Abstract
Although studies evaluating the effects of the blasting vibration on the adjacent structures from various angles have continued, cases of securing the safety of the adjacent buildings and researching the proper blasting method for the field condition by analyzing the vibration waveform of the measuring field while performing the open pit blasting are poor. Therefore, it is necessary to present a remedy for blasting pattern selection through test blasting that is appropriate for field conditions, and is economical and efficient. In this study, open pit blasting work was conducted based on the separation distance applied according to the standard blasting method by test blasting and the vibration regulation standard in the road expansion construction site to measure the blasting vibration value, and the vibration prediction equation by blasting methods was examined using a regression analysis computer program to calculate K, N, and R of the confidence level 95%. By setting the blasting allowed vibration standard of the test blasting target area to 0.3cm/sec, and the charring weight and blasting method by the separation distances according to the blasting vibration estimation equation of the open pit blasting guideline and the blasting vibration estimation equation of the test blasting were compared/analyzed, it was possible to identify the factors that increased the working expenses. In addition, the measurement and analysis of the adjacent structures during open pit blasting and the blasting vibration were performed after selecting the most adjacent structure to the open pit blasting spot to analyze the problems on the test blasting procedure and analysis method in the open pit blasting design/construction guidelines, which appeared in the process of completing open pit blasting construction, and a remedy is presented.
대규모 건설공사 현장에서는 발파공사에 대한 표준발파패턴과 시험발파패턴의 발파진동추정식의 상이에 따른 설계변경의 반영 문제로 시공사, 건설사업관리자, 발주처간의 갈등요인을 해소하기 위한 체계적인 자료의 수집 및 분석 과정을 통하여 효율적인 대책수립이 필요한 실정이다. 발파진동에 의한 인접 구조물에 미치는 영향을 여러 각도로 평가하려는 연구들은 계속 되어 왔으나, 노천발파를 수행하면서 현장계측의 진동파형을 분석하여 인접 건축물의 안전성을 확보하고 현장여건에 적합한 발파공법을 연구한 사례는 미미한 실정이다. 따라서 현장여건에 적합하고 경제적이며 효율적인 발파작업을 수행할 수 있도록 시험발파를 통하여 발파패턴 선정의 개선방안을 제시하는 것이 필요하다. 본 연구에서는 실제 도로확장공사 현장에서 시험발파를 통한 표준발파공법 및 진동규제기준별로 적용되는 이격 거리를 기준으로 노천 발파작업을 수행하여 발파진동 값을 계측하고 이를 통한 발파공법별 진동예측식을 회귀분석 전산프로그램을 이용하여 신뢰수준 95%의 K, n, R등을 산출하였다. 시험발파 대상지역의 발파허용진동기준을 0.3cm/sec로 설정하고 노천발파지침의 발파진동추정식과 시험발파의 발파진동추정식에 따른 이격 거리별 장약량과 발파공법을 비교분석한 결과 사업비가 증가하는 요인을 도출할 수 있었다. 또한, 노천발파 작업 중 인접 구조물에 대한 계측 및 분석을 수행하고 노천발파지점과 가장 인접한 구조물을 선정하여 발파진동 계측 및 평가를 시행하여 노천발파공사를 완료하는 과정에서 나타난 노천발파 설계 시공 지침에서의 시험발파 절차 및 해석방법에 대한 문제점을 분석하여 개선방안을 제시하였다.