시멘트 액체방수 공사의 작업조 기반 품셈을 위한 생산량 및 노무량 분석 (Analysis of Actual Labor and Productivity for Based Work Crew Standard of Cement Liquid Watertight Construction)

  • 하기주;최민권;이동렬;하민수;하재훈;김외곤
    • 한국건축시공학회:학술대회논문집
    • /
    • 한국건축시공학회 2009년도 춘계 학술논문 발표대회 학계
    • /
    • pp.171-174
    • /
    • 2009
  • The standard estimation system, used to estimate the predetermined cost of construction work, is measured by the standard and typical construction methods and field conditions. And the standard estimation system is applied to basic data for the measuring of construction cost, such as the consumed quantity of material, labor hours, and machinery cost. However it does not reflect sufficiently for the diversity and reality of constructions work Therefore, this study is recognized the necessity of new cost estimation models for the rational construction cost estimation. To improve estimation technique and construction ability, it was analyzed labor hours, production volume based on the work crew in construction work.