• Title/Summary/Keyword: 굴착시공

Search Result 728, Processing Time 0.021 seconds

Evaluation of the Standard Support Pattern in Large Section Tunnel by Numerical Analysis and Field Measurement (수치해석 및 현장계측에 의한 대단면 터널 표준지보패턴의 적정성 검증)

  • Byun, Yoseph;Chung, Sungrae;Song, Simyung;Chun, Byungsik;Park, Duhee
    • Journal of the Korean GEO-environmental Society
    • /
    • v.12 no.7
    • /
    • pp.5-12
    • /
    • 2011
  • When choosing the support pattern of tunnel, the characteristics of rock are identified from the result of the surface geologic survey, boring, and geophysical prospecting and laboratory test. And a rock mass rating is classified and excavation method and standard support pattern are designed considering rock classification, domestic and international construction practices, numerical analysis. According to the revised design standard for tunnel, it was recommended to classify the rock mass rating for the design of tunnel into a rating based on RMR. If necessary, it proposed a flexible standard allowed applying more atomized the rock mass rating and Q-System. Also, the resonable verification of the support pattern must be accompanied because the factors affecting the structure and behavior of ground during the construction of tunnel are the main factors of uncertainty factors such as the nature of ground, ground water and the characteristics of structural materials. These days, such verification method is getting more specialized and diversified. In this study, the empirical method, numerical analysis and comparative analysis of in situ measurements were used to prove the reasonableness in the support pattern by RMR and Q-value on the Imha Dam emergency spillway.

A study on platform-based preliminary design guidelines associated with the behaviour of piles to adjacent tunnelling (터널근접시공에 의한 말뚝의 거동을 고려한 플랫폼 기반의 예비 설계 가이드라인에 대한 연구)

  • Jeon, Young-Jin;Lee, Gyu-Seol;Lee, Jae-Cheol;Batbuyan, Chinzorig;Lee, Cheol-Ju
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.24 no.2
    • /
    • pp.129-151
    • /
    • 2022
  • In the current work, a series of three-dimensional finite element analyses have been carried out to understand the behaviour of piles when the adjacent tunnelling passes underneath grouped piles with a reinforced pile cap. In the current study, the numerical analysis studied the computed results regarding the ground reinforcement condition between the tunnel and pile foundation. In addition, several key issues, such as the pile settlements, the axial pile forces, the shear stresses and the relative displacements have been thoroughly analysed, and the IoT platform based preliminary design guidelines were also presented. The pile head settlements of the nearest pile from the tunnel without the ground reinforcement increased by about 70% compared to the farthest pile from the tunnel with the maximum level of reinforcement. The quality management factor data of the piles were provided as API (Application Programming Interface) of various forms by the collection and refinement. Hence it has been shown that it would be important to provide the appropriate API by defining the each of data flow process when the data were created. The behaviour of the grouped piles with the pile cap, depending on the amount of ground reinforcement, has been extensively analysed, and the IoT platform regarding the quality management of piles has been suggested.

Development of a Pavement Cutter for Eco-friendly Road Excavation Construction (친환경 도로굴착 시공을 위한 도로절단기 개발)

  • Kim, Kyoontai
    • Korean Journal of Construction Engineering and Management
    • /
    • v.23 no.6
    • /
    • pp.111-118
    • /
    • 2022
  • Recently, as underground facilities buried under roads in Korea are aging, the amount of underground facility maintenance work is rapidly increasing. For the maintenance and management of such underground facilities, the cutting work of the road pavement should be preceded. However, the conventional road pavement cutters used in Korea are not eco-friendly, and the reality is that they generate a lot of noise and cutting sludge (scattering dust). Therefore, in this study, the concept of the cutting sludge recovery device was derived, and an eco-friendly pavement cutter including this function was designed and manufactured. The developed equipment took about 20 to 30 seconds to cut 1m to a depth of 100 to 150mm. Also, the sludge suction performance was good in most sections, and the noise level of the equipment briefly measured at a distance of 2m was 82.7dB on average. However, due to the limitation that the developed equipment was at the level of the first prototype, the driving stability was somewhat low, and equipment abnormalities such as engine shutdown and sludge recovery performance decreased in some cases. The cutting performance and sludge recovery function will be more stable through tuning and improvement of the developed prototype in the future. In addition, we plan to quantitatively compare and analyze productivity by applying the improved prototype to actual field conditions.

Development of 3D Underground Information Construction and Visualization System Based on IUGIM (지하공간통합지도 기반 3차원 지하정보 구축 및 가시화시스템 개발)

  • Kang, Kyung Nam;Kim, Wooram;Hwang, Seung Hyun;An, Joon Sang
    • Journal of the Korean Society of Surveying, Geodesy, Photogrammetry and Cartography
    • /
    • v.39 no.6
    • /
    • pp.497-505
    • /
    • 2021
  • Due to recent underground space accidents, are a frequent occurence in Korea, the government established the basic plan for the construction of the IUGIM (Integrated Underground Geospatial Information Map) in 2015 as a measure for safety management of underground spaces. The development of IUGIM was partially completed as of 2021. The underground space management entity and related organizations are utilizing it. This study is being carried out as part of a plan to improve the usability of IUGIM, and to build a visualization system that compares real-time field data with stored data. A system, equipped with a visualization function for borehole data and 6 types of underground facilities built and managed on IUGIM; a tool capable of comparative analysis with real-time data measured in the field, is being built. The 6 types of underground facilities are water supply pipe, sewage pipe, power pipe, gas pipe, communication pipe, and heating pipe. The completed system was demonstrated at three locations in Seocho-gu, Gangnam-gu in Seoul. The field demonstration was carried out by accessing the mobile center and downloading IUGIM data, visualizing IUGIM data (surface creation, borehole information, underground facilities), and visualizing the GPR(Ground Penetrating Radar)-based data acquired at the field. As a result of the empirical results of IUGIM data and GPR-based field data, it was judged to be suitable. As a result of this study, it is judged that it can be helpful for safe construction at the excavation site.

Evaluation of the Lateral Influence Range on Temporary Structures for a Train Operating at 80km/h (시속 80km/h의 열차 운행시 가시설 구조물에 미치는 수평영향범위 평가)

  • Jong-Chul Kim;Yeong-Bae Kim;Tae-Hyun Hwang;Kang-Il Lee
    • Journal of the Korean Geosynthetics Society
    • /
    • v.22 no.2
    • /
    • pp.35-45
    • /
    • 2023
  • In accordance with the urban development project, cases of constructing temporary wall structures for ground excavation in the vicinity of railway structures are increasing. In addition, the complaints about train vibration are also increasing from people living in large buildings newly built after installing the temporary wall structures. In order to solve this problem, a method for reducing train vibration is considered from the design stage of the building, and a vibration reduction system is installed on the structure when the building is newly constructed. However, the vibration reduction method established at the structure design stage can be determined through the results of field measurements or dynamic numerical analysis for a specific area, and there is a limit to evaluating whether the established vibration reduction method is appropriate due to the lack of objective research data. Therefore, in order to provide objective basic data when establishing a vibration reduction method, this study performed the dynamic numerical analysis for a operating train with a speed 80km/h by applying differently the depths of railway structures, the distances between railways and temporary wall structures, and ground conditions. It was found that the range of influence of a train operating at 80 km/h was within 4.5D of the lateral distance from the railway structure in the case of the condition where the temporary wall was installed.

Seismic analysis and dynamic behavior characterization of rib-reinforced pre-cast tunnels (리브 보강 프리캐스트 터널의 내진 해석 및 동적거동 특성 파악)

  • Song, Ki-Il;Jung, Sung-Hoon;Cho, Gye-Chun
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.11 no.3
    • /
    • pp.287-301
    • /
    • 2009
  • The novel cut-and-cover tunnel construction method using rib-reinforced pre-cast arch segments has been recently developed and applied for practice to secure a structural stability of high covering and wide width section tunnels. Cut-and-cover tunnels are usually damaged by the seismic behavior of backfill grounds in case of a low covering condition. Seismic analyses are performed in this study to characterize the dynamic behavior of rib-reinforced pre-cast arch cut-and-cover tunnels. Seismic analyzes for 2 lane cast-in-place and rib-reinforced pre-cast arch cut-and-cover tunnels are carried out by using the commercial FDM program (FLAC2D) considering various field conditions such as the covering height embankment slope and excavation slope. It can be concluded that the amplification of seismic wave is reduced due to an increase in the structural stiffness induced by rib-reinforcement. The results show that the rib-reinforced pre-cast arch cut-and-cover tunnels are more effective against the seismic loading, compared to the cast-in-place cut-and-cover tunnels.

A study on the soil conditioning behaviour according to mixing method in EPB shield TBM chamber (EPB 쉴드 TBM 챔버 내 혼합방법에 따른 배토상태거동에 대한 연구)

  • Kim, Yeon-Deok;Hwang, Beoung-Hyeon;Cho, Sung-Woo;Kim, Sang-Hwan
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.23 no.4
    • /
    • pp.233-252
    • /
    • 2021
  • This paper is a study to improve the efficiency of mixing technology in the shield TBM chamber. Currently, the number of construction cases using the TBM method is increasing in Korea. According to the increasing use of TBM method, research on TBM method such as Disc Cutter, Cutter bit, and Segment also shows an increasing trend. However, there is little research on the mixing efficiency in chamber and chamber. In order to improve the smooth soil treatment and the behavior of the excavated soil, a study was conducted on the change of the mixing efficiency according to the effective mixing bar arrangement in the chamber. In the scale model experiment, the ground was composed using plastic materials of different colors for ease of identification. In addition, the mixing bar arrangement was different and classified into 4 cases, and the particle size distribution was classified into single particle size and multiple particle size, and the experiment was conducted with a total of 8 cases. The rotation speed of the cutter head of all cases was the same as 5 RPM, and the experiment time was also carried out in the same condition, 1 minute and 30 seconds. In order to check the mixing efficiency, samples at the upper, middle (left or right), and lower positions of each case were collected and analyzed. As a result of the scaled-down model experiment, the mixing efficiency of Case 4 and Case 4-1 increased compared to Case 1 and Case 1-1, which are actually used. Accordingly, it is expected that the mixing efficiency can be increased by changing the arrangement of the mixing bar in the chamber, and it is considered to be effective in saving air as the mixing efficiency increases. Therefore, this study is considered to be an important indicator for the use of shield TBM in Korea.

Analysis on dynamic numerical model of subsea railway tunnel considering various ground and seismic conditions (다양한 지반 및 지진하중 조건을 고려한 해저철도 터널의 동적 수치모델 분석)

  • Changwon Kwak;Jeongjun Park;Mintaek Yoo
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.25 no.6
    • /
    • pp.583-603
    • /
    • 2023
  • Recently, the advancement of mechanical tunnel boring machine (TBM) technology and the characteristics of subsea railway tunnels subjected to hydrostatic pressure have led to the widespread application of shield TBM methods in the design and construction of subsea railway tunnels. Subsea railway tunnels are exposed in a constant pore water pressure and are influenced by the amplification of seismic waves during earthquake. In particular, seismic loads acting on subsea railway tunnels under various ground conditions such as soft ground, soft soil-rock composite ground, and fractured zones can cause significant changes in tunnel displacement and stress, thereby affecting tunnel safety. Additionally, the dynamic response of the ground and tunnel varies based on seismic load parameters such as frequency characteristics, seismic waveform, and peak acceleration, adding complexity to the behavior of the ground-tunnel structure system. In this study, a finite difference method is employed to model the entire ground-tunnel structure system, considering hydrostatic pressure, for the investigation of dynamic behavior of subsea railway tunnel during earthquake. Since the key factors influencing the dynamic behavior during seismic events are ground conditions and seismic waves, six analysis cases are established based on virtual ground conditions: Case-1 with weathered soil, Case-2 with hard rock, Case-3 with a composite ground of soil and hard rock in the tunnel longitudinal direction, Case-4 with the tunnel passing through a narrow fault zone, Case-5 with a composite ground of soft soil and hard rock in the tunnel longitudinal direction, and Case-6 with the tunnel passing through a wide fractured zone. As a result, horizontal displacements due to earthquakes tend to increase with an increase in ground stiffness, however, the displacements tend to be restrained due to the confining effects of the ground and the rigid shield segments. On the contrary, peak compressive stress of segment significantly increases with weaker ground stiffness and the effects of displacement restrain contribute the increase of peak compressive stress of segment.