Feasibility Study to Apply Automated Trench Cutter (지하연속벽 공법 자동화 도입 타당성 검토)

  • Park, Kyoung-Soon;Koo, Ja-Kyung;Lee, Tai-Sik
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2007.11a
    • /
    • pp.364-367
    • /
    • 2007
  • According to increase of construction projects which is accomplished in the town, diaphragm wall method was proposed. This method diminished noise and vibration. And it is able to excavate deeper than other methods. But excavation work is difficult to maintain vertical and requires much time to work. Also the work result depends on know-how, experience and intuition of excavating machine operator. We interviewed technical experts related with slurry wall method and find equipment's characteristics. We used cost-concern matrix to investigate the propriety for the introduction of trench cutter automation. Through the research, it is proper to apply trench cutter automation.

  • PDF

A Study on the Compression of Construction Period by the Improvement of Trench Excavation for Slurry Wall Method (지하연속벽 시공 시 트렌치 굴착방법 개선을 통한 공기단축에 관한 연구: 현장적용사례를 중심으로)

  • Lee, Young Soo;Park, Hyung-Keun;Kang, Kyubyung
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.32 no.5D
    • /
    • pp.499-505
    • /
    • 2012
  • As the excavation depths during excavation works in urban sites are getting deeper and bigger, It is necessary to study for the improvements to solve the problems in the excavation processes. This research deals with the excavation method that can not only minimize the effect on the surrounding constructions, but also shorten the construction period of the excavation work. For this research, there have been an extensive literature review of the bibliographic data about Slurry Wall Method, which is recognized around the world, and the analysis of the major problems in the existing ineffective construction step. These efforts led to the technical improvements. Accordingly, a new construction method applied with the new technical factors has been suggested, and it was possible to compare Slurry Wall Method with the construction method and analyze them on the base of the examples using the suggested method. This new method decreased the excavation period by 15 days. It took only 33days to finish the excavation work, as compared to 48 days that can be seen on the pre-modification schedule. Furthermore, the suggested method in this research is safer, more economically feasible, and better for the environment than Slurry Wall Method. It will contribute to shortening the construction period of Slurry Wall Method in the end.

The Fluid Loss and Sealing Mechanisms in Slurry Trench Condition (I) : A Large Scale Test and Design Procedure (Slurry wall 공법에서 안정액의 역할 (I) : 대형모형실험과 설계절차)

  • Kim, Hak-Moon
    • Journal of the Korean Geotechnical Society
    • /
    • v.18 no.4
    • /
    • pp.239-248
    • /
    • 2002
  • Bentonite slurries in a slurry wall construction must fulfill a stabilizing function by forming impermeable membrane (surface cake and penetrated cake) on the excavated soil faces. Thus problems are occurring in practice for the construction of diaphram walls and cut-off walls with a low permeability for wastes disposal areas in some deep excavations or different grounds. In this paper, the fundamental mechanics of fluid loss and filter cake formation in various soil beds are investigated using large scale laboratory apparatus. The sealing efficiency of filter cake from the large scale tests and the significance of fluid loss in a slurry trench are utilized for practical situation as a recommended design procedure.

Top-Down Method of Deep Basement Construction in Urban Area : a Comparison of Numerical Analysis and Field observation Data (도심지 지하굴착에 적용된 Top-Down 공법의 수치해석과 실측비교)

  • 김학문
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1991.10a
    • /
    • pp.312-331
    • /
    • 1991
  • Top-down Method of basement construction technique has been applied for building of the deep basement car park the close proximity of priceless historic buildings in LONDON. Numerical analysis for the prediction of ground movement of the surrounding buildings was performed in order to compare the field data at the various stages of excavation and support. The predicted results from the elasto-plastic analytical method were compared with the observed data and the agreement is very satisfactory. It may be concluded that the system of diaphragm wall supported by the permanent base slabs (Top-Down Method) was proved to be the most effective technique in terms of reducing any critical damage to the surrounding buildings.

  • PDF

A Study on the Analysis of the Relaxation Area and the Improvement Effect of the Ground by Road Subsidence (지하연속벽 배면 도로의 지반침하에 따른 이완영역분석방법과 지반 보강 효과검증에 관한 연구)

  • Lee, Hyoung Kyu;Lee, Yong-Sun
    • Journal of the Korean Geotechnical Society
    • /
    • v.37 no.1
    • /
    • pp.29-41
    • /
    • 2021
  • Although underground works are essential to use underground spaces in urban areas efficiently, various damages caused by constructions have often occurred, making them major social problems. Since 2018, it is stipulated in the Special Act on Underground Safety Management that appropriate construction methods must be used in the design stage to prevent various damage cases. This Special Act includes establishing an area subject to underground safety impact assessment, analysis of ground and geological status, review of effects caused by changes in groundwater, review of ground safety, and establishment of measures to secure underground safety. This study area consists of various strata in order of landfill, sedimentary silt, sedimentary sand, sedimentary gravel, weathering zone, and foundation rock. Also, the slurry wall, a highly rigid underground continuous wall, was chosen as a construction method to consider high water table distribution and minimize the influence of the surroundings in this area. However, ground subsidence occurred on the road nearby in December 2019 due to the inflow of loosening soil to the construction area. Thus, several types of site investigations were conducted to suggest an appropriate analysis method and to find out loosed ground behavior and its area for the subsided site. As a result, new design soil properties were re-calculated, and the reinforcement measures were proposed through analytical verification.

Study on the Application of Semi-open cut Top-Down Construction for Framework (세미 오픈컷 역타공법의 현장적용에 관한 연구)

  • Sho, Kwang-Ho
    • Journal of Korean Association for Spatial Structures
    • /
    • v.11 no.2
    • /
    • pp.129-138
    • /
    • 2011
  • Construction methods for underground structure are classified as bottom-up, up-up, and top-down methods depending on the procedure of construction related to a superstructure. In top-down construction methods, building's main structure is built from the ground level downwards by sequentially alternating ground excavation and structure construction. In the mean time, the main structure is also used as supporting structure for earth-retaining wall, which results in the increased stability of the earth-retaining wall due to the minimized deformation in adjacent structures and surrounding grounds. In addition, the method makes it easy to secure a field for construction work in the downtown area by using each floor slabs as working spaces. However top-down construction method is often avoided since an excavation under the slab has low efficiency and difficult environment for work, and high cost compared with earth anchor method. This paper proposes a combined construction method where semi-open cut is selected as excavation work, slurry as earth -retaining wall and CWS as top-down construction method. In the case study targeted for an actual construction project, the proposed method is compared with existing top-down construction method in terms of economic feasibility, construction period and work efficiency. The proposed construction method results in increased work efficiency in the transportation of earth and sand, and steel frame erection, better quality management in PHD construction, and reduced construction period.

Case Study of Self-Supported Diaphragm Wall Method Using Counterfort Technique (부벽식 기법을 사용한 자립식 지하연속벽 공법의 사례 연구)

  • Jeong, Gyeong-Hwan;Park, Hun-Kook;Shin, Min-Sik;Han, Kyoung-Tae;Ryu, Ji-Young
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2006.03a
    • /
    • pp.276-285
    • /
    • 2006
  • Application of anchored or strutted wall system for the earth retention of excavation works in a populated urban area or a poor soil deposit can be limited due to various restrictions. Since the strut becomes longer in a wide excavation site, the stability of an earth retaining wall is decreased, the wall deformation is increased, and the ground settlement is also increased due to an increased buckling or bending deformation of struts. Especially, in a populated urban area, the installation of anchors can be problematic due to the property line of adjacent structures or facilities. Thus, a new concept of earth retaining system like Self-Supported diaphragm Wall can solve several problems expected to occur during excavation in the urban area. In this study, Numerical analyses of counterfort diaphragm wall was introduced and the monitored data from the site was compared with the original results of numerical analyses. Also, in the case of the deep excavation applied the counterfort diaphragm wall, numerical analyses was performed to predict the wall deformation and the reinforcement to reduce the wall deformation was suggested.

  • PDF

Application of Self-Supported Diaphragm Wall Method Using Counterfort Technique (부벽식 기법을 사용한 자립식 지하연속벽 공법의 적용)

  • Jeong, Gyeong-Hwan;Jeong, Dong-Yeong;Park, Hun-Kook;Han, Kyoung-Tae;Ryu, Ji-Young
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2004.03b
    • /
    • pp.775-782
    • /
    • 2004
  • Recently, the cases which are constructed close by neighboring structure or underground structure are on the increase to get the utmost out of the land exploitation of underground space in the downtown area. As the building becomes larger, the excavation depth is getting deep, and the excavation area is getting, wide too. These are frequent occasions that the application of Strut or Anchor method is difficult, because of site boundary, civil application and the ground condition. Therefore, to solve these problem, we analyze and compare design with measuring data, change the design factor and show the improvement of course through the application of self-supported diaphragm wall using counterfort technique which is a new method. It is expected to be a contribution to the suitable exploitation method of construction.

  • PDF

Singapore Case Study of Self-Supported Diaphragm Wall Method Using Counterfort Technique (부벽식 기법을 사용한 자립식 지하연속벽 공법의 싱가폴사례)

  • Jeong, Gyeong-Hwan;Park, Hun-Kook;Shin, Min-Sik;Han, Kyoung-Tae;Ryu, Ji-Young
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2008.10a
    • /
    • pp.605-613
    • /
    • 2008
  • Application of anchored or strutted wall system for the earth retention of excavation works in a populated urban area or a poor soil deposit can be limited due to various restrictions. Since the strut becomes longer in a wide excavation site, the stability of an earth retaining wall is decreased, the wall deformation is increased, and the ground settlement is also increased due to an increased buckling or bending deformation of struts. Especially, in a populated urban area, the installation of anchors can be problematic due to the property line of adjacent structures or facilities. Thus, a new concept of earth retaining system like Self-Supported diaphragm Wall can solve several problems expected to occur during excavation in the urban area. Application of self-supported counterfort diaphragm wall was verified in this paper though comparing the design of self-supported counterfort diaphragm wall with the data monitored during excavation in Singapore.

  • PDF

A Study on the Utilization Method in the SCW Method using Supplementary Cementitious Materials (시멘트 대체재료를 활용한 SCW공법에서의 활용 방안에 대한 연구)

  • Kwang-Wu Lee;Jae-Hyun Park;Young-Won Lee;Dae-Sung Cho
    • Journal of the Korean Geosynthetics Society
    • /
    • v.22 no.3
    • /
    • pp.87-95
    • /
    • 2023
  • Recently, redevelopment of the original downtown area is underway, the necessity of construction in adjacent location is increasing. However, excavations in dense urban areas are prone to ground problems due to various causes, so it is necessary to use materials and methods that can minimize such problems. As a general earth retaining method, various methods such as diaphragm wall and CIP method are applied using cement. However, since a large amount of cement is used for the installation of earth retaining method, it is necessary to conduct research on the development of new cement substitute materials to significantly reduce greenhouse gas emissions. In this study, we utilized the hardening reaction of blast furnace slag powder, desulfurized gypsum and high calcium fly ash by alkali activation and applied it to the SCW method. As a result, it was analyzed that the compressive strength of solidified soil using development solidification material was 96.2 ~ 106.3% of OPC at 28 days of curing. In addition, the strength increment ratio was 2.06 for sandy soil and 2.41 for clayey soil, which was higher than 1.85 of OPC. It seems an advantageous in terms of long-term strength. In addition, from the environmental point of view, it was analyzed that there is no elution of heavy metals and that greenhouse gas emissions can be dramatically reduced. Therefore, if further studies are conducted, it can be applied to the SCW method.