Figure 1. Research procedure
Figure 2. Histogram and normal Q-Q plot for dependent value
Figure 3. Histogram and normal Q-Q plot for transformed dependent value
Table 1. Study method and applicable phase of previous studies
Table 2. Causes of plant construction project losses
Table 3. Total/average claim payouts by loss causes
Table 4. Claim payout and frequency by construction phase
Table 5. Claim payout and frequency by schedule rate
Table 6. Claim payout and frequency by landform
Table 7. Claim payout and frequency by total cost
Table 8. Claim payout and frequency by total duration
Table 9. Normality test of transformed dependent value
Table 10. Normality test of dependent value
Table 11. Categories of independent values
Table 12. Descriptive statistics
Table 13. ANOVA and adjusted R square
Table 14. Coefficients
References
- Yun JY. A study on the international competitiveness of korean plant industries [Master's thesis]. Jeonju (Korea): Chonbuk National University; 2011. 124 p.
- A Guideline of Risk Analysis method, X-19-2012 [Internet]. Ulsan(Korea) : Korea Occupational Safety and Health Agency.2012 [cited 2012. June 20]. Available from: http://www1.kosha.or.kr/kosha/media/guidance_X.do?mode=download&articleNo=103308&attachNo=87020
- Mulholland B, Christian J. Risk assessment in construction schedules. Journal of Construction Engineering and Management. 1999 Jan;125(1):8-15. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:1(8)
- Carr V, Tah JH. A fuzzy approach to construction project risk assessment and analysis: construction project risk management system. Advances in Engineering Software. 2001 Oct;32(10-11):847-57. https://doi.org/10.1016/S0965-9978(01)00036-9
- Hsiau HJ, Lin CW. A fuzzy pert approach to evaluate plant construction project scheduling risk under uncertain resources capacity. Journal of Industrial Engineering and Management. 2009 Jul;2(1):31-47.
- Heravi G, Gholami A. The influence of project risk management maturity and organizational learning on the success of power plant construction projects. Project Management Journal. 2018 Aug;49(5):22-37 https://doi.org/10.1177/8756972818786661
- An SH, Lee YN, Jo HK. A study on the risk assessment methodology and application for international plants construction. Korean Journal of Construction Engineering and Management. 2008 Feb;9(1):134-42.
- Kang HW, Min BJ, Kim YS. A study on the costs variation range through the risk factors for overseas plant projects. Journal of the Architectural Institute of Korea. 2010 Jul;26(7):139-47.
- Lee K, Choi J. Project risk assessment through construction sequence analyses for industrial plant construction projects. Korean Journal of Construction Engineering and Management. 2013 Jul;14(4):140-51. https://doi.org/10.6106/KJCEM.2013.14.4.140
- Won SK, Kang M, Lee J, Kim S, Han C. An analysis of procurement processes for the application of system prototype of overseas plant projects. Journal of the Architectural Institute of Korea Structure and Construction. 2008 Feb;24(2):113-21.
- Kim K, Choi B, Chun J. Safety management factor analysis of expert perceptions based on 4m method for plant construction phase. Korean Journal of Construction Engineering and Management. 2016 Jan;17(1):18-27. https://doi.org/10.6106/KJCEM.2016.17.1.018
- Kang HW, Won YM, Kang MK, Kim YS. An analysis on the probability costs variation ranges of the cost items from the risk factor model for construction phase of overseas gas plant projects. Journal of the Architectural Institute of Korea Structure & Construction. 2012 Jan;28(1):191-8. https://doi.org/10.5659/JAIK_SC.2012.28.1.191
- Ji DK, Park MS, Kim YS. Qualitative risk factor analysis of overseas lng plant in operation and management phases. Journal of the Architectural Institute of Korea Structure & Construction. 2014 Aug;30(8):55-62. https://doi.org/10.5659/JAIK_SC.2014.30.8.55
- Wood GD, Ellis RCT. Risk management practices of leading UK cost consultants. Engineering, Construction and Architectural Management. 2003 Aug;10(4):254-62. https://doi.org/10.1108/09699980310489960
- Dikmen I, Birgonul MT, Arikan AE. A critical review of risk management support tools. 20th Annual Conference of Association of Researchers in Construction Management; 2004 Sep 1-3; Edinburgh, UK. Resding (UK): Association of Researchers in Construction Management (ARCOM); 2004. p. 1145-54.
- Cagno E, Caron F, Mancini M. A multi-dimensional analysis of major risks in complex projects. Risk Management. 2007 Feb;9(1):1-18. https://doi.org/10.1057/palgrave.rm.8250014
- Cioffi DF, Khamooshi H. A practical method of determining project risk contingency budgets. Journal of the Operational Research Society. 2009 Apr;60(4):565-71. https://doi.org/10.1057/palgrave.jors.2602586
- Lawry K, Pons DJ. Integrative approach to the plant commissioning process. Journal of Industrial Engineering 2013;2013:1-12. https://doi.org/10.1155/2013/572072
- Ryu HG, Son KY, Kim JM. Loss prediction model for building construction projects using insurance claim payout. Journal of Asian Architecture and Building Engineering. 2016 Jun;15(3):441-6. https://doi.org/10.3130/jaabe.15.441
- Taroun A. Towards a better modelling and assessment of construction risk: Insights from a literature review. International Journal of Project Management. 2014 Jan;32(1):101-15. https://doi.org/10.1016/j.ijproman.2013.03.004