Schedule Optimization in Resource Leveling through Open BIM Based Computer Simulations

  • 김현주 (서울시립대학교 국제도시과학대학원)
  • Received : 2019.02.22
  • Accepted : 2019.03.29
  • Published : 2019.06.30

Abstract

In this research, schedule optimization is defined as balancing the number of workers while keeping the demand and needs of the project resources, creating the perfect schedule for each activity. Therefore, when one optimizes a schedule, multiple potentials of schedule changes are assessed to get an instant view of changes that avoid any over and under staffing while maximizing productivity levels for the available labor cost. Optimizing the number of workers in the scheduling process is not a simple task since it usually involves many different factors to be considered such as the development of quantity take-offs, cost estimating, scheduling, direct/indirect costs, and borrowing costs in cash flow while each factor affecting the others simultaneously. That is why the optimization process usually requires complex computational simulations/modeling. This research attempts to find an optimal selection of daily maximum workers in a project while considering the impacts of other factors at the same time through OPEN BIM based multiple computer simulations in resource leveling. This paper integrates several different processes such as quantity take-offs, cost estimating, and scheduling processes through computer aided simulations and prediction in generating/comparing different outcomes of each process. To achieve interoperability among different simulation processes, this research utilized data exchanges supported by building SMART-IFC effort in automating the data extraction and retrieval. Numerous computer simulations were run, which included necessary aspects of construction scheduling, to produce sufficient alternatives for a given project.

Keywords

References

  1. BuildingSMART. "IFC Overview Summary", Welcome to BuildingSMART-Tech.org. Web. 05 Dec. 2011.
  2. Castro-Lacouture, D., S er, G., Gonzalez-Joaqui, J., Yates, J.K. (2009). Construction Project Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical Models and Critical Path Method, Journal of Construction Engineering Management, 135(10), pp. 1096-1104. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:10(1096)
  3. Hariga, M., El-Sayegh, S. (2010). Cost Optimization Model for the Multiresource Leveling Problem with Allowed Activity Splitting, Journal of construction engineering and management, 137(1), 56-64. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000251
  4. Lee, G., Won, J., Ham, S., Shin, Y. (2011). Metrics for Quantif ying the Similarities and Differences between IFC Files, ASCE Journal of Computing in Civil Engineering, 25(2), pp. 172-181. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000077
  5. Eastman, C. M., Jeong, Y. S., Sacks, R., Kaner, I. (2010). Exchange Model and Exchange Object Concepts for Implementation of National BIM Standards, ASCE Journal of Computing in Civil Engineering, 24(1), pp. 25-34. https://doi.org/10.1061/(ASCE)0887-3801(2010)24:1(25)
  6. Hegazy, T., Ersahin, T. (2001). Simplified Spreadsheet Solutions. II: Overall Schedule Optimization, ASCE Journal of Construction Engineering and Management, 127(6), pp. 469-475. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:6(469)
  7. Ibbs, W., Nguyen, L. (2007). Schedule Analysis under the Effect of Resource Leveling. Journal of construction engineering and management, 133(2), pp. 131-138. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:2(131)
  8. Jiang, G., Shi, J. (2005). Exact Algorithm for Solving Project Scheduling Problems under Multiple Resource Constraints, Journal of construction engineering and management, 131(9), pp. 986-992. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:9(986)
  9. Kim, H., Anderson, K., Lee, S., Hildreth, J. (2013). Generating construction schedules through automatic data extraction using OPEN BIM (building information modeling) technology, Automation in Construction.
  10. Perdomo-Rivera, J. L. (2004). A Framework for a Decision Support Model for Supply Chain Management in the Construction Industry, Ph.D. dissertation, Virginia Polytechnic Institute & State University.
  11. Sol, S. "XML Advantages & Disadvantages", The UK Web Design Company. Web. 05 Dec. 2011.