A New Quantification Method for Multi-Unit Probabilistic Safety Assessment

다수기 PSA 수행을 위한 새로운 정량화 방법

  • 박성규 ((주)액트 원전안전성평가센터) ;
  • 정우식 (세종대학교 원자력공학과)
  • Received : 2019.10.18
  • Accepted : 2020.02.04
  • Published : 2020.02.29

Abstract

The objective of this paper is to suggest a new quantification method for multi-unit probabilistic safety assessment (PSA) that removes the overestimation error caused by the existing delete-term approximation (DTA) based quantification method. So far, for the actual plant PSA model quantification, a fault tree with negates have been solved by the DTA method. It is well known that the DTA method induces overestimated core damage frequency (CDF) of nuclear power plant (NPP). If a PSA fault tree has negates and non-rare events, the overestimation in CDF drastically increases. Since multi-unit seismic PSA model has plant level negates and many non-rare events in the fault tree, it should be very carefully quantified in order to avoid CDF overestimation. Multi-unit PSA fault tree has normal gates and negates that represent each NPP status. The NPP status means core damage or non-core damage state of individual NPPs. The non-core damage state of a NPP is modeled in the fault tree by using a negate (a NOT gate). Authors reviewed and compared (1) quantification methods that generate exact or approximate Boolean solutions from a fault tree, (2) DTA method generating approximate Boolean solution by solving negates in a fault tree, and (3) probability calculation methods from the Boolean solutions generated by exact quantification methods or DTA method. Based on the review and comparison, a new intersection removal by probability (IRBP) method is suggested in this study for the multi-unit PSA. If the IRBP method is adopted, multi-unit PSA fault tree can be quantified without the overestimation error that is caused by the direct application of DTA method. That is, the extremely overestimated CDF can be avoided and accurate CDF can be calculated by using the IRBP method. The accuracy of the IRBP method was validated by simple multi-unit PSA models. The necessity of the IRBP method was demonstrated by the actual plant multi-unit seismic PSA models.

Keywords

References

  1. C.E. Shannon, "The Synthesis of Two-terminal Switching Ccircuits", Bell System Technical Journal, Vol. 28, pp. 59-98, 1948. https://doi.org/10.1002/j.1538-7305.1949.tb03624.x
  2. C.H. Roth Jr. and L. L. Kinney, Fundamentals of Logic Design, Seventh Edition, 2014.
  3. EPRI, Direct Probability Calculator (DPC) Version 4.0, Product ID # 1019191, 2009.
  4. S. Epstein and A. Rauzy, "Can We Trust PRA?", Reliability Engineering & System Safety, Vol. 88, pp. 195-205, 2005. https://doi.org/10.1016/j.ress.2004.07.013
  5. A. Rauzy, "New Algorithms for Fault Tree Analysis", Reliability Engineering and System Safety, Vol. 40, pp. 203-211, 1993. https://doi.org/10.1016/0951-8320(93)90060-C
  6. W. S. Jung, "A Fast BDD Algorithm for Large Coherent Fault Trees Analysis", Reliability Engineering and System Safety, Vol. 83, pp. 369-374, 2004. https://doi.org/10.1016/j.ress.2003.10.009
  7. W. S. Jung, S. H. Han and J. E. Yang, "Fast BDD Truncation Method for Efficient Top Event Probability Calculation", Nuclear Engineering and Technology, Vol. 40, pp. 571-580, 2008. https://doi.org/10.5516/NET.2008.40.7.571
  8. EPRI, FTREX 1.9 Software Manual, Product ID # 3002012968, 2018.
  9. W. S. Jung, "A Method to Improve Cutset Probability Calculation in Probabilistic Safety Assessment of Nuclear Power Plants", Reliability Engineering and System Safety, Vol. 134, pp. 134-142, 2015. https://doi.org/10.1016/j.ress.2014.10.019
  10. W.S. Jung, BeEAST 1.1 User Manual, 2015.
  11. EPRI, Advanced Cutset Upper Bound Estimator(TM) (ACUBE), Version 1.0, Test Report, Product ID #1024896, 2012.