Assessment of the Impacts of "pre-Compensation and Post-Construction Policy" on Public Construction Projects (선보상-후시공 제도의 공공건설사업 파급효과 분석)

  • Kim Sang-Bum;Choi Jeong-Won
    • Korean Journal of Construction Engineering and Management
    • /
    • v.5 no.6 s.22
    • /
    • pp.245-254
    • /
    • 2004
  • Pre-compensation and post-construction policy'(PCPC) is a part of $\ulcorner$public project performance improvement policies (PPPIP)$\lrcorner$ whose purpose is to reduce the construction project cost by $20\%$. This research focuses on measuring the quantitative and qualitative impacts of PCPC public construction project. The evaluation of PCPC was conducted using five performance indices which are measuring performance improvement in terms of project cost and schedule. The analysis results show that implementation of this policy reduced $4.8\%$ of public construction project budget while playing a positive role in shortening the project schedule.