A Study on the Fire Risk of ESS through Fire Status and Field Investigation (화재현황 및 현장조사를 통한 ESS의 화재 위험성 연구)

  • Park, Kwang-Muk;Kim, Jae-Hyun;Park, Jin-Yeong;Bang, Sun-Bae
    • Fire Science and Engineering
    • /
    • v.32 no.6
    • /
    • pp.91-99
    • /
    • 2018
  • Recently, the spread of ESS in Korea has increased and a fire accident has also occurred. By July 2018, there were a total of 7 cases. All 7 cases were ESS systems consisting of lithium-ion batteries and were burned down. Both the automatic fire extinguisher and the fire department were not able to digest. In this paper, the characteristics of ESS fire are analyzed based on recent ESS fire situation and field investigation, and the cause of fire is divided into environmental, electrical and thermal factors. As a result, it was found that the ESS fire was correlated with the installation environment of the system. In the domestic and overseas lithium ion battery test standard and ESS facility standard survey, the trends and differences of domestic and overseas facilities standards were identified. Based on the fire status and field investigationy, and domestic and overseas facility standard survey, measures were suggested to prevent and prevent the spread of fire in ESS fire.

A Study on the Development of Fire Extinguishing Agent and Extinguishing System for ESS Fire (ESS 화재전용 소화약제 및 소화시스템 개발에 관한 연구)

  • Lee, Yeon-Ho;Lee, Joo-Hyung;Kim, Soo-Jin;Chon, Sung-Ho;Choi, Byoung-Chul;Oh, Seung-Ju;Kim, Si-Kuk
    • Fire Science and Engineering
    • /
    • v.34 no.2
    • /
    • pp.147-155
    • /
    • 2020
  • This paper presents a study on the development of a fire extinguishing agent and extinguishing system for an energy storage system (ESS) fire. The fire extinguishing agent designed to extinguish an ESS fire is a highly permeable fire extinguisher that reduces the surface tension and viscosity while bringing about cooling action. This is the main extinguishing effect of this type of wetting agent, which displays the characteristics of fire extinguishing agents used for penetrating the battery cells inside the ESS module. For the fire extinguishing system, a local application system was designed to suppress fire on a rack-by-rack basis. A 360° rotating nozzle was inserted into the rear hall of the ESS module, and general nozzles were installed in the rack to maximize the fire extinguishing effect. The fire extinguishing agent was strongly discharged by virtue of the gas release pressure. Experiments on fire suppression performance with ESS module 1 unit and module 3 units showed that all visible flames were extinguished in 8 s and 9 s, respectively, by the fire extinguishing agent. In addition, based on confirming reignition for 600 s after the fire extinguishing agent was exhausted, it was confirmed that the ESS fire was completely extinguished without reignition in all fire suppression performance experiments.

A Study to Prevent the Occurrence and Spread of Fire Caused by ESS Storage (ESS 저장창고로 인한 화재의 발생 및 확산방지를 위한 연구)

  • Shin, Joung Hyeon;Jo, Su Yeon;Kim, Geon-Woo;Jung, Ui In;Kim, Bong Joo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2021.11a
    • /
    • pp.140-141
    • /
    • 2021
  • ESS refers to a device that can store electrical energy produced by renewable energy generation, etc. and use it when necessary. Lithium-ion batteries are composed of high energy density and combustible electrolyte, so once ignited, it is difficult to extinguish. Many studies have been conducted to solve the problem of the battery itself as the cause of the fire. However, there is also a problem with the structure in which ESS(hereinafter referred to as ESS storage) is installed itself. Therefore, the purpose of this paper is to provide data to solve the problems related to ignition and fire spread due to the problem of ESS storage. In summer, the internal temperature of the ESS storage rises due to solar radiation to trigger a fire, so it is necessary to prevent an internal temperature rise due to solar radiation. Research on standards, materials used, structures, etc. for ESS storage and new regulations are required.

  • PDF

Analysis of the Cell Balancing Effect on the ESS Fire by Simulating the Euljiro 3-ga Subway ESS (을지로 3가 지하철 ESS를 모의한 ESS 화재에서 Cell Balancing이 미치는 영향성 분석)

  • Yun, Sang-Sun;Kee, Seok-Cheol
    • The Transactions of the Korean Institute of Power Electronics
    • /
    • v.25 no.3
    • /
    • pp.219-226
    • /
    • 2020
  • Given the change in the energy market, large energy storage systems (ESS) is rapidly entering the market. In this rapid spread, fire accidents are becoming an issue. This study attempts to approach the fire from the system point of view to analyze the problems caused by bonding from different perspectives. Moreover, to conduct this study, the fabrication of real objects is dangerous, which needs to be verified through simulation. In this study, we approach the cause of fire that occurs in large-capacity ESS from the system perspective. We focus on determining the effects of cell balancing performed on the BMS after charging. Thus, we analyze the cell balancing behavior and the linkage risks to the various stacks. The study also explores why no fire occurs during 70% operation.

A Study on Economic Evaluations of ESS Load Test Device for Field Load Test in Fire-fighting Emergency Generator Systems (소방용 비상발전기의 현장부하시험을 위한 ESS 부하시험장치의 경제성평가에 관한 연구)

  • Choi, Seung-Kyou
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.21 no.9
    • /
    • pp.380-386
    • /
    • 2020
  • The ESS load test device (ELTD) can store and exchange electrical energy during the load test of an emergency generator. On the other hand, it is difficult to commercialize ELTDs based on Li-ion batteries because of the high initial cost, which is higher than a load bank test. If the trade of electrical energy stored in ELTD during the test of an emergency generator is considered, it may be possible to commercialize the ELTD. Therefore, this paper proposes an economic model of ELTD composed of the costs and benefits by considering electrical energy trade to perform accurately economic evaluations of an ELTD. From the simulation results of the economic evaluations of an ELTD and the load bank method, it was found that the commercialization of ELTD is possible when the trade in electrical energy in ELTDs is considered.

A Study on Protection Method of Energy Storage System for Lithium-ion Battery Using Surge Protection Device(SPD) (SPD를 이용한 리튬이온전지용 전기저장장치의 보호방안에 관한 연구)

  • Hwang, Seung-Wook;Lee, Hu-Dong;Tae, Dong-Hyun;Rho, Dae-Seok
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.21 no.4
    • /
    • pp.568-574
    • /
    • 2020
  • Recently, the installation of energy storage systems (ESSs) that have a range of functions, such as power stabilization of renewable energy sources, demand control, and frequency regulation, has been increasing annually. On the other hand, since the fire accident of ESS occurred at Gochang Power Test Center in August 2017, 29 fire accidents with significant property losses have occurred, including the Gyeongsan substation and Kunsan PV power plant. Because these fire accidents of ESS are arisen regardless of the season and capacity of ESS, an analysis of the fault characteristics in ESS is required to confirm the causes of the fire accidents accurately and ensure the safety of the ESS. This paper proposes the modeling of ESS using PSCAD/EMTDC S/W to identify the fault characteristics and ensure the safety of the ESS. From the simulation results of fault characteristics based on various scenarios, it is clear that the insulation of ESS may be breakdown due to the largely occurring CMV (common mode voltage). Furthermore, the CMV between the PCS and battery can be reduced, and the insulation breakdown of ESS can be prevented if an SPD (surge protect device) is installed in the battery and PCS sides, respectively.

Fire Protection, Facility Improvement and Protections for FR ESS (FR ESS 의 화재 예방, 설비 개선 및 보호 기술 현장 적용)

  • Lee, Ilyong
    • KEPCO Journal on Electric Power and Energy
    • /
    • v.7 no.1
    • /
    • pp.35-43
    • /
    • 2021
  • 한국전력공사 전력연구원에서는 2018 년 고창 전력시험센터에서 최초 화재 발생 이후, ESS 시스템의 화재 발생 원인에 대한 분석 및 실증시험을 수행하였으며, 이를 통해 현장에서 화재 발생을 최소화할 수 있는 다양한 설비개선안을 도출하였다. 도출된 설비개선안을 통하여 기술지원 요청 부서에서는 전국의 모든 현장 적용을 시행하고 있으며, 이를 통하여 한전이 보유한 모든 ESS 설비는 2021 년 내재 가동될 예정이다.

An Experimental Study on Fire Risks Due to Overcharge and External Heat of ESS Lithium Battery (ESS 리튬배터리의 과충전 및 외부수열에 따른 화재위험성에 관한 실험적 연구)

  • Kim, Si-Kuk;Choi, Su-Gil;Jin, Se-Young;Bang, Suck-Sung
    • Fire Science and Engineering
    • /
    • v.33 no.4
    • /
    • pp.59-69
    • /
    • 2019
  • The present article relates to an experimental study on fire risks due to overcharge and external heat of ESS lithium battery. According to the experimental results of overcharge, ignition occurred as combustible gas and smoke was slowly increased after occurrence of venting, and an explosive combustion form accompanied by flame eruption and sparks was displayed as charged energy is rapidly discharged in an instant. On the other hand, according to the experimental results of external heat, as a tremendous amount of combustible gas and smoke was ignited following being discharged after occurrence of vent, the charged energy itself was rapidly reduced due to the discharged energy so that a passive combustion form was observed when compared with overcharge after occurrence of flames. According the analysis results of fire damage characteristics, differences between external heat (External flame) could be found through visual and X-ray inspections. Namely, while inside electrode plate was completely destroyed and perforation of the electrode plate was observed in the case of overcharge, fire damage of the electrode plate was not severe maintaining the form in the case of external heat.

Study on Improvement of Dew Point within ESS Container for Fire Prevention (컨테이너형 ESS 화재방지를 위한 내부 응결점 개선 관한 연구)

  • Kim, Woonhak;Kang, Seokwon;Shin, Giseok
    • Journal of the Society of Disaster Information
    • /
    • v.15 no.2
    • /
    • pp.165-174
    • /
    • 2019
  • Purpose: In this study, we investigated the relationship between the causes of ESS container fire accidents. Method: We investigated the possibility of reducing the container fire accident by improving the air environment of the container which is necessary for improvement of these. Result: Through this study, we can be confirmed that the condensing condition of water in the air caused by the difference of internal and external temperature is improved and the dielectric strength of BMS board is reduced. Conclusion: The correlation between the BMS board condensation and the dielectric strength was confirmed.

Profitability Analysis of ESS with PV Generation (PV연계형 ESS의 설치 규모에 따른 수익영향)

  • Kim, Chang Soo;Choi, Sang Bong
    • Current Photovoltaic Research
    • /
    • v.8 no.3
    • /
    • pp.86-93
    • /
    • 2020
  • The investment in solar and wind generation is rapidly increasing with government's renewable expansion policy and Renewable Portfolio Standard (RPS). Since the large penetration of solar and wind generation increases the variability and uncertainty of supply and demand balance in power system, the government is pursuing the policy of supplying energy storage system (ESS) linked to renewable energy. ESS contributes to the ease of transmission and distribution grid by shifting PV generation from daytime to evening hours. Recently, the declining market price of REC as ESS incentive, policies to cut down incentives and limited ESS storage due to fire events lead to the aggravation of long-term profitability, thus working as a barrier of ESS spreading. In this study, the factors affecting the profit of ESS are analyzed and brief indicators are derived. Based on the indicators, the profit changes are analyzed considering the variation of REC market price and REC incentive weights. Based on the profit change with respect to the increase of ESS capacity, economical ESS installation capacity is suggested.