, Xiongyao
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2008.10a
    • /
    • pp.395-406
    • /
    • 2008
  • An excavation with the depth of 32.7m will be constructed as a ventilation shaft in Shanghai metro Line 9. The excavation induced effect on a nearby undercrossing road in operation must be properly evaluated. A centrifuge model test was conducted to study the impact of deep excavation on this existing undercrossing. Detail simulation works are described in this paper. The excavation steps could be simulated in the no-stop state of centrifuge machine. And induced settlements of the undercrossing road in both parallel and vertical directions were analyzed. Protective partition cement soil piles were also simulated in the tests. Simulation test shows deep excavation has a great influence on undercrossing road and the partition pile can obviously deduce the influence.

  • PDF

Comparison of Displacement of the Braced Retaining Wall by Developed Elasto-Plastic Analysis (개선된 탄소성 해석을 이용한 버팀지지 흙막이벽의 거동비교)

  • Shin, Jin-Whan;Kim, Dong-Shin
    • Journal of the Korean Society of Safety
    • /
    • v.19 no.2
    • /
    • pp.112-118
    • /
    • 2004
  • Recently, when being constructed the large structures, the deep excavations have performed to utilize the underground space. As the ground excavation is deeper, the damage of the adjacent structure and the ground is frequently occurred. the Analysis of the retaining structures is necessary to safety of the excavation works. There are many methods such as elasto-plastic theory, FEM, and FDM to analyze the displacement of the retaining structure. In this thesis, GEBA-1 program by the Nakamura-Nakajawa elasto-plastic method was developed. The lateral displacement of the wall was analyzed by the developed program GEBA-1, SUNEX, and EXCAD, and compared with the measured displacement bye the Inclinometer. The monitored fields were three excavation work site in S-I, S-II, and S-III area. Excavation method of each site is braced retaining wall using H-pile. Excavation depth is 14m, 14m, and 8.2m.

Decision Support Tool for Excavation Operation using Genetic Algorithms

  • Lee, Ung-Kyun;Kang, Kyung-In;Cho, Hun-Hee
    • Architectural research
    • /
    • v.8 no.2
    • /
    • pp.43-48
    • /
    • 2006
  • The appropriate fleet estimation of the excavation equipment is a major factor in the determination of the cost and time requirements of a project. But the decision of what kind of equipment selected is often based on heuristic methods or trial and error in Korea. Thus, this study proposes a prototype model that uses genetic algorithms to select fleet estimation of loaders (backhoe) and trucks used in excavation work. To verify the applicability of this model, the case study was performed. And the result of the genetic model was compared with that of the trial & error method. The use of the genetic model suggested this study required 44days, 2 units of backhoes, 7 units of trucks, and a total cost of 171,839,756 won. With the estimated fleet number of equipment, the minimum cost of excavation work can be calculated, taking account of the time-cost trade-off. By utilizing this prototype model, the efficiency of excavation work can be improved.

Study on Load Carrying Capacity of Top Down Prefounded Columns (Top Down 선기둥의 지지력 산정방법에 관한 연구)

  • Hwang Hee-Sun;Rhim Hong-Chul
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2006.05a
    • /
    • pp.137-140
    • /
    • 2006
  • As underground construction is a large component of the cost of construction and a term of works in Top-Down construction, it is important to reduce the term of works in underground construction. The purpose of this study is to analyse buckling stress and load of prefounded columns as the process of excavation is changed, and propose a suitable process of excavation to increase the speed of works. When several floors are excavated, the valid buckling length of profounded column is increase and allowable buckling stress is decreased. The result shows that all columns are safe in buckling down to B3th story whether 2 stories or 3 stories are excavated straightly. However, several columns are not safe from B4th story when 2 or 3 stories are excavated straightly. With these results, a process can be designed that first B3 stories are excavated straightly, and then excavate B4th story putting concrete on B1st and B2nd story.

  • PDF

Earth Retaining Structure Using a Row of piles during Shallow Excavation in Soft Clay (연약점성토지반의 얕은 굴착시 줄말뚝을 이용한 흙막이공)

  • 홍원표;윤종민;송영식
    • Journal of the Korean Geotechnical Society
    • /
    • v.16 no.1
    • /
    • pp.191-201
    • /
    • 2000
  • In this study, the earth retaining structure using a row of piles considering plastic flow of the ground is suggested for shallow excavation works instead of conventional anchored sheet-pile wall method in the marine clays with high groundwater level. The behavior of the earth retaining structure using a row of piles is precisely observed during excavation by inclinometer and piezometer installed in opposite to the excavation side. As a result of field measurement, it was found that the behaviors of the piles and the soil were influenced mainly by slope of excavation face, interval ratio of piles, fixity condition of pile head, and stability number, etc. The earth retaining structure using a row of piles is ascertained for workability, stability, and economical construction on the soft ground having no adjacent structures.

  • PDF