• Title/Summary/Keyword: 해체공법

Search Result 106, Processing Time 0.029 seconds

A Case Study on Partial Explosive Demolition of a Large-Section Turbine Foundation Structure (대단면 터빈 기초 구조물의 부분발파해체 시공사례)

  • Park, Hoon;Suk, Chul-Gi;Nam, Sung-Woo;Noh, You-Song
    • Explosives and Blasting
    • /
    • v.34 no.1
    • /
    • pp.19-28
    • /
    • 2016
  • The number of industrial structures that must be demolished due to functional and structural deterioration has been increased. There is an increasing application of explosive demolition or explosive demolition combined with mechanical demolition to minimize temporal and spatial environmental hazardous factors created during the process of demolition. In this case study, to demolish the turbine foundation structure, which is a large-section reinforced concrete structure, the parital explosive demolition thchnique was conducted. As a result of the partial explosive demolition, the overall crushing of the blasting sections of beam-column joints structure with haunched beams and second-floor columns about the turbine foundation was satifactory, and the explosive demolition was completed without causing any damage to surrounding facilities.

Case Study of Explosive Demolition of Airport Structure (김해국제공항 구 국제선 청사 발파해체 시공 사례)

  • 이윤재;송영석;정민수;권오성;강대우
    • Explosives and Blasting
    • /
    • v.21 no.3
    • /
    • pp.37-48
    • /
    • 2003
  • 김해 국제공항 2단계 확장 공사 중 구 국제선 청사 발파해체공사"는 5.5초의 기폭시차를 두고 약 7초간에 구조물의 붕괴를 유도하여, 단기간에 안전하며 최대의 효율을 낼 수 있는 발파해체공법을 적용하여 시공하였다. 이에 따라 발파해체공사의 공법, 공정, 세부 현황 및 결과, 발파공해영향권에 대해 분석, 평가 하였다. 구 국제선청사 구조물은 3층 높이로 저층 구조물에 해당하고 구조물의 특성상 Span 간격이 길고 충고가 높다. 또한 지반이 액상한계점 상태까지 도달하여 구조안전진단 결과 위험등급인 D등급으로 판정되었다. 본 대상건물과 같이 충고는 낮지만, 구조 안전성 측면에서 위험 요소를 가지고 있으므로 발파공법을 적용하여 해체를 실시하였다.

A Case Study on Explosive Demolition of a the Industrial Stack (산업용 연돌 발파해체 시공사례)

  • Park, Hoon;Nam, Sung-Woo;Noh, You-Song;Kim, Suk-Weon;Suk, Chul-Gi
    • Explosives and Blasting
    • /
    • v.40 no.2
    • /
    • pp.15-24
    • /
    • 2022
  • Recently, the demand of demolition for the unnecessary industrial structure is increasing due to deterioration tendency and the issue of demolition is becoming a major highlight. The restoration of the dismantled industrial site to its original natural state was currently underway. This execution case was intented to describe an application of the felling method one of the explosive demolition method to the demolition of the industrial stack. This stack was 150m high, a composite structure in which the outer wall of the stack was a reinforced concrete shell structure and internal stovepipe was a steel shell structure. As as result of the explosive demolition, the stack had collapsed precisely according to estimated direction. And the explosive demolition was completed without causing any damage to surrounding facilities.

Simulation of Blasting Demolition Using Three-Dimensional Bonded Particle Model (삼차원 입자결합모델을 이용한 구조물 해체발파 모사 연구)

  • Shin Byung-Hun;Jeon Seok-Won
    • Explosives and Blasting
    • /
    • v.23 no.1
    • /
    • pp.65-77
    • /
    • 2005
  • Reflecting the fact that there are increasing number of old high-story apartment structures in urban area, it is expected that the demand of blasting demolition will increase in the near future. It is of great important to make up for the insufficient empirical knowledge in blasting demolition through priori method such as computer simulation. Computer simulation of the blasting demolition involves complicated process. In the past domestic researches, two-dimensional bonded particle model was used to examine the overall demolition behavior of a five-story simple structure. It was observed that the two-dimensional simulation did not properly simulate the collapsing behavior of a structure mainly due to the reduced degree of freedom. In this study, three-dimensional simulation was tried. It consumed a great amount of calculation time, which limited the extent of the study. A few parameters, such as delay times, amount of charge at each hole, ball properties, were modified in order to check oui; their effect on the collapsing behavior. The differences were observed as expected but the collapsing behavior did not exactly coincide with the test blasting with a scaled model.

A Case Study on Explosive Demolition of a Steel-Frame Structure (철골구조물 발파해체 시공사례)

  • Park, Hoon;Noh, You-Song;Nam, Sung-Woo;Jang, Seong-Ok;Kim, Nae-Hoi;Suk, Chul-Gi
    • Explosives and Blasting
    • /
    • v.39 no.2
    • /
    • pp.27-36
    • /
    • 2021
  • Recently, the demand for demolition for the unnecessary steel frame structure is increasing due to deterioration and unsatisfactory functional conditions and the major highlights of demolition issues. This execution case was intended to describe an application of the felling method as one about the suggested method for explosive demolition method of ore bin and coke bin facilities, which were steel frame structures. And we used the charging container for blast cutting of the steel frame structure. As a result of the explosive demolition, the ore bin and coke bin had collapsed precisely according to the estimated direction. And the explosive demolition was completed without causing any damage to surrounding facilities.

A Case Study on Explosive Demolition of the Industrial Steel Shell Structure (산업용 스틸 셸 구조물의 발파해체 시공사례)

  • Park, Hoon;Noh, You-Song;Nam, Sung-Woo;Jang, Seong-Ok;Suk, Chul-Gi
    • Tunnel and Underground Space
    • /
    • v.31 no.3
    • /
    • pp.198-209
    • /
    • 2021
  • Recently, the demand for demolition of unnecessary steel shell structure is increasing due to deterioration and unsatisfactory functional conditions and the issue of demolition is becoming a major highlight. This execution case was intended to describe an application of the felling method, a explosive demolition method to demolish steel shell structures, for the demolition of a steel stack and steel head tank. As a result of the explosive demolition, the steel stack and steel head tank had collapsed precisely according to the estimated direction. And the explosive demolition was completed without causing any damage to surrounding facilities.

A Case Study on Explosive Demolition of Boiler Building of Steel Frame Structure (보일러동 철골구조물 발파해체 시공사례)

  • Park, Hoon;Nam, Sung-Woo;Noh, You-Song;Suk, Chul-Gi
    • Explosives and Blasting
    • /
    • v.40 no.3
    • /
    • pp.66-76
    • /
    • 2022
  • Recently, the demand for the dismantling of old industrial complexes has been increasing, and the construction of restoring the dismantled industries to their original natural environment is underway. In this case, the felling method was applied to the explosive demolition method to dismantle a large steel frame structure in an old industrial complex. We used a charging container to cut the steel frame structure that generates a metal jet. The thickness of the thick steel structure in the blasting section was controlled by gouging which a method of digging deep groove by gas and oxygen flame or arc thermal. As a result of the explosive demolition, the steel frame structure collapsed precisely according to the estimated direction. The explosive demolition was completed without causing any damage to the surrounding facilities.

A Case Study of Blast Demolition at Chung-Ang Department Store in Daejeon City (대전 중앙데파트 발파해체 사례)

  • Min, Hyung-Dong;Park, Jong-Ho;Song, Young-Suk;Park, Hoon
    • Explosives and Blasting
    • /
    • v.27 no.1
    • /
    • pp.62-78
    • /
    • 2009
  • Recently, construction techniques have been rapidly developed with reconstruction of old buildings, urban regeneration and efforts of restoring natural ecology, so demolition of deteriorated buildings has been rapidly increasing. Demolition work of building should be executed without damaging surrounding environments according to relevant regulations. There are various demolition methods and among them, explosives demolition is the most practical way for expenses and safety of work. As a part of Daejeon stream ecological restoration project, this thesis is a case of executing demolition of Chung-Ang Department Store which was built 35 years ago as covered structure on the upper part of Daejeon stream with explosives demolition. This structure is 8 stories high, total height of 41.6 m including basement floor, $1,650m^2$ for building area and $18,351m^2$ for total floor area. It is located in the center of Daejeon city where shopping centers and buildings are crowded and main facilities are Daejeon subway (18m), backside shopping center (20m), underground shopping center(15m), Mokchuk bridge, Eunjung bridge(0.25m) and fiber-optic cable(0.25m). In this project, implosion was selected for explosives demolition methods by considering this area being a busy urban area, and this project was executed after examining collapse movement of structure in advance using simulation program not to damage main facilities. Total 80kg of explosives and 1,000 detonators were being used. This project will be a good case of executing explosives demolition successfully by applying implosion on urban area in the country.