A COMPARATIVE STUDY OF CAUSES AND EFFECTS OF PROJECT DELAYS AND DISRUPTIONS IN CONSTRUCTION PROJECTS IN THE SOUTH AFRICAN CONSTRUCTION INDUSTRY

  • Oshungade, Oluwaseun O. (Oluwaseun Oshungade is with the Postgraduate School of Engineering Management, University of Johannesburg) ;
  • Kruger, Deon (Deon Kruger is with the Department of Civil Engineering Science, University Of Johannesburg)
  • Published : 2017.03.01

Abstract

Construction projects have been observed to have problems of project delays and disruptions and the South African construction industry is not an exception. This research identified causes and effects of project delay and disruption through a desktop study. Subsequently, a questionnaire was designed and used to conduct a survey to obtain the views of the three main construction project participants - clients, consultants, and contractors. The questionnaire contains 48 causes and 13 effects of project delay and disruption identified from the desktop study. This research identified sixteen most important causes of project delay and disruption and five most important effects of delay and disruption. Sixteen most important causes were: (1) strikes, (2) rework due to errors during construction, (3) shortage of materials in market, (4) suspension of work by the client, (5) poor communication between the parties, (6) ineffective planning and scheduling of project, (7) delays in issuing working drawings, (8) mistakes and discrepancies in design documents, (9) shortage of labours and equipment, (10) delay in decision making process by the client, (11) unforeseen ground conditions, (12) unclear and inadequate details in drawing, (13) inadequate contractor's experience, (14) delay in approving changes in the scope of works, (15) delay in material delivery and (16) unacceptable quality of materials. The five major effects include: (1) create stress on contractors, (2) cost overrun, (3) time overrun, (4) poor quality of work due to rush, and (5) disputes. Furthermore, the result of this research was compared with the result of previous studies conducted in other regions of Africa in terms of causes and effects of project delay and disruption. The research concludes that numerous causes and effects of delay and disruption are limited to South African construction projects based on the comparison. The causes limited to South African construction projects include: (1) strikes, (2) suspension of work by the client (3) mistakes and discrepancies in design documents (4) delay in approving changes in the scope of works and (5) unacceptable quality of materials, while the two major effects limited to South African construction projects includes: (1) create stress on contractors and (2) poor quality of work. In conclusion, some recommendations were made in order to minimise the causes of delay and disruption identified.

Keywords

References

  1. B.P. Sunjka, U. Jacob, "Significant causes and effects of project delays in the Niger Delta region, Nigeria," in SAIIE25 proc., Stellenbosch, SA, 2013, pp. 1 - 14.
  2. O. Okeola, "Construction engineering" 2013.
  3. R.N. Nkado, "Competencies Required of Quantity Surveyors," Unpublished MBA research Report, University of the Witwatersrand, Johannesburg, 1999.
  4. City of Johannesburg (CoJ), "2013/14 Group Integrated Annual Report," 2014.
  5. D.W.M. Chan, M.M. Kumaraswamy, "A comparative study of causes of time overruns in Hong Kong construction projects," Int. J. of Project Manage., Vol. 15, No. 1, pp. 55 - 63, 1997. https://doi.org/10.1016/S0263-7863(96)00039-7
  6. G. Sweis, R. Sweis, A. Abu Hammad, A. Shboul, "Delays in construction projects: The case of Jordan," Int. J. of Project Manage., Vol. 26, No. 6, pp. 665 - 674, 2008. https://doi.org/10.1016/j.ijproman.2007.09.009
  7. G. Stumpf, "Schedule delay analysis," Cost Eng. J., Vol. 42, No. 7, pp. 32 - 43, 2000.
  8. G.J. Kikwasi, "Causes and effects of delays and disruptions in construction projects in Tanzania," Australasian J. Construction Econ. and Building, Conf. Series, Vol. 1, No. 2, pp. 52 - 59, 2012.
  9. R.F. Aziz, "Ranking of delay factors in construction projects after Egyptian revolution," Alexandria Eng. J., Vol. 52, pp. 387 - 406, 2013. https://doi.org/10.1016/j.aej.2013.03.002
  10. S.A. Assaf, S. Al-Hejji, "Causes of delay in large construction projects," Int. J. of Project Manage., Vol. 24, pp. 349 - 357, 2006. https://doi.org/10.1016/j.ijproman.2005.11.010
  11. D.W. Bordoli, A.N. Baldwin, "A methodology for assessing construction project delays," Constr. Manage. Econ., Vol. 16, pp. 327 - 337, 1998. https://doi.org/10.1080/014461998372358
  12. S.K. Wei, "Causes, effects and methods of minimizing delays in construction projects: Universiti Teknologi Malaysia, 2010.
  13. S.F. Behboudi, "A model to predict the impact of excusable and non-excusable delay on selected construction projects," AEI, 2008.
  14. M. Mukuka, C. Aigbavboa, W. Thwala, "A theoretical assessment of the causes and effects of construction project delay," in CEE 2013 proc., Johannesburg, SA, 2013, pp. 174 - 177.
  15. N. Hamzah, M.A. Khoiry, I. Arshad, N.M. Tawil, A.I. Che Ani, "Cause of construction delay - theoretical framework," Procedia Eng., Vol. 20, pp. 490 - 495, 2011. https://doi.org/10.1016/j.proeng.2011.11.192
  16. O.E. Akinsiku, A. Akinsulire, "Stakeholders' perception of the causes and effects of construction delays on project delivery," KICEM J. Construction Eng. and Project Manage., Vol. 2, No. 4, pp. 25 - 31, 2012. https://doi.org/10.6106/JCEPM.2012.2.4.025
  17. S.S.S. Gardezi, I.A. Manarvi, S.J.S. Gardezi, "Time extension factors in construction industry of Pakistan," Procedia Engineering, Vol. 77, pp. 196 - 204, 2014. https://doi.org/10.1016/j.proeng.2014.07.022
  18. M.M. Marzouk, T.I. El-Rasas, "Analysing delay causes in Egyptian construction projects," J. of Advanced Research, Vol. 5, pp. 49 - 55, 2014. https://doi.org/10.1016/j.jare.2012.11.005
  19. M.E. Abd El-Razek, H.A. Bassioni, A.M. Mobarak, "Causes of delay in building construction projects in Egypt" J. Constr. Eng. Manage, Vol. 134, No. 11, pp. 831 - 841, 2008. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831)
  20. A.S. Ezeldin, M. Abdel-Ghany, "Causes of construction delays for engineering projects in the Middle-East: An Egyptian perspective" AEI, pp. 53 - 62, 2013.
  21. A.A. Aibinu, H.A. Odeyinka, "Construction delays and their causative factors in Nigeria," J. Construction Eng. and Manage., Vol. 132, No. 7, pp. 667 - 677, 2006. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667)
  22. L. Baloyi, M.C. Bekker, "Causes of construction cost and time overruns: the 2010 FIFA world cup stadia in South Africa," Acta Structilia, Vol. 18, No. 1, pp. 51-67, 2011.
  23. M.A. Nkobane, "Causes of delay and cost overruns in engineering, procurement and construction management projects in South Africa," M.S. thesis, Dept. Eng. Manage., Univ. Johannesburg, Johannesburg, South Africa, 2012.
  24. C. Semple, F.T. Hartman, G. Jergeas, "Construction claims and disputes: causes and cost/time overruns," J. Constr. Eng. Manage., Vol. 120, No. 4, pp. 785 - 795, 1994. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(785)
  25. O. Motaleb, M. Kishk, "An investigation into causes and effects of construction delays in UAE," in Egbu, C. (Ed) Proc. 26th Annual ARCOM Conf., 6-8 September 2010, Leeds, UK, Association of Researchers in Construction Management, 2010, pp. 1149-1157.
  26. A.A. Aibinu, G.O. Jagboro, "The effects of construction delays on project delivery in Nigerian construction industry," Int. J. of Project Manage., Vol. 20, No. 8, pp. 593 - 599, 2002. https://doi.org/10.1016/S0263-7863(02)00028-5
  27. M. Sambasivan, Y.W. Soon, "Causes and effects of delays in Malaysian construction industry," Int. J. of Project Manage., Vol. 25, pp. 517 - 526, 2007. https://doi.org/10.1016/j.ijproman.2006.11.007
  28. A.A. Salunkhe, R.S. Patil, "Effect of construction delays on project time overrun: Indian scenario," Int. J. Research Eng. Tech., Vol. 3, No. 1, pp. 543 - 547, 2014.
  29. StatPac, Survey sampling methods, [online]. Available: https://www.statpac.com/surveys/sampling.htm [Accessed July 06, 2015].
  30. M. Saunders, P. Lewis, A. Thornhill, Research Methods for Business students, 6th ed. England: Pearson Education Limited, 2012.
  31. H. Doloi, A. Sawhney, K.C. Lyer, S. Rentala, "Analysing factors affecting delays in Indian construction projects," Int. J. of Project Manage., Vol. 30, pp. 479 - 489, 2012. https://doi.org/10.1016/j.ijproman.2011.10.004
  32. A. Albogamy, D. Scott, N. Dawood, G. Bekr, "Addressing crucial risk factors in the Middle East construction industries: a comparative study of Saudi Arabia and Jordan," in Sustainable Building Conf. Coventry University, West Midlands, UK, 2013, pp. 118 - 128.
  33. L.T. Van, N.M. Sang, N.T. Viet, "A conceptual model of delay factors affecting government construction projects," ARPN J. Sci. Tech., Vol. 5, No. 2, pp. 92 - 100, 2015.

Cited by

  1. The top 10 universal delay factors in construction projects vol.11, pp.3, 2018, https://doi.org/10.1108/IJMPB-05-2017-0052