Factors Influencing Cost Overruns in Construction Projects of International Contractors in Vietnam  

VU, Thong Quoc (Accounting Information System Department, Faculty of Accounting and Auditing, Ho Chi Minh City Open University)
PHAM, Cuong Phu (Faculty of Transport and Economics, University of Transport and Communications)
NGUYEN, Thu Anh (Ho Chi Minh City University of Technology (HCMUT))
NGUYEN, Phong Thanh (Department of Project Management, Ho Chi Minh City Open University)
PHAN, Phuong Thanh (Department of Project Management, Ho Chi Minh City Open University)
NGUYEN, Quyen Le Hoang Thuy To (Office of Cooperation and Research Management, Ho Chi Minh City Open University)
Publication Information
The Journal of Asian Finance, Economics and Business / v.7, no.9, 2020 , pp. 389-400 More about this Journal
Abstract
A construction project is a designed product made up of labors, materials, and installations in the project positioned on the ground and may include the underground and ground section, and the section in water or on the water surface. It is a civil, industrial, transport, agricultural and rural development, infrastructure, or some other. A key phase in the life cycle of these construction projects is the implementation when building products are made directly with workers, equipment, materials, and managers. If there is a lack of management experience, information, and problem-solving solutions to tackle the risks faced by contractors, especially foreign ones, will fail in controlling the project's cost. This study was conducted with investigations, discussions, and evaluation of the factors that lead to cost overruns in the construction projects of international contractors in Vietnam. The principal component analysis (PCA) showed that those factors that influence cost overruns these construction projects fall into five general groups, including factors related to (i) the owners, (ii) the foreign contractors, (iii) the subcontractors and suppliers, (iv) state management, and (v) the project itself. Besides, the study proposes solutions to limit cost overruns in construction projects and improve the profitability of international contractors in Vietnam.
Keywords
Cost Overrun; Financial Management; Foreign Contractor; Project Management; International Management;
Citations & Related Records
Times Cited By KSCI : 12  (Citation Analysis)
연도 인용수 순위
1 Bozgulova, N., Parmanova, R., Abenova, M., Ivanyuk, T., & Aryshev, V. (2019). Calculation methods for cost management in the construction industry. Entrepreneurship and Sustainability Issues, 7(2), 1450-1461. https://doi.org/10.9770/jesi.2019.7.2(46)   DOI
2 Brahmasrene, T., & Lee, J. W. (2020). Exchange rate movements and structural break on china fdi inflows. Contemporary Economics, 14(2), 112-126. https://doi.org/10.5709/ce.1897-9254.335   DOI
3 Eybpoosh, M., Dikmen, I., & Birgonul, M. T. (2011). Identification of risk paths in international construction projects using structural equation modeling. Journal of Construction Engineering and Management, 137(12), 1164-1175. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000382   DOI
4 Fang, D., Li, M., Fong, P. S. W., & Shen, L. (2004). Risks in chinese construction market - contractors' perspective. Journal of Construction Engineering and Management, 130(6), 853-861. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:6(853)   DOI
5 Fidan, G., Dikmen, I., Tanyer, A. M., & Birgonul, M. T. (2011). Ontology for relating risk and vulnerability to cost overrun in international projects. Journal of Computing in Civil Engineering, 25(4), 302-315. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000090   DOI
6 Ha, N. M., Le, N. D., & Trung-Kien, P. (2019). The impact of urbanization on income inequality: A study in vietnam. Journal of Risk and Financial Management, 12(3), 14. https://doi.org/10.3390/jrfm12030146   DOI
7 Vu, H. A., Vu, C. C., Wang, J., & Min, L. (2018). Evaluating impacts of financial risks on schedule delays of international highway projects in vietnam using structural equation model. International Journal of Performability Engineering, 14(2), 363-375. https://doi.org/10.23940/ijpe.18.02.p18.363375
8 Weiss, M. (2018). State vs. Market in india: How (not) to integrate foreign contractors in the domestic defense-industrial sector. Comparative Strategy, 37(4), 286-298. https://doi.org/10.1080/01495933.2018.1497323   DOI
9 Zhi, H. (1995). Risk management for overseas construction projects. International Journal of Project Management, 13(4), 231-237. https://doi.org/10.1016/0263-7863(95)00015-I   DOI
10 Ha, N. M., & Ngoc, B. H. (2020). Revisiting the relationship between energy consumption and economic growth nexus in vietnam: New evidence by asymmetric ardl cointegration. Applied Economics Letters, 1-7. [In Press]. https://doi.org/10.1080/13504851.2020.1789543
11 Huynh, V. D. B., Nguyen, P. T., Nguyen, T. A., Nguyen, Q., & Nguyen, T. T. H. (2019). Identifying the key competitiveness indicators for construction contractors. International Journal of Advanced and Applied Sciences, 6(4), 59-64. https://doi.org/10.21833/ijaas.2019.04.007   DOI
12 Lee, J. W., & Brahmasrene, T. (2019). Long-run and shortrun causality from exchange rates to the korea composite stock price index. Journal of Asian Finance, Economics and Business, 6(2), 257-267. https://doi.org/10.13106/jafeb.2019.vol6.no2.257   DOI
13 Lee, K. T., & Park, S. B. (2017). The effects of sla on service quality level and service productivity of sub-contractor. Journal of Distribution Science, 15(5), 65-73. https://doi.org/10.15722/jds.15.5.201705.65   DOI
14 Long, L. D., Tran, D. H., & Nguyen, P. T. (2019). Hybrid multiple objective evolutionary algorithms for optimising multi-mode time, cost and risk trade-off problem. International Journal of Computer Applications in Technology, 60(3), 203-214. https://doi.org/10.1504/IJCAT.2019.100299   DOI
15 Luong, D. L., Tran, D. H., & Nguyen, P. T. (2018). Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution. International Journal of Construction Management. [Online First]. https://doi.org/10.1080/15623599.2018.1526630
16 Memon, A. H., Rahman, I. A., Abdullah, M. R., & Azis, A. A. A. (2010). Factors affecting construction cost in mara large construction project: Perspective of project management consultant. International Journal of Sustainable Construction Engineering and Technology, 1(2), 41-54.
17 Nguyen, P., & Nguyen, P. (2020). Risk management in engineering and construction: A case study in design-build projects in vietnam. Engineering, Technology & Applied Science Research, 10(1), 5237-5241.   DOI
18 Nguyen, H. H. (2020). Impact of foreign direct investment and international trade on economic growth: Empirical study in vietnam. Journal of Asian Finance, Economics and Business, 7(3), 323-331. https://doi.org/10.13106/jafeb.2020.vol7.no3.323   DOI
19 Nguyen, H. M., & Ngoc, B. H. (2020). Energy consumption - economic growth nexus in vietnam: An ardl approach with a structural break. Journal of Asian Finance, Economics and Business, 7(1), 101-110. https://doi.org/10.13106/jafeb.2020.vol7.no1.101   DOI
20 Nguyen, H. M., Quan, B. Q. M., Le, H. V., & Van Tran, T. (2020). Determinants of intra-industry trade between vietnam and countries in tpp. Journal of Asian Finance, Economics and Business, 7(1), 123-129. https://doi.org/10.13106/jafeb.2020.vol7.no1.123   DOI
21 Nguyen, P. T., Nguyen, V. N., Pham, L. H., Nguyen, T. A., Nguyen, Q. L. H. T. T., & Huynh, V. D. B. (2018). Application of supply chain management in construction industry. Advances in Science and Technology Research Journal, 12(2),11-19. https://doi.org/10.12913/22998624/92112   DOI
22 Nguyen, T. A., Do, S. T., & Nguyen, P. T. (2020). Application of building information modeling (bim) in volume management of construction projects. Journal of Advanced Research in Dynamical and Control Systems, 12(2), 1845-1852. https://doi.org/10.5373/JARDCS/V12I2/S20201228   DOI
23 Olaniran, O. J., Love, P. E. D., Edwards, D., Olatunji, O. A., & Matthews, J. (2016). Cost overruns in hydrocarbon megaprojects: A critical review and implications for research. Project Management Journal, 46(6), 126-138. https://doi.org/10.1002/pmj.21556   DOI
24 Pham, C. P., Nguyen, P. T., Nguyen, T. A., & Dinh, H. T. T. (2020). Project change management using building information modeling 360 docs. International Journal of Advanced Science and Technology, 29(4 Special Issue), 1348-1357.
25 Sy, D. T., Likhitruangsilp, V., Onishi, M., & Nguyen, P. T. (2017). Different perceptions of concern factors for strategic investment of the private sector in public-private partnership transportation projects. ASEAN Engineering Journal, 7(2), 66-86.   DOI
26 Pham, L. H., & Hadikusumo, H. (2014). Schedule delays in engineering, procurement, and construction petrochemical projects in vietnam: A qualitative research study. International Journal of Energy Sector Management, 8(1), 3-26. https://doi.org/10.1108/IJESM-06-2013-0009   DOI
27 Pham, V. Q., Nguyen, B. K. Q., Van Tu, B., Pham, H. T. T., & Le, T. Q. (2019). Critical success factors of project management: The case of construction related projects in vietnam. Journal of Asian Finance, Economics and Business, 6(2), 223-230. https://doi.org/10.13106/jafeb.2019.vol6.no2.223   DOI
28 Phan, P. T., Nguyen, P. T., & Nguyen, L. T. (2020). Project manager selection using the evaluation based on distance from average solution approach. International Journal of Disaster Recovery and Business Continuity, 11(1), 364-372.
29 Phong, N. T., Likhitruangsilp, V., & Onishi, M. (2017). Developing a stochastic traffic volume prediction model for public-private partnership projects. In: AIP Conference Proceedings 1903. 060010 (2017). https://doi.org/10.1063/1.5011564
30 Ramabodu, M. S., & Verster, J. J. P. (2013). Factors that influence cost overruns in south african public sector mega-projects. International Journal of Project Organisation and Management, 5(1-2), 48-56. https://doi.org/10.1504/IJPOM.2013.053153   DOI
31 Sy, D. T., Likhitruangsilp, V., Onishi, M., & Nguyen, P. T. (2017). Impacts of risk factors on the performance of public-private partnership transportation projects in vietnam. ASEAN Engineering Journal, 7(2), 30-52.   DOI
32 Tu, M. T. C., & Giang, H. T. T. (2018). Estimating the impact of trade cost on export: A case study vietnam. Journal of Asian Finance, Economics and Business, 5(3), 43-50. https://doi.org/10.13106/jafeb.2018.vol5.no3.43   DOI