A Review of Plugging Limit for Steam Generator Tubes in Nuclear Power Plants

원전 증기발생기 전열관 관막음 한계 고찰

  • 강용석 (한국수력원자력(주) 중앙연구원) ;
  • 이국희 (한수원중앙연구원)
  • Received : 2020.09.10
  • Accepted : 2020.10.29
  • Published : 2020.12.30

Abstract

Securing the integrity of steam generator tubes is an essential requirement for safe operation of nuclear power plants. Therefore, tubes that do not satisfy integrity requirements are no longer usable and must be repaired according to the related requirements. In general, the repair criterion is that the damage depth is more than 40% of the tube wall thickness. However, the plugging limit can be changed and be applied, provided a technical proof is given that integrity can be secured against specific degradation at a specific plants and that approval can be obtained from a regulatory agency. A typical example is alternative repair criteria for defects within the tube sheet or tube support plates. In this paper, a background of establishing the plugging limit for steam generator tubes and changes in maintenance criteria are reviewed as examples.

Keywords

References

  1. ASME BPVC Sec. III, 2013, "Rules for Construction of Nuclear Power Plant Components", American Society of Mechanical Engineers, NY.
  2. Lee, C. H., 1991, "Allowable Tube Wall Degradation Analysis", Cal No. 10287-SS-902, ABB Combustion Engineering Nuclear Power.
  3. SGMP: Steam Generator Integrity Assessment Guidelines: Revision 4. EPRI, Palo Alto, CA:2016. 3002007571.
  4. NEI 97-06, 2001, "Steam Generator Program Guidelines, Revision 1", Nuclear Energy Institute.
  5. Fuller, E., Cipolla, R. C., Reinhardt, W. D., Zhao, Z. F., Begley, J. A., Costa, D. E., Ayres, D. J., Keating, R.F. and Lagally, H.O., "Impacts of the Structural Integrity Performance Criterion on Steam Generator Tube Integrity Evaluations", EPRI, Palo Alto, CA:2004. 1009541.
  6. Reg. Guide 1.121, 1976, "Bases for Plugging Degraded PWR Steam Generator Tubes", U.S. Nuclear Regulatory Commission, Washington, D.C.
  7. Krzywosez, K., "Balance-of-Plant Heat Exchanger Condition Assessment and Inspection Guide", EPRI, Charlotte, NC:1999. TR-108009, pp. 7-1.
  8. ASME BPVC Sec. XI, 2015, "Rules for Inservice Inspection of Nuclear Power Plant Components", American Society of Mechanical Engineers, NY.
  9. KHNP, 2011, Integrated Technical Specifications Kori Units 3,4 Revision 452, "4.19 Steam Generator Program", pp. 4.0-21.
  10. KHNP, 2011, Integrated Technical Specifications Hanbit Units 5,6 Revision 154, "4.19 Steam Generator Program", pp. 4.0-21.
  11. EPRI SGMP Website : www.epri.com
  12. USNRC Generic Letter 95-05, 1995, "Voltage-Based Repair Criteria for Westinghouse Steam Generator Tubes Affected by Outside Diameter Stress Corrosion Cracking", U.S. Nuclear Regulatory Commission, Washington, D.C.
  13. Cothron, H., Steam Generator Tubing Diameter Stress Corrosion Cracking at Tube Support Plates Database for Alternate Repair Limits: Addendum 7, EPRI, Palo Alto, CA: 2008. 1018047.
  14. Smith, J. D., 2008, "Sequoyah Nuclear Plant (SQN)-Unit2-2Cycle 15(U2C15) 90-day Steam Generator (SG) Report for Voltage-Based Alternate Repair Criteria(ARC) and W* Alternate Repair Criteria", US ADAMS Accession No. ML 082480690.
  15. Srikantiah, G., Pitterle, T. A., Keating, R. F. and Srinivas. V., 1998, "Steam Generator Tubing Outside Diameter Stress Corrosion Cracking at Tube Support Plates Database for Alternate Repair Limits", NP 7480-L, EPRI, Palo Alto.
  16. Blandford, E., Pitterle, T. and Keating, R., 2005, "Steam Generator Tubing Outside Diameter Stress Corrosion Cracking at Tube Support Plates Database for Alternate Repair Limits: Update 2004", EPRI, Palo Alto, CA:2005. 1011456.
  17. EPRI, 1994, Steam Generator Reference Book Vol. I, TR-103824a-V1R1, pp. 8-2-8-4.
  18. Pitterle, T. A., Keating R. F., Pierini, G. P., Malinowski, D. D., Cullen, W. K., Lilly, G. P., Sagar, A., Pierini, G. P., Begley, J. A. and Arhar, J. H., 2001, "Depth-Based SG Tube Repair Criteria for Axial PWSCC at Dented TSP Intersections-Alternate Burst Pressure Calculation", Westinghouse Electric Company LLC, PA, WCAP-15574 Revision 1, pp. 2-1-2-10.
  19. USNRC GL 2004-1, 2004, "Requirements for Steam Generator Tube Inspections", US ADAMS Accession No. ML042370766.
  20. Cassino, C. D., Lagally H. O., Whiteman, G. W., 2009, "H*: Alternate Repair Criteria for the Tubesheet Expansion Region in Steam Generators with Hydraulic Expanded Tubes(Model F)", Westinghouse Electric Company LLC, PA, WCAP-17071-NP Revision 0, US ADAMS Accession No. ML093620086.
  21. Magee, T. P., Nelson, P. R., Bell, B. A. and Coe, K. E., 2005, "NDE Inspection Length for CE Steam Generator Tubesheet Region Explosive Expansions", Westinghouse Electric Company LLC, PA, WCAP-16208-NP Revision 1, US ADAMS Accession No. 051520417.
  22. USNRC, 2012, "Catawba Nuclear Station Unit 1 and 2, Issuance of Amendments Regrading Technical Specifications Amendments for Permanent Alternate Repair Criteria for Steam Generator Tubes(TAC NOS. ME6670 and ME6671)", US ADAMS Accession No. 12054A692.
  23. C. B. Bahn, S. Majumdar, K. E. Kasza, and W. J. Shack, "Leak Behaviors of Steam Generator Tube-to-Tubesheet Joints from Room Temperature to 320℃", Int. J. Pressure Vessels Piping, 101 (2013) 45-54. https://doi.org/10.1016/j.ijpvp.2012.10.003
  24. C. B. Bahn, S. Majumdar, K. E. Kasza, and W. J. Shack, "Leak Behavior of Steam Generator Tube-to-Tubesheet Joints under Creep Condition: Experimental Study", Int. J. Pressure Vessels Piping, 101 (2013) 55-63. https://doi.org/10.1016/j.ijpvp.2012.10.002