Precast concrete walls can be one of solutions to quickly build the core structure in modular buildings. The horizontal connection of PC load-bearing wall requires vertical continuity across joints to acquire the strength and stability of the structure. To achieve continuity, the horizontal joints are designed as an emulative connection which performs similarly to monolithic wall of cast-in-place structure. A common method of emulative detailing in the horizontal connection between PC walls is the use of splice sleeve, known as mechanical splices. In this study, the wall shoe, a temporary connector, which is necessary for construction safety when assembling PC walls and the splice sleeves that is able to secure vertical continuity are investigated experimentally in consideration of field conditions, and compared with the strength according to structural design codes.

키워드

과제정보

이 연구는 2020년도 국토교통과학기술진흥원(20RERP-B082884-7)의 연구비 지원에 의한 결과의 일부임.

참고문헌

  1. ACI Innovation Task Group 5 (2007). Acceptance Criteria for Special Unbonded Post-Tensioned Precast Structural Walls Based on Validation Testing (ACI ITG-5.1-07) and Commentary. American Concrete Institute, USA.
  2. Architectural Institute of Korea (2016). Korea Building Code (KBC2016 / KBC2009), Seoul, Korea.
  3. Kang, S.M., Oh, J.K., Kim, O.J., Lee, D.B., & Park, H. G. (2010). Development of a Precast Concrete Structural Wall Adopting Improved Connections in the Plastic Hinge Region, Journal of the Korea Concrete Institute, 14(2), 15-26.
  4. Kim, S.K., Seo, S.Y., Kim, S.H., Lim, B.H., & Cha, J. W. (2019). Hysteretic Characteristic of Precast Concrete Wall with Box Type Connector for Vertical Bars under Horizontal Load, Journal of the Korea Concrete Institute, 31(2), 153-163. https://doi.org/10.4334/jkci.2019.31.2.153
  5. Kim, S.K., Seo, S.Y., Lim, B.H., Kim, S.H., Woo, J.W. & Cha, J.W. (2017). Structural Performance of Precast Concrete Horizontal Joint Connected Vertically by Corrugate Pipe Joint Method, Proceedings of Autumn Conference of the Architectural Institute of Korea, 37(2), 683-686.
  6. Kim, M.S., Kim, M.J., Lee, Y.H., Kim, H.C., & Kim, K.S. (2010). Experimental Study on Structural Performance of Joints for Precast Concrete Segment under Cyclic Lateral Loading, Journal of the Architectural Institute of Korea, Structure and Construction Section, 26(12), 65-72.
  7. Lim, W.Y., & Hong, S.G. (2014). Seismic Performance of T-Shaped PC Walls with Wet Cast Joint, Journal of the Korea Concrete Institute, 26(3), 255-266. https://doi.org/10.4334/JKCI.2014.26.3.255
  8. Ling, J.H., Ahmad, A.B., & Ibrahim, I.S. (2014). Feasibility study of grouted splice connector under tensile load. Construction and Building Materials, 50, 530-539. https://doi.org/10.1016/j.conbuildmat.2013.10.010
  9. Oh, Y.H., & Moon, J.H. (2013). Analytical and Experimental Studies on Splice Sleeves for SD500 Rebars, Journal of the Korea Concrete Institute, 25(2), 165-173. https://doi.org/10.4334/JKCI.2013.25.2.165
  10. Seifi, P., Henry, R.S., & Ingham, J.M. (2019). In-plane cyclic testing of precast concrete wall panels with grouted metal duct base connections, Engineering Structures, 184, 85-98. https://doi.org/10.1016/j.engstruct.2019.01.079
  11. Singhal, S., Chourasia, A., Chellappa, S., & Parashar J. (2019). Precast reinforced concrete shear walls: State of the art review, Structural Concrete, 20, 886-898. https://doi.org/10.1002/suco.201800129
  12. Tolsma K.V. (2010). Precast concrete cores in high-rise buildings, Master Thesis, Delft University of Technology.
  13. Zhi, Q., Song, J., & Guo, Z. (2015). Experimental study on behavior of precast shear wall using post-cast at the connection, International Conference on Civil Engineering and Transportation (ICCET2015), 1089-1092.