Development of Dynamic Model of 680 MW Rated Steam Turbine and Verification and Validation of its Speed Controller

680 MW 증기터빈 동적모델 개발 및 속도제어기 검증

  • Choi, Inkyu (KEPCO Research Institute, Korea Electric Power Corporation) ;
  • Woo, Joohee (KEPCO Research Institute, Korea Electric Power Corporation) ;
  • Son, Gihun (Department of Mechanical Engineering, Sogang University)
  • Received : 2019.09.05
  • Accepted : 2019.10.04
  • Published : 2019.09.30

Abstract

The steam turbine used in nuclear power plant is modeled for the purpose of verification of control system rather than the operator education. The valves, reheater and generator are modeled also and integrated into the simulator. After that, the operation data and the designed data such as heat balance diagram are utilized to identify the model parameters. It was evident that model outputs of developed simulator are very close to the measured operating ones. The simulator within dynamic model was used to verify and validate the whole control system together with field instruments. And the target plant has been operating long time.

Keywords

References

  1. Ali Chaibakhsh, Ali Ghaffari, "Simulation Modelling Practice and Theory," 16 (2008) 1145.1162, 2008.
  2. M. Nagpal, A. Moshref, G.K. Morison, P. Kundur, "Experience with testing and modeling of gas turbines," IEEE Power Engineering Society Winter Meeting, 2 (2001) 652.656, 2001.
  3. M. Wang, N.F. Thornhill, B. Huang, "Closed-loop identification with a quantizer," Journal of Process Control 15 (2005) 729.740, 2005. https://doi.org/10.1016/j.jprocont.2004.10.007
  4. D. W. Kim, C. Youn, B.-H. Cho and G. Son, "Development of a power plant simulation tool with GUI based on general purpose design software," International Journal of Control, Automation, and Systems, vol. 3, no. 3, pp. 493-501, 2005.
  5. A. Stodola, Steam and Gas Turbine, vol. 1, Peter Smith, New York, 1945.