Delay Factors in Building Construction Projects in Rwanda

  • Received : 2019.08.14
  • Accepted : 2019.10.10
  • Published : 2019.10.20

Abstract

Delay is one of the most critical issues for construction projects and leads to huge losses in both developing and industrialized countries. The construction sector in Rwanda, a rapidly-developing nation, is no exception. Delays can be mitigated only once we have identify their primary causes, and these may not be the same in each region. This study aims to ascertain the main critical factors responsible for delays in building construction in Rwanda through an intensive literature review and questionnaire survey. A total of 40 delay causative factors were obtained from a literature review and were further classified into nine major categories. The questionnaire survey was distributed to about 80 respondents from clients, contractors, and consultants. From the list of 40 different factors, the top twelve most critical causes were identified as stoppage of work due to cash flow constraints, delay in approving design documents, confidentiality of physical plan, price fluctuations and delay in approving significant change, change orders, delay in performing inspections, Ineffective project planning, inadequate drawing details, unqualified labor, lack of materials on the market and dishonesty.

Keywords

References

  1. Aynur K, Serdar U, Nihan AT. Causes of delays in construction projects in Turkey. Journal of Civil Engineering and Management. 2012 Jun;18(3):426-35. https://doi.org/10.3846/13923730.2012.698913
  2. Kim DY, Chi SH. Causes of schedule delays in building construction projects in vanuatu. Korea Institute of Building Construction. 2015 Jun;15(6):641-51. https://doi.org/10.5345/JKIBC.2015.15.6.641
  3. Long LH, Young DL, Jun YL. Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering. 2008 Jul;12(6):367-77. https://doi.org/10.1007/s12205-008-0367-7
  4. Sambasivan M, Soon WY. Causes and effects of delays in Malaysian construction industry. International Journal of Project Management. 2007 Jul;25(5):517-26. https://doi.org/10.1016/j.ijproman.2006.11.007
  5. Opportunities in the construction industry in Rwanda[Internet]. Business Sweden in Eastern Africa,2017[Cited: 2017 April 21]. Available from: https://www.businessSweden.Se/Contentassets/46366e8d9f584bf495f139ae7f2020d7/factpack-construction-industry-in-rwanda-2017.pdf.
  6. Amandin MM, Julius WK. Project construction projects Kigali. ABC Journal of Advanced Research. 2006;5(1):21-34. https://doi.org/10.18034/abcjar.v5i1.55
  7. Ndundo FN, Mbabazi M, Jaya S, Ephantus NW. Institutional factors influencing timely completion of road project in Rwanda: Case of Government Externally Financed Projects. European Journal of Business and Social Sciences. 2016 Apr;5(01):146-59.
  8. Report of the auditor of state finances for the year ended 30 June 2017. Rwanda: Office of the auditor general of state finances, 2017 [Cited: 2018April20]. Available from:wwwoag.gov.rw/fileadmin/user-upload/Financialreports/AnnualReport-june-2017-ExecutieSummary.pdf
  9. The world bank. Project information documents/integrated safeguards datasheet(PID/ISDS). Rwanda affordable housing finance project, 2018. [Cited:2018 Sept 18]. Available from: documents.Worldbank.org/curated/en/33851153767763132/pdf/Project-Information-Document-Integrated-Safeguards-Data-Sheet-Rwanda-Housing-Finance-Project-P165649.pdf
  10. Kenny W, Vanissorn V. A study of the factors affecting construction time in western Australia. Scientific Research and Essays. 2012 Oct;7(40):3390-8. https://doi.org/10.5897/SRE12.138
  11. Fugar FDK, Agyakwah-Baah AB. Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building. 2010 Jul;10(1/2):103-16. https://doi.org/10.5130/AJCEB.v10i1-2.1592
  12. Muhwezi L, Acai J, Otim G. An assessment of the factors causing delays on building construction projects in Uganda. International Journal of Construction Engineering and Management. 2014 Mar;3(1):13-23. https://doi.org/10.5923/j.ijcem.20140301.02
  13. Geraldine K. Causes and effects of delays and disruptions in construction projects in tanzania. Australasian Journal of Construction Economics and Building Conference Series. 2012;1(2):52-9. https://doi.org/10.5130/ajceb-cs.v1i2.3166
  14. Odeyinka AH, Yusif A. The causes and effects of construction delays on completion cost of housing projects in Nigeria. Journal of Financial Management of Property and Construction. 1997 Jan;2(3):31-44.
  15. Durdyev S, Omarov M, Ismail SOM. Causes of delay in residential construction projects in Cambodia. Cogent Engineering. 2017 Feb;4(1):1-12. https://doi.org/10.1080/23311916.2017.1291117
  16. Pourrostam T, Ismail A. Causes and effects of delay in Iranian construction projects. International Journal of Engineering and Technology. 2012 Oct;4(5):598-601. https://doi.org/10.7763/IJET.2012.V4.441
  17. Arya A, Kansal R. Analyzing delays of construction projects in India: Causes and effects. IJSTE International Journal of Science Technology and Engineering. 2016 Dec;3(6):66-74.
  18. Ahmed SM, Azher S, Castillo M, Kappagantula P. Construction delays in Florida: An empirical study. Miami: Florida International University (US); 2002. 44 p. Report No.: CEAS2952
  19. Balduin JR, Manthei JM , Rothbart H , Harris RB. Causes of delay in the construction industry. Journal of the construction Engineering Division .1971;97(2):177-87. https://doi.org/10.1061/JCCEAZ.0000305
  20. Zidane JTY, Andersen B. Causes of delay and their cures in major Norwegian projects. Journal of Modern Project Management. 2018 5(3);80-91.
  21. Elhag TMS, Boussabaine AH. Evaluation of construction cost and time attributes. 15th Annual ARCOM Conference; 1999 Sep 15-17; Liverpool John Moores University, UK. Reading(UK): Association of Researchers in Construction Management; 1999. p. 473-80.
  22. Chan DWM, Kumaraswamy MM. Compresing construction durations: Lessons learned from Hong Kong building projects. International Journal of Project Management. 2002 Jan;20(1):23-35. https://doi.org/10.1016/S0263-7863(00)00032-6
  23. Adel AK, Martin S. Causes of Delays in Saudi Arabian Public Sector Construction Projects. Construction Management and Economics. 2009;27(1):23-35.
  24. Bekithemba M, Eduard GO, Cletus M, Adrian P. Profiling causative factors leading to construction project delays in the United Arab Emirates. Journal of Engineering Construction and Architectural Management. 2017 Mar;24(2):346-76. https://doi.org/10.1108/ECAM-05-2015-0072
  25. Kenny, Vanissorn. A study of the factors affecting construction time in western Australia. Scientific Research and Essays. 2012 Oct;7(40):3390-8. https://doi.org/10.5897/SRE12.138
  26. Gasasira I, Peter M, Eugene N. The causative factor leading to cost overrun in dam construction project in Rwanda: Case study Kinoni 1 dam construction project. European Journal of Business and Social Sciences. 2016 Feb;4(11):142-68.
  27. Walewski JA. International Project Risk Assessment (IPRA), [dissertation]. [Austin (Texas)]: The University of Texas at Austin; 2005. 388 p.
  28. An SH, Lee YN, Jo HK. A study on the risk assessment methodology and application for international plants construction. Journal of Korean Institute of Construction Engineering and Management. 2007 Oct;9(1):134-42.