• Title/Summary/Keyword: 건설분쟁해결

Search Result 70, Processing Time 0.025 seconds

Proposal of Improvement Devices for Construction Dispute Resolution System in Public Works (공공건설공사의 분쟁해결조항 개선방안 연구)

  • Lee Ji-Yeon;Shin Kyoo-Chul;Lee Jae-Seob
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2004.11a
    • /
    • pp.437-441
    • /
    • 2004
  • This study aims to propose a set of improvement devices for construction dispute resolution clause of public improvement project in Korea. To do so, the study addresses the system and procedure of construction dispute resolution in domestic and overseas, and reviews precedent cases, specifically focused of a selective arbitration case. In public sector's initiated contracts, the absence of c)aim procedure clause is unable to response to the claims in timely manner, and the ambiguity of clause o( selective arbitration make it difficult to resolve a dispute by arbitration. Thus, in this study alternative dispute resolutions are explored as a way to resolve various construction disputes of public-initiated project in developed countries.

  • PDF

건설분쟁이 발생할 경우 소송외적 해결제도

  • Korea Mechanical Construction Contractors Association
    • 월간 기계설비
    • /
    • no.10 s.195
    • /
    • pp.53-56
    • /
    • 2006
  • 시공을 하다가 손해를 보았는데도 발주자 혹은 원도급업체에서 인정을 안해준다면 어떻게 해야 할까? "소송을 할까?", "다음 공사는 어떻게 해. 그냥 손해보고 말지 뭐", "아니야 그냥 넘어가기에는 너무 억울해" 설비건설업을 하다보면 누구나 한번쯤 이런 경험이 있었을 것이다. 이럴 경우 공정거래위원회에 문의 하거나 건설하도급 분쟁조정협의회에 문의하다가 정 안될 경우 소송에 돌입한다. 소송의 경우 대법원의 최종 판결이 나기까지 2~3년은 고스란히 걸림은 물론 소송비용도 만만치 않다. 이렇게 기간이 길지 않고 가격도 저렴하면서 해결 가능한 방법은 없을까? 물론 있다. 본지가 지난 7월부터 연재한 대한상사중재원과 건설하도급분쟁조정협의회, 공정거래위원회 등을 통해 해결 가능하다. 이번 호에는 그동안 게재되었던 건설분쟁시의 해결방안에 대한 총론으로 민사분쟁의 소송외적 해결제도 및 건설분쟁의 소송외적 해결제도, 건설공사 계약문서별 분쟁해결 조항에 대하여 게재한다.

  • PDF

건설분쟁은 건설하도급분쟁조정협의회에 의뢰, 해결

  • Korea Mechanical Construction Contractors Association
    • 월간 기계설비
    • /
    • no.8 s.193
    • /
    • pp.34-39
    • /
    • 2006
  • 시공을 하다가 손해를 보았는데도 발주자 혹은 원도급업체에서 인정을 안해준다면 어떻게 해야 할까? "소송을 할까?", "다음 공사는 어떻게 해. 그냥 손해보고 말지 뭐", "아니야 그냥 넘어가기에는 너무 억울해" 설비건설업을 하다보면 누구나 한번쯤 이런 경험이 있었을 것이다. 이럴 경우 공정거래위원회에 문의 하거나 건설하도급분쟁조정협의회에 문의하다가 정 안될 경우 소송에 돌입한다. 소송의 경우 대법원의 최종 판결이 나기까지 2~3년은 고스란히 걸림은 물론 소송비용도 만만치 않다. 이렇게 기간이 길지 않고 가격도 저렴하면서 해결 가능한 방법은 없을까? 물론 있다. 건설하도급분쟁조정협의회에 의뢰하면 된다. 건설하도급분쟁조정협외희는 건설하도급 불공정거래행위에 따른 분쟁의 신속하고도 자율적인 해결을 도모하기 위해 지난 '85년 대한건설협회와 대한전문건설협회가 공동으로 설치하여 운영하고 있으며, 설비부문은 대한전문건설협회와 통합하여 운영하고 있다. 본지는 지난 호 대한상사중재원의 '중재'에 이어 이번 호에서는 건설하도급 분쟁조정협의회를, 다음호에는 공정거래위원회를 게재할 계획이다.

  • PDF

Effective Handling of Construction Disputes for Strengthening the International Competitiveness of the Construction Industry (건설산업 국제경쟁력강화를 위한 건설분쟁처리절차 개선방안)

  • Cho, Youngjun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.21 no.4
    • /
    • pp.3-11
    • /
    • 2020
  • Problems related to construction contracts arise if they are not reflected in the design phase from the planning phase of the construction project, or if they are not properly dealt with despite various changes in the construction phase. So far, there have been a number of discussions in Korea regarding the improvement of the procedures for resolving construction disputes, and the problems related to the procedures for solving construction disputes have been raised steadily, but the problems related to the procedures for solving construction disputes are still unresolved. Therefore, in this study, the followings were proposed to strengthen the international competitiveness of the construction industry. First, the so-called Construction Dispute Mediation Act should be enacted to prepare the basis for the establishment of a tentatively named Construction Dispute Mediation and Arbitration Agency(CDMA). Second, the work of the CDMA should be limited to the work of supporting the DRB, mediation and Arbitration the private and public sectors. Third, it is required to choose between adjustment and arbitration when obtaining a contract and to operate the DRB during construction phase. Fourth, CDMA should be established as standing bodies, and branches should be operated in various parts of the country. Fifth, construction experts from various areas should be included as members so that disputes over construction contracts can be dealt with quickly. And finally, relevant laws that specify the procedures for dealing with construction disputes should be amended together.

A Study of the Introduction and Application of Partnering to the Alternative Dispute Resolution(ADR) (재판 외 분쟁해결제도로서의 파트너링 도입에 관한 연구)

  • Lee Tai Sik;Jeong Hyun Jin
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.329-332
    • /
    • 2001
  • Alternative dispute resolution(ADR) techniques, like negotiation, arbitration, meditation, have been used to resolve dispute in Korea construction industry with litigation. Nowadays, in construction, there are growing numbers of disputing cases, because of the different viewpoint of the owner and the constructor, great demand of opening market, and bad construction business situation. As the name implies, ADR plays an important roles after disputes have already arisen. This paper suggests the one of the solutions that prevents disputes befor they have been occurred. There are some proves that the partnering has a substantial effect on reducing disputes and time reduction and improving communication among the parties. This paper proposes the partnering model for the one of preventive methods to solve disputes.

  • PDF

Empirical Study on the Validity of Construction Bond-related Litigations (건설보증(建設保證) 분쟁해결(紛爭解決)의 소송(訴訟) 유효성(有效性)에 관(關)한 실증적(實證的) 연구(硏究))

  • Kim, Jong-Seo;Choi, Jong-Soo;Lee, Jae-Seob
    • Korean Journal of Construction Engineering and Management
    • /
    • v.7 no.6
    • /
    • pp.99-111
    • /
    • 2006
  • Of the numerious dispute resolution methods, Alternative Dispute Resolution(ADR) is the most highly recommended approach for the guarantee bond-related dispute. In reality, however, claims were not resolved satisfactorily through ADR because of the lack of reference materials for negotiation, thus those were frequently had to be resolved through litigation. The above fact implies that, it is required to seek an efficient way to resolve the bond-related claims prior to they progress to litigation. This research paper intensively investigated judicial precedents of 232 cases with regard to construction bond-related disputes that observed during the analysis period(2000-2004). According to the summary statistics, it turned out that litigation were time consuming and potential economic loss was tremendous; on average, it takes 1067 days(the longest case was 1965 days) for dispute resolution. It suggests that litigations should be discouraged considering the magnitude of potential loss of stake holders. Research results revealed that there are some significant differences between categories in some variables affecting to the rate of winning; i) the number of lawsuit deputies of a plaintiff (in the 1st trial), ii) dispute locations (in the 1st and 3rd trials), iii) contract price (in the 1st trial), iv) contractors' operating capability (in the 1st and 2nd trials). For the rest of variables, significance level between categories was too low for preparing efficient improvement plan. Despite the important implications drawn from the analysis, this research has limitation due to the several reasons such as data structure, the depth of Information, etc. Therefore, more systematic research should be followed in the future.

Governance for the negotiation and Management of Water Resources related Conflicts (수자원과 관련된 분쟁 및 갈등의 조정을 위한 거버넌스)

  • Lee, Joo-Heon;Kim, Hyung-Soo;Hong, Il-Pyou;Kang, Bu-Sik;Kim, Kwang-Hun
    • Proceedings of the Korea Water Resources Association Conference
    • /
    • 2008.05a
    • /
    • pp.1530-1535
    • /
    • 2008
  • 수자원과 관련된 많은 분쟁 및 갈등들은 국내뿐만 아니라 전 세계적으로 발생하고 있다. 따라서 분쟁 및 갈등해결을 위한 많은 연구들이 진행되고 있지만 수자원과 관련된 분쟁들은 대부분 원활한 해결을 이루지 못하고 있으며, 특히 국내의 경우에는 더욱 심각하다 할 수 있다. 따라서 제한된 자원인 수자원을 둘러싸고 수자원분쟁이 일어나는 것은 당연한 일이라 할 수 있으며, 분쟁의 양상도 다양하다. 댐 건설로 인한 상류지역과 하류지역의 갈등, 수로의 건설로 인해 수자원을 빼앗기는 지역과 수자원을 얻게 되는 지역 간의 갈등, 새로운 공단이나 개발로 인하여 하류지역에서 수질악화를 우려하여 반대하는 경우 등 여러 종류의 수자원으로 인한 분쟁이 있다. 수자원을 둘러싼 갈등이 쉽게 해결이 되지 않고, 또한 갈등 및 분쟁이 쉽게 발생되는 이유도 주체자들간 입장 차이에서 오는 성격이라 할 수 있겠다. 수자원과 관련된 분쟁에서 오는 여러 가지 갈등들은 사회적으로 많은 문제들을 발생시켜 수자원의 원활한 공급이 저해될 수 있다. 이로 인해 사회적으로 수자원과 관련된 분쟁 해결에 들어가는 많은 시간과 노력, 비용을 생각해 볼 때, 효과적인 갈등 및 분쟁의 해결은 국가적 발전에 있어서 영향을 줄 수 있다. 그러므로 갈등 및 분쟁의 원활한 해결이 국가적 발전에 많은 비중을 차지 한다고 할 수 있다는 것은 이런 이유들 때문이라 할 수 있다. 본 연구에서는 국내 수자원과 관련된 분쟁사례들을 하천의 기능에 따른 분류, 발생 원인에 따른 분류, 분쟁주체에 따른 분류 등을 유형별로 구분하여 수자원분쟁의 여러 가지 사례들을 조사하였다. 또한 분쟁 및 갈등을 해결하기 위한 방안으로 거버넌스 시스템을 적용하였고 분쟁의 원활한 합의 조정방안 및 문제점을 제시하기 위한 외국의 시민참여 모델을 특징 및 특성을 분석하였다. 또한, 공영시각모형, 게임이론, 제도설계이론의 공학적 모형을 바탕으로 물분쟁의 해결을 위한 대안을 모색할 수 있는 과학적 접근 방안을 제시하여 향후 여러 가지형태의 국책사업 시행 시 발생 할 수 있는 분쟁의 해결 및 조정을 위한 방안으로 활용할 수 있는 토대를 마련하고자 한다.

  • PDF

A Suggestion of the ADR in Public Construction Disputes (공공건설사업에서의 사전분쟁해결(ADR)방법 도입방안)

  • Cho, Young-Jun
    • Proceedings of the Korea Contents Association Conference
    • /
    • 2006.05a
    • /
    • pp.356-359
    • /
    • 2006
  • Dispute is construction itself. Serious difficulties ore occurred between contract parties when These disputes have occurred. Authority may fear the defective work if the requirement of contractor is fully reflected in the adjustment of contract. On the other hand the contractor may have fears that no payment or some payment of the extra work or the additional work done will be required. Therefore these problems must be resolved before these result in an enlarged riffle effect. To reduce the fear of the contract parties, ADR(Alternative Dispute Resolution) process were suggested.

  • PDF

환경오염피해분쟁조정제도

  • 장창훈
    • Journal of KSNVE
    • /
    • v.7 no.4
    • /
    • pp.552-554
    • /
    • 1997
  • 산업의 고도성장으로 물질문명은 발전하고 있으나 원치않는 환경오염의 피해가 발생하고 있으며, 피해의 양상도 인체의 건강에 미치는 피해와 재산사의 피해 등 그 양태가 매우 다양하다. 환경오염피해가 발생하면 피해자는 책임 있는 자에게 피해의 배상을 요구하고 정당한 배상을 받도록 해야 할 것이나 당사자간의 의견차로 인하여 분쟁이 빈발하고, 이러한 환경분쟁이 주로 환경오염 피해분쟁조정법에 의한 조정으로 해결되고 있으며, 특히 건설공사로 인한 소음.진동 피해분쟁이 전체 환경분쟁의 63%에 달하고 있어 관련법규를 소개함으로써 분쟁의 발생 예방과 해결에 도움이 되고자 한다.

  • PDF