Developing Crew Synchronization System for Repetitive Units  

Lee, Hong-Chul (경북대학교 건설환경에너지공학부 대학원)
Park, Sang-Min (경북대학교 건설환경에너지공학부 대학원)
Lee, Dong-Eun (경북대학교 건축 토목공학부)
Publication Information
Journal of the Architectural Institute of Korea Structure & Construction / v.30, no.12, 2014 , pp. 45-52 More about this Journal
Abstract
Repetitive project planning and scheduling method requires complementing the disadvantages of the critical path method (CPM) and the line of balance (LOB) method, which are confined in time-driven and graphical analysis, respectively. CPM is lack of capability to handle repetitive projects. LOB is also lack of analytical qualities of schedule information due to its' dependency on graphical technique. Existing studies attempt to combine CPM and LOB techniques in a system. However, they are mostly graphical methods. A new method integrating CPM and LOB techniques is presented so as to schedule repetitive projects using formula computing schedule information of each and every units of a project schedule. The proposed method perform basic LOB calculations to ensure resource employment continuity. Each and every activity durations at all units, floats and project completion time are computed using CPM method. Test cases are conducted to verify the potential of the proposed method.
Keywords
Repetitive project; Scheduling; CPM; LOB;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 류한국, 김태희, 선형 공정계획 모델의 액티비티 관계의 경계조건 분석, 한국건설관리학회논문집, 12(1), 23-32, 2011   과학기술학회마을   DOI   ScienceOn
2 류한국, 장명훈, CPM공정표를 선형 공정표로 변환하기 위한 액티비티 생성 방법, 대한건축학회논문집 - 구조계, 27(10), 161-168, 2011
3 이재섭, 선형계획법을 이용한 건설공사 공기지연 분석방법, 대한건축학회논문집 - 구조계, 23(8), 213-220, 2007   과학기술학회마을
4 이재섭, 학습효과와 선형계획법을 이용한 건설공사 공기지연 분석방법, 대한건축학회논문집 - 구조계, 24(5), 185-192, 2008   과학기술학회마을
5 Ammar, M., Float analysis of non-serial repetitive activities, Journal of Construction Management and Economics, 21(5), 535-542, 2003   DOI   ScienceOn
6 Ammar, M. and Mohieldin, Y., CPM/RSM: CPM-Based repetitive scheduling method III, Middle East Regional Civil Engineering Conference, Egypt Section, ASCE, Reston, VA, 2002
7 Arditi, D. and Albulak, M., Line-of-balance in pavement construction, Journal of Construction Engineering and Management, 112(3), 411-424, 1986   DOI   ScienceOn
8 Duffy, G., Oberlender, G. and Jeong, D., Linear scheduling model with varying production rates, Journal of Construction Engineering and Management, 137(8), 574-582, 2011   DOI   ScienceOn
9 El-Rayes, K. and Moselhi, O., Resource-driven scheduling of repetitive projects, Construction Management and Economics, 16(4), 433-446, 1998   DOI
10 Fan, S. and Tserng, H., Object-oriented scheduling for repetitive projects with soft logics, Journal of Construction Engineering and Management, 132(1), 35-48, 2006   DOI   ScienceOn
11 Hegazy, T., Computer-based construction project management, Prentice Hall, Upper Saddle River, NJ, 2002
12 Hegazy, T. and Kamarah, E., Efficient repetitive scheduling for high-rise construction, Journal of Construction Engineering and Management, 134(4), 253-264, 2008   DOI   ScienceOn
13 Hegazy, T. and Wassef, N., Cost optimization in projects with repetitive nonserial activities, Journal of Construction Engineering and Management, 127(3), 183-191, 2001   DOI   ScienceOn
14 Jaafari, A., Criticism of CPM for project planning analysis, Journal of Construction Engineering and Management, 110(2), 222-233, 1984   DOI   ScienceOn
15 Lucko, G., Productivity scheduling method compared to linear and repetitive project scheduling methods, Journal of Construction Engineering and Management, 134(9), 711-720, 2008   DOI   ScienceOn
16 Lucko, G. and Orozco, A., Float types in linear schedule analysis with singularity functions, Journal of Construction Engineering and Management, 135(5), 368-377, 2009   DOI
17 Maravas, A. and Pantouvakis, J., A fuzzy repetitive scheduling method for projects with repeating activities, Journal of Construction Engineering and Management, 137(7), 561-564, 2011   DOI   ScienceOn
18 Mattila, K. and Abraham, D., Resource leveling of linear schedules using integer linear programming, Journal of Construction Engineering and Management, 124(3), 232-244, 1998   DOI   ScienceOn
19 Reda, R., RPM: Repetitive project modeling, Journal of Construction Engineering and Management, 116(2), 316-330, 1990   DOI
20 Russel, A. and Wong, W., New generation of planning structures, Journal of Construction Engineering and Management, 119(2), 196-214, 1993   DOI   ScienceOn
21 Selinger, S., Construction planning for linear projects, Journal of the Construction Division, 106(2), 195-205, 1980
22 Yang, T. and Ioannou, P., Scheduling system with focus on practical concerns in repetitive projects, Journal of Construction Engineering and Management, 22(6), 619-630, 2004   DOI
23 Strdal, O. and Cacha, J., Time space scheduling method, Journal of the Construction Division, 108(3), 445-457, 1982
24 Suhail, S. and Neale, R., CPM/LOB: New methodology to integrate CPM and line of balance, Journal of Construction Engineering and Management, 120(3), 667-684, 1994   DOI   ScienceOn